RE: Powerhouse site build - video19 Dec 2020 07:29
No it doesn't. Whislt ground works, civil, utilities and general enabling works are going on at site, off site the plant and equipment can be manufactured. Steel structures are put up in days or just weeks dependent on size and equipment delivered to site and installed within a similar time frame. Site acceptance, commissioning and start up doesnt take that long once everythings sited, bolted down, wired in, checked and tested. Something like Protos could literally be built in 9 - 12 months from this point and with good construction planning