RE: Failed Test21 May 2021 11:18
More to the point someone posted this on Tuesday:
"From an earlier RNS - could this be the sticking point and the reason the cessation order has been put in place...
"In order to better inform the FEED study, the joint venture has recently decided to start processing ore from the Potential Site, which has different physical characteristics to the ore previously processed by the POSP. Accordingly, Greenfield has identified certain additional enhancements that are required to be made to the POSP in order to allow for a more efficient and optimised operation, in particular to address issues caused during periods of cold weather, as recently experienced in Utah. Such requirements for additional heating within the process and the inclement weather experienced, have prevented the test production rate of the POSP from reaching the optimised target of 250 bopd per single shift. The additional equipment required to address the aforementioned issues, is now on site and being installed with completion expected shortly after Easter. Greenfield believes that this will then enable the POSP to produce at higher rates of production than achieved to date, particularly during periods of cold weather, and that the oil produced by the POSP will be of a higher overall quality."
This was from the RNS dated 1st April 2021 and I think the important point here is that this clearly stated that " Greenfield has identified certain additional enhancements that are required to be made to the POSP in order to allow for a more efficient and optimised operation, in particular to address issues caused during periods of cold weather, as recently experienced in Utah. Such requirements for additional heating within the process and the inclement weather experienced, have prevented the test production rate of the POSP from reaching the optimised target of 250 bopd per single shift."
So up to this point they have not reached the required target of 250 bopd per single shift - which basically is as good as saying that the test has failed.
In an attempt to still get this seemingly failed test to work they planned to use different ore and to make some "additional enhancements". These enhancements, which were ordered (presumably at TOM'S expense) and on-site on 1st April were intended to be installed "shortly after Easter".
The market was informed that they were installed and tested and operational by 27th April - hardly "just after Easter" which was w/end 3rd/4th April - but maybe the market was just informed late.
Whichever, the enhancements have now been in operation for nearly a month or more but the market still hasn't been informed of any improvements or of the test hitting the required target of 250bopd - and that's without the cold weather interference.
This looks like the Utah DOGM may have saved Greenfield for now as they can use this dispute as an excuse to take another few months trying to hit the elusive 250bopd per single shift.