Prem24 Apr 2023 12:10
Cosmonaut--beg to differ--the minimum rate at 4000 tonnes per month,that is how i am reading it.
"Offset of the Advance Purchase Amount through invoices raised by Suzhou TA&A for shipped SC6 should commence no later than 31 March 2023 at a minimum rate of 4,000 tonnes per month on a rolling average basis plus or minus 10% ("Minimum Delivered Product") following first Concentrate Production ("Supply Commencement Date"). If the Supply Commencement Date does not occur by 31 March 2023 or there is a substantive delay in the subsequent supply of SC6, or there is a shortfall in the Minimum Delivered Amount, then Premier will pay interest to Suzhou TA&A at a reasonable interest rate that represents Suzhou TA&A's actual funding cost for the delay or shortfall.
If the Supply Commencement Date does not occur on or before 30 May 2023, then Suzhou TA&A may terminate and seek repayment of the Advance Purchase Amount. Premier has the right to settle the Advance Purchase Amount at any point."
Acker