This is a material win and should be RNS’ed. Further details of the case copied below from the HY results:
(a) High Court dispute with Vallourec
On behalf of the Group and Tullow's Jubilee field joint venture partners, Tullow Ghana is claiming from Vallourec Oil and Gas France ("Vallourec") losses of approximately £256 million, arising from the supply by Vallourec of defective tubular goods, which Tullow believes constitutes a breach of contract from which Tullow Ghana and the Jubilee field joint venture partners have suffered loss.
In June 2015 (as amended in August 2015 and October 2015), Tullow Ghana and Vallourec entered into standstill agreements which provide that neither party will proceed with a claim unless a party gives the other 28 days' notice to terminate the applicable standstill agreement, which was terminated on April 21, 2023. Tullow Ghana filed the Particulars of Claim and the Claim Form with the Commercial Court on May 22, 2023. The case is funded by a third-party litigation funder.
Vallourec's Defense was served on November 17, 2023, and Tullow Ghana issued its Reply to the Defense on December 22, 2023. Tullow Ghana took part in two rounds of mediation on November 28, 2023 and March 4, 2025 to seek an early resolution as part of the pre-action protocols, in parallel with the commencement of proceedings to preserve limitations and the formalities of service being complied with. No settlement was reached at the mediation, but the parties will continue to keep the mediation route open for a potential settlement.
On April 26, 2024, a Case Management Conference took place where the judge decided that there should be a Preliminary Issues Trial on seven issues due to be held between May 20-22, 2025