RE: Updates8 Jun 2022 11:13
In April 27th update, we were told that wet commissioning was due to start on 18th May, giving us our first gas date of 1st June. That gave them 11 working days.
The start of wet commissioning is a major milestone, so I'm sure the company will announce it asap. Therefore we can safely assume it has not started.
Even if they start it tomorrow, the 11 eleven working days would give us a first gas date of 23rd June.
This is NOT the middle of June.
The BOD have literally not earned a penny of their salaries, it has all been funded by investors and borrowing.
A little more respect for their investors isn't much to ask for. Updates on slippage should be timely, and should be triggered by a lot less than a two week slippage like last time.