George Frangeskides, Chairman at ALBA, explains why the Pilbara Lithium option ‘was too good to miss’. Watch the video here

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksZephyr Energy Regulatory News (ZPHR)

Share Price Information for Zephyr Energy (ZPHR)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 4.35
Bid: 4.20
Ask: 4.50
Change: -0.20 (-4.40%)
Spread: 0.30 (7.143%)
Open: 4.55
High: 4.55
Low: 4.30
Prev. Close: 4.55
ZPHR Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Paradox project update

10 Jul 2023 07:00

RNS Number : 4654F
Zephyr Energy PLC
10 July 2023
 

Prior to publication, the information contained within this announcement was deemed by the Company to constitute inside information as stipulated under the UK Market Abuse Regulation. With the publication of this announcement, this information is now considered to be in the public domain.

 

 

10 July 2023

Zephyr Energy plc

("Zephyr" or the "Company")

 

Paradox project update

Update on State 36-2 well;

First tranche of insurance proceeds received;

Amendment to White Sands Unit acreage approved; and

Assessments underway on previously acquired Greentown wells

 

Zephyr Energy plc (AIM: ZPHR) (OTCQB: ZPHRF), the Rocky Mountain oil and gas company focused on responsible resource development from carbon-neutral operations, is pleased to provide an update on operations at its flagship Paradox Project in the Paradox Basin, Utah, U.S (the "Paradox project").

 

State 36-2 LNW-CC well update

On 19 January 2023 the Company announced that it had intersected a major, highly-pressured, natural fracture network while drilling the State 36-2 LNW-CC well (the "State 36-2 well"). On 20 March 2023 the Company announced that workover and subsequent production test operations were set to commence.

In early April 2023, a significant well control issue arose in which hydrocarbons flowed from the well in an uncontrolled manner. The incident was the apparent result of multiple equipment failures and in particular the failure of a safety valve. Importantly, there were no injuries during the incident and subsequent well control efforts proved to be successful.

At present, the State 36-2 well remains static and under control, and Zephyr is in the process of pulling the production tubing out of the hole, as some joints were compressed/compromised or stuck due to the high pressures experienced during the well control incident and subsequent well control efforts. To date approximately 7,000 feet of 8,900 feet of tubing has been pulled and inspected with circa 15 per cent of the pulled joints requiring replacement. The Company is moving methodically to remove and inspect the remaining joints while keeping the wellbore static. Once the tubing work is complete, a final cement squeeze will be performed and then the casing will be perforated across the reservoir interval prior to production testing the well.

Current and future operations will continue to be conducted in such a way that well control is maintained and working conditions are safe for our team. Although recent operations have been slower than initially expected, the Company's Board of Directors (the "Board") notes the safe progress to date and fully expects to deliver a production test in the near-term. This methodical and patient approach is necessitated by the expected high pressure and substantial apparent deliverability of the well and reservoir, as witnessed during the earlier phases of the operation.

 

Well control insurance update

While the State 36-2 well control incident was a powerful illustration of the high pressures and productivity inherent in certain Paradox Basin natural fracture networks, the resulting well work operations have subsequently resulted in a delay to the work programme.

As previously reported, the Company retains comprehensive well control insurance coverage, and the Board ultimately expects to recover the vast majority of costs associated with the well control incident. Under the terms of Zephyr's insurance policy these payment recoveries are made on a reimbursement basis (after approval by the insurer, and after the Company has paid the corresponding contractor invoices). 

The Company is pleased to announce the initial invoices submitted to its insurer have now been approved and funds from Zephyr's initial claim, totaling circa US$800,000, have been received. Additional invoices are being submitted on a regular basis with payments expected within 30 days of receipt by the insurer.

 

BLM Approval of White Sands Unit Acreage Expansion/Contraction

On 25 August, 2022, the Company announced the acquisition of additional prime Paradox Basin acreage adjacent to its operated White Sands Unit (the "WSU") through the targeted acquisition of 1,920 leased acres deemed by the Company to have immediate development potential.  Additional contiguous acreage was acquired as reported on 14 September 2022 (collectively, the "acquired acreage").

The acquired acreage was largely covered by Zephyr's existing 3D seismic, and directly bordered the Zephyr lease on which the State 36-2 is located, and with access to pre-existing surface infrastructure which Zephyr subsequently acquired.

A portion of the acquired acreage was envisioned to be added to the WSU, subject to approval from the U.S. Bureau of Land Management (the "BLM") for which the Company applied in early 2023. Zephyr is pleased to report such approval has now been granted as part of larger Expansion/Contraction amendment of the WSU. As part of the approval, 5,000 high-graded acres with near-term development potential have been added to the WSU, and roughly 5,395 acres deemed by the Company to be less suitable for future development have been relinquished.

These actions are part of the Company's active and ongoing portfolio management of its Paradox Basin position. The Board is pleased with its recent BLM interactions and subsequent approval, which results in an amended federal unit with an upgraded and manageable acreage position - a position increasingly difficult to replicate in today's regulatory and political environment.

 

Assessment underway on recently acquired Greentown wells

The Company is also pleased to report that it has commenced the assessment on five existing wellbores (located in the WSU) acquired as part of a larger acquisition of infrastructure assets and which was announced on 14 September 2022. Several of the existing wells are former producers of hydrocarbons and were subsequently shut-in due to lack of operating infrastructure. Others were deemed to have potential future use as salt water disposal wells or as producers of salt water brine for potential extraction of lithium resources.

As part of this assessment, Zephyr's operations team recently recommenced production from the Greentown Federal 28-11 well in order to understand the well's potential contribution to overall field production when ongoing field infrastructure work has been completed. Hydrocarbons are currently flowing from the well, with condensate volumes collected for sale and natural gas volumes being flared. Once flow stabilises, the Company will assess its future potential for the short and longer term when gas export is available.

 

Colin Harrington, Zephyr's Chief Executive Officer, stated: 

"Work on the State 36-2 well has progressed safely, and the team continues to push forward while maintaining control of the well and ensuring the safety of those working on it. I would like to once again thank our team on the ground for their ongoing efforts in keeping the well stable and safe. 

 

"I am also pleased to report the receipt of initial proceeds from our well control insurance policy. We appreciate the level of engagement from our insurance partners.

 

"In relation to the upgraded acreage position in the WSU, we continue to work closely with the BLM and other regulatory authorities to perfect the federal unit by maximising its upside potential and minimising environmental impact in areas not deemed as prospective.

 

"Finally, I would like to note the work being done on the Paradox project away from the 36-2 well, with recent operations including the restart of the Federal 28-11 well where hydrocarbons are now flowing. While this well will not have the same volumetric potential as the State 16-2 LN-CC well or the State 36-2 well, we do believe it will have positive economic impact once our infrastructure buildout has been completed. Two other existing wells in the Zephyr portfolio have also had notable prior shows of hydrocarbons and offer potential future locations and/or workover opportunities.

 

"We look forward to updating investors on continued progress in the coming weeks during this pivotal time for the Paradox project."

 

 

Contacts

 

Zephyr Energy plc

Colin Harrington (CEO)

Chris Eadie (FD)

 

 Tel: +44 (0)20 7225 4590

Allenby Capital Limited - AIM Nominated Adviser

Jeremy Porter / Vivek Bhardwaj

 

 Tel: +44 (0)20 3328 5656

 

Turner Pope Investments - Joint-Broker

James Pope / Andy Thacker 

 

Panmure Gordon (UK) Limited - Joint-Broker

John Prior / Hugh Rich / James Sinclair-Ford

 

Celicourt Communications - Public Relations

Mark Antelme / Felicity Winkles / Ali Al Qahtani

 Tel: +44 (0)20 3657 0050

 

 

Tel: +44 (0) 20 7886 2500

 

 

 

Tel: +44 (0) 20 7770 6424

 

 

Qualified Person

Dr Gregor Maxwell, BSc Hons. Geology and Petroleum Geology, PhD, Technical Adviser to the Board of Zephyr Energy plc, who meets the criteria of a qualified person under the AIM Note for Mining and Oil & Gas Companies -June 2009, has reviewed and approved the technical information contained within this announcement.

Notes to Editors

Zephyr Energy plc (AIM: ZPHR) (OTCQB: ZPHRF) is a technology-led oil and gas company focused on responsible resource development from carbon-neutral operations in the Rocky Mountain region of the United States. The Company's mission is rooted in two core values: to be responsible stewards of its investors' capital, and to be responsible stewards of the environment in which it works.

Zephyr's flagship asset is an operated 45,000-acre lease holding located in the Paradox Basin, Utah, 25,000 acres of which has been assessed to hold, net to Zephyr, 2P reserves of 2.6 million barrels of oil equivalent ("mmboe"), 2C resources of 34 mmboe and 2U resources 270 mmboe.

In addition to its operated assets, the Company owns working interests in a broad portfolio of non-operated producing wells across the Williston Basin in North Dakota and Montana. 

The Williston portfolio currently consists of working-interests in over 220 modern horizontal wells. Cash flow from the Williston production will be used to fund the planned Paradox Basin development. In addition, the Board will consider further opportunistic value-accretive acquisitions. 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDEAAXNEEDDEAA
Date   Source Headline
25th Apr 20247:00 amRNSStart of well drilling operations
17th Apr 20247:00 amRNSState 36-2R well drilling operations update
10th Apr 20247:00 amRNSGrant of share options and issue of warrants
28th Mar 20247:00 amRNSAdditions to senior management team
27th Mar 20241:02 pmRNSSalt Wash helium project update - replacement
27th Mar 20247:00 amRNSSalt Wash helium project update
22nd Mar 20247:00 amRNSCommencement of Initial Drilling Operations
15th Mar 20247:00 amRNSAward of rig contract to Helmerich & Payne
11th Mar 20247:00 amRNSParadox project update
29th Feb 20247:00 amRNSQ4 2023 results from Williston Basin portfolio
14th Feb 20247:00 amRNSState 36-2R Drilling Permit Sundry Notice Approval
8th Feb 20247:00 amRNSOperations update
15th Dec 20237:00 amRNSOperational update
15th Nov 20237:00 amRNSQ3 2023 results from Williston Basin portfolio
1st Nov 20237:00 amRNSWilliston Basin Update
25th Oct 20237:00 amRNSInvestor Webinar Registration
18th Oct 202312:38 pmRNSInvestor Webinar
18th Oct 20237:00 amRNSParadox project update
29th Sep 20237:00 amRNSHalf-year Report
20th Sep 20237:00 amRNSStatement Re Market Speculation
15th Aug 20237:00 amRNSQ2 Williston Basin & State 36-2 LNW-CC Update
26th Jul 202311:39 amRNSResult of AGM
26th Jul 20237:00 amRNSAGM Statement
10th Jul 20237:00 amRNSParadox project update
30th Jun 20235:00 pmRNSTotal Voting Rights
26th Jun 20237:00 amRNSFinal Results
6th Jun 20237:00 amRNSPlacing & Subscription & Project Update
16th May 20237:00 amRNSQ1 Williston Basin & State 36-2 LNW-CC Update
2nd May 20237:00 amRNSHedging programme update
20th Apr 20236:15 pmRNSCorporate Presentation
13th Apr 20234:02 pmRNSInvestor Webinar
11th Apr 20237:00 amRNSState 36-2 LNW-CC well update
20th Mar 20237:00 amRNSState 36-2 LNW-CC well production test to commence
8th Mar 20237:00 amRNSParadox project update
28th Feb 20235:00 pmRNSTotal Voting Rights
15th Feb 20237:00 amRNSQ4 & FY 22 results from Williston Basin portfolio
14th Feb 20237:00 amRNSState 36-2 LNW-CC well update
10th Feb 20238:00 amRNSCompletion of Paradox project acquisition
1st Feb 20237:00 amRNSIssue of equity and change to total voting rights
31st Jan 20235:00 pmRNSTotal Voting Rights
19th Jan 20232:05 pmRNSSecond Price Monitoring Extn
19th Jan 20232:00 pmRNSPrice Monitoring Extension
19th Jan 20237:00 amRNSState 36-2 LNW-CC well update
29th Dec 20222:11 pmRNSWarrants exercise & Director/PDMR/PCA holdings
21st Dec 20227:00 amRNSAcquisitions and Operational Update
9th Dec 20227:00 amRNSAward of Grant Funding
1st Dec 20227:00 amRNSState 16-2 LN-CC well – Production test commenced
29th Nov 20227:00 amRNSCorporate Presentation
22nd Nov 20227:00 amRNSHolding(s) in Company
21st Nov 20227:00 amRNS36-2 LNW-CC well – Drilling Operations Commenced

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.