Adam Davidson, CEO of Trident Royalties, discusses offtake milestones and catalysts to boost FY24. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksXtract Regulatory News (XTR)

Share Price Information for Xtract (XTR)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 1.00
Bid: 0.90
Ask: 1.10
Change: 0.00 (0.00%)
Spread: 0.20 (22.222%)
Open: 1.00
High: 1.00
Low: 1.00
Prev. Close: 1.00
XTR Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Update on Open Pit Mining Study for Bushranger

7 Mar 2023 07:00

RNS Number : 0749S
Xtract Resources plc
07 March 2023
 

 

For immediate release

7 March 2023

 

Xtract Resources Plc

("Xtract" or the "Company")

Update on Open Pit Mining Study for Bushranger Copper-Gold Project

 

The Board of Xtract Resources Plc ("Xtract" or the "Company") is pleased to provide an update on the mining study ("Study") by independent consultants Optimal Mining Solutions (Pty) Ltd ("Optimal Mining") to examine the economics of a 20Mpta and 25Mpta open pit operation on the Bushranger Copper-Gold Project ("Project") in central New South Wales, Australia. Optimal Mining has prepared an initial report for the Company which has reviewed the pit optimisation options ("Interim Report"). Optimal Mining has identified that the economics of the Project can be improved by way of modern ore sorting technology and the full Study will be completed based on further test work already under way on this option.

 

Highlights

 

· The combined copper-gold mineral resources at the Racecourse and Ascot Prospects on the Project were previously updated by the Company (see RNS dated 19 December 2022) to contain approximately 1.3Mt of copper-equivalent metal, with the combined shallow high-grade zones at the Racecourse and Ascot prospects hosting a total of 225Mt @ 0.33% CuEq*.

 

· 16 economic pit shells were modelled in the Interim Report from an operating cost perspective only with capital cost requirements excluded and to be finalised on completion of the Study. The 20Mtpa and 25Mtpa open pit options potentially generate significant operating cash margins dependent upon mining rate, copper price and cut-off grade.

 

· As processing of the Bushranger ore contributes between 49% and 61% of the total production cost across the 16 cases examined, Optimal Mining identified that the Bushranger copper mineralisation may be well suited to pre-concentration, providing opportunities to streamline mining and processing with positive impacts on metal recoveries, capital and operating costs through the use of ore sorting technology.

 

· Optimal Mining has identified a copper project with similar grades to Bushranger where pre-concentration reduced the amount of material to be concentrated up to approximately 50%, significantly reducing pre-production capital and operating costs.

 

· Xtract has initiated the pre-concentration study with the objective of quantifying improvement in cash margins, which will then allow Net Present Values and Internal Rates of Returns to be calculated for various mining scenarios, finalising the mining Study.

 

· Further drilling is at planning stage to test the remaining shallow to moderate depth copper-gold mineralisation targets located proximal to the Racecourse Mineral Resource. 

 

*CuEq % = (Cu%) + (Au g/t * 0.6577)% + (Ag g/t * 0.008769)%

Cu Price = US$8800/t, Au Price = US$1800/oz, Ag Price = US$24/oz

 

Colin Bird, Executive Chairman said: "The initial work by Optimal Mining shows that pre-concentration of ore has the potential to significantly increase cash flows from an open pit operation. On a project with similar grades to Bushranger, pre-concentration of the copper mineralisation reduced the amount of material to be concentrated by over 50%, while retaining 87% of the contained copper metal. This significantly reduced the pre-production capital expenditure, improved the operating cash margin and the overall project Net Present Value and Internal Rate of Return. Therefore, we have initiated a study to determine how effective ore pre-concentration could be at Bushranger and will then feed those results into the final open pit economic modelling.

Given the potential upside of locating additional mineralisation in close proximity to the Racecourse Mineral Resource further drill testing of adjacent targets is being planned which, together with the results of the pre-concentration test work, will allow us to finalise our ongoing plans for the Bushranger project."

 

Bushranger Project Results from Open Pit Mining Interim Report

Following definition of the updated Mineral Resource for the Racecourse Prospect and the maiden Mineral Resource for the Ascot Prospect, Xtract contracted independent consultants Optimal Mining to update the Bushranger Project open pit mining study. The update was aimed at examining the economics of either a 20Mtpa or 25Mtpa open pit mining operation for copper prices ranging from US$8,000/t to US$11,000/t and cut-off grades of 0.10% CuEq and 0.15% CuEq. A total of 16 scenarios were run for open pit mining of the Racecourse and Ascot Mineral Resources, with economic pit shells being generated for all of these scenarios.

 

The Interim Report is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorised as mineral reserves. The Interim Report is based on low-level technical and economic assessments and is insufficient to support estimation of Ore Reserves or to provide assurance of an economic development case at this stage, or to provide certainty that the conclusions of the Interim Report will be realised.  

 

A consequence of the grade of the mineralisation of the Racecourse and Ascot Mineral Resource is that processing costs are estimated to be approximately half of the total production costs. Optimal Mining has identified that pre-concentration treatment of the copper-gold mineralisation could have significant benefits as follows:

 

· Reduce processing and operating costs;

· Reduce pre-production capital expenditure due to a significantly smaller concentrator;

· Improve concentrator recoveries due to higher feed grades;

· Generate more coarse dry rejects that are easier to manage;

· Reduce the size of the tailings dam due to less concentrator feed.

 

The Interim Report further identified that, on a copper project with similar grades to the Bushranger Project, pre-concentration retained 87% of the contained metal and reduced the amount of material to be concentrated by approximately 50%, significantly reducing pre-production capital and operating costs. The feed grade into the concentrator on this comparable project increased from 0.15% Cu to 0.29% Cu, improving metal recoveries. Due to the close association of the copper mineralisation at both the Racecourse and Ascot prospects with the mineral pyrrhotite, which is both conductive and magnetic, there are several options for pre-concentrating the mineralisation which may be highly effective.

 

Next Steps

Due to the highlighted potential for improvement of the project's economic viability, Xtract has initiated a study to assess the effectiveness of pre-concentration. Mineralisation from four drill holes from the Racecourse Prospect has already been submitted for ore pre-concentration analysis which will allow the open pit economic model to be refined and then finalised. Finalisation of the open pit mining Study will include the development of production schedules, capital cost and operating cost estimates, which will then allow Net Present Values and Internal Rates of Returns to be calculated for various mining scenarios for a range of production rates, cut-off grades and copper prices.

 

The initial work by Optimal Mining for the open pit economic study have reinforced the benefits of further shallow to moderate depth copper-gold mineralisation to the overall economic value of the Bushranger Project. Consequently, additional drilling is at planning stage to test the upside potential of remaining exploration targets in close proximity to the Racecourse Mineral Resource

 

Further information is available from the Company's website which details the company's project portfolio as well as a copy of this announcement: www.xtractresources.com

 

 

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 as it forms part of UK Domestic Law by virtue of the European Union (Withdrawal) Act 2018 ("UK MAR").

 

The person who arranged for the release of this announcement on behalf of the Company was Colin Bird, Executive Chairman and Director.

 

Enquiries:

 

Xtract Resources Plc

Colin Bird,

Executive Chairman

 

+44 (0)20 3416 6471

www.xtractresources.com

Beaumont Cornish Limited

Nominated Adviser and Joint Broker

Roland Cornish

Michael Cornish

Felicity Geidt

+44 (0)207628 3369

www.beaumontcornish.co.uk

 

Novum Securities Limited

Joint Broker

 

Jon Belliss

Colin Rowbury 

 

+44 (0)207 399 9427

www.novumsecurities.com  

 

 

 

Qualified Person

Information in this announcement relating to the exploration works has been reviewed by Edward (Ed) Slowey, BSc, PGeo, a consultant to Xtract. Mr Slowey is a graduate geologist with more than 40 years' relevant experience in mineral exploration and mining, a founder member of the Institute of Geologists of Ireland and is a Qualified Person under the AIM rules. Mr Slowey has reviewed and approved the geological content of this announcement.

 

Qualified Person

In accordance with AIM Note for Mining and Oil & Gas Companies, June 2009 ("Guidance Note"), Colin Bird, CC.ENG, FIMMM, South African and UK Certified Mine Manager and Director of Xtract Resources plc, with more than 40 years' experience mainly in hard rock mining, is the qualified person as defined in the Guidance Note of the London Stock Exchange, who has reviewed the technical information contained in this press release.

 

Optimal Mining Solutions (Pty) Ltd of Australia

Optimal Mining Solutions (Pty) Ltd of Australia has reviewed the information in this announcement which has been derived from the interim pit optimisation Study and has confirmed that the information so presented is balanced and complete and not inconsistent with the interim pit optimisation Study.

Mineral Reserves and Resources

The Company estimates and discloses mineral reserves and resources using the definitions adopted by JORC. Further details are available at www.jorc.org. See the "Glossary of Geological and Mining Terms" for complete definitions of mineral reserves and mineral resources.

About Mineral Resources

Mineral resources are not mineral reserves and do not have demonstrated economic viability but do have reasonable prospect for economic extraction. They fall into three categories: measured, indicated, and inferred. The reported mineral resources are stated inclusive of mineral reserves. Measured and indicated mineral resources are sufficiently well-defined to allow geological and grade continuity to be reasonably assumed and permit the application of technical and economic parameters in assessing the economic viability of the mineral resource. Inferred mineral resources are estimated on limited information not sufficient to verify geological and grade continuity or to allow technical and economic parameters to be applied. Inferred mineral resources are too speculative geologically to have economic considerations applied to them. There is no certainty that mineral resources of any category will be upgraded to mineral reserves.

Important Information about Mineral Reserve and Resource Estimates

Whilst the Company takes all reasonable care in the preparation and verification of the mineral reserve and resource figures. the figures are estimates based in part on forward-looking information. Estimates are based on management's knowledge, mining experience, analysis of drilling results, the quality of available data and management's best judgment. They are, however, imprecise by nature, may change over time, and include many variables and assumptions including geological interpretation, commodity prices and currency exchange rates, recovery rates, and operating and capital costs. There is no assurance that the indicated levels of metal will be produced, and the Company may have to re-estimate the mineral reserves based on actual production experience. Changes in the metal price, production costs or recovery rates could make it unprofitable to operate or develop a particular deposit for a period of time.

Forward Looking Statements

Certain statements in this announcement, are, or may be deemed to be, forward looking statements. Forward looking statements are identied by their use of terms and phrases such as ''believe'', ''could'', "should" ''envisage'', ''estimate'', ''intend'', ''may'', ''plan'', ''will'' or the negative of those, variations or comparable expressions, including references to assumptions. These forward-looking statements are not based on historical facts but rather on the Directors' current expectations and assumptions regarding the Company's future growth, results of operations, performance, future capital and other expenditures (including the amount, nature and sources of funding thereof), competitive advantages, business prospects and opportunities. Such forward looking statements reect the Directors' current beliefs and assumptions and are based on information currently available to the Directors. A number of factors could cause actual results to differ materially from the results discussed in the forward-looking statements including risks associated with vulnerability to general economic and business conditions, competition, environmental and other regulatory changes, actions by governmental authorities, the availability of capital markets, reliance on key personnel, uninsured and underinsured losses and other factors, many of which are beyond the control of the Company. Although any forward-looking statements contained in this announcement are based upon what the Directors believe to be reasonable assumptions, the Company cannot assure investors that actual results will be consistent with such forward looking statements.

 

TECHNICAL GLOSSARY

The following is a summary of technical terms:

 

"Ag"

Silver

"Au"

Gold

"Cu"

Copper

"CuEq"

Copper equivalent grade, calculated using assumed metal prices for copper, gold and other metals

 

"Indicated Mineral Resource"

That part of a Mineral Resource for which quantity, grade (or quality), densities, shape and physical characteristics are estimated with sufficient confidence to allow the application of Modifying Factors in sufficient detail to support mine planning and evaluation of the economic viability of the deposit. Geological evidence is derived from adequately detailed and reliable exploration, sampling and testing gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes, and is sufficient to assume geological and grade (or quality) continuity between points of observation where data and samples are gathered. (JORC 2012)

 

"Inferred Mineral Resource"

That part of a Mineral Resource for which quantity and grade (or quality) are estimated on the basis of limited geological evidence and sampling. Geological evidence is sufficient to imply but not verify geological and grade (or quality) continuity. It is based on exploration, sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes. (JORC 2012)

 

"mineralisation"

Process of formation and concentration of elements and their chemical compounds within a mass or body of rock

"porphyry"

A deposit of disseminated copper minerals in or around a large body of intrusive rock

 

 

"Mtpa"

Million tonnes per annum

 

ENDS

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDDBGDXIGGDGXL
Date   Source Headline
27th Jul 201610:06 amRNSAdmission of Shares
20th Jul 20167:00 amRNSManica and Chepica Update and Placing
4th Jul 201611:13 amRNSResult of AGM
30th Jun 20167:00 amRNSAGM Update
16th Jun 201612:30 pmRNSShareholder Presentation - 16 June
15th Jun 20162:00 pmRNSHolding(s) in Company
8th Jun 201612:00 pmRNSHolding(s) in Company
7th Jun 20167:22 amRNSFinal Results
7th Jun 20167:00 amRNSShareholder presentation - 16 June 2016
26th May 20167:00 amRNSDisposal of Manica Gold Project for US$17.5m
23rd May 201612:21 pmRNSXtract will NOT present at Shares Investor Evening
19th May 20167:00 amRNSXtract to present at Shares Investor Evening
11th May 20167:00 amRNSManica Gold Resource increased 36% to 1.257Moz
10th May 20168:11 amRNSDrawdown of US$2.4m in Debt
4th May 20169:04 amRNSQ1 Operational update
26th Apr 201612:13 pmRNSOperations Update Notice and UK Investor Show
13th Apr 20167:00 amRNSChepica Earn-in Option
15th Mar 20164:24 pmRNSHolding(s) in Company
14th Mar 20163:53 pmRNSHolding(s) in Company
8th Mar 201612:47 pmRNSCorrection on Manica cash costs & webcast playback
7th Mar 20167:00 amRNSUpdate on Manica Gold Project
1st Mar 20167:00 amRNSMozambique Government approve Manica acquisition
4th Feb 20167:46 amRNSProcessing plant restart at Chepica Mine
3rd Feb 201611:20 amRNSQ4 Operational Update
27th Jan 201611:52 amRNSChepica Update and Q4 Production Presentation
21st Jan 20167:00 amRNSOperations Update
13th Jan 20167:00 amRNSChepica Gold Mine - Update
29th Dec 20157:00 amRNSChepica Gold Mine - Fatal Accidents
30th Nov 20157:00 amRNSChepica Gold Mine - Operational Update
12th Nov 20157:00 amRNSOption Extensions
30th Oct 20151:56 pmRNSHolding(s) in Company Replacement
30th Oct 20159:52 amRNSHolding(s) in Company
20th Oct 201512:55 pmRNSInvestor presentation
20th Oct 20157:15 amRNSJV on new alluvial gold production at Manica
20th Oct 20157:00 amRNSChepica Q3 Operational Update
15th Oct 20157:31 amRNSAuroch Shareholders approve sale of Manica
13th Oct 20157:00 amRNSQ3 Production Update Presentation in London
8th Oct 20157:00 amRNSAssay results from Copper Tailings Project
29th Sep 20157:01 amRNSHalf Yearly Report
22nd Sep 20157:00 amRNSCarolusberg & O'Kiep Drilling Programme Completed
10th Sep 20157:00 amRNSManica Acquisition - Revised Terms Agreed
4th Aug 20157:00 amRNSHigh Grade Gold Reef system discovered at Chepica
22nd Jul 20151:28 pmRNSDirector/PDMR Shareholding
22nd Jul 201512:42 pmRNSDirector/PDMR Shareholding
15th Jul 201510:36 amRNSNew high grade reef system discovered at Chepica
8th Jul 20159:50 amRNSHolding(s) in Company
7th Jul 20159:38 amRNSImproved recoveries from test work at Fair Bride
29th Jun 20156:16 pmRNSResult of AGM
29th Jun 20157:00 amRNS£4.4m Placing and Acquisition agreement signed
25th Jun 20159:35 amRNSChepica Mine - Delivering on key milestones

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.