La Parrilla mine development plan

8 Sep 2014 10:43

RNS Number : 0640R
W Resources PLC
08 September 2014
 



 

 

 

 

 

 

 

 

 

08 September 2014

 

 

 

 

W Resources Plc

("W" or the "Company")

 

 

Staged Approach to La Parrilla Mine Development

W Resources Plc (AIM:WRES), the tungsten, copper and gold production, exploration and development company with assets in Spain and Portugal, is pleased to provide an update on current planning for development and financing of the La Parrilla mine following on from recent success in completing the La Parrilla tailings facility.

 

The La Parrilla mine is a world scale tungsten mine development with JORC compliant resources of 47 mt at 0.09% WO3. W Resources plans to develop the tailings and mine in a staged program to maximise use of existing infrastructure, keeping initial capital costs low and targeting high rate of return on invested capital.

 

The plan is to develop La Parrilla in three stages:

- Stage 1: La Parrilla Tailings completed in March 2014 and in production

- Stage 2: Fast Track Mine in the area adjacent to the current pit utilising existing tailings and power, water and road infrastructure

- Stage 3: Large scale La Parrilla Mine development to a current target design level of 2,300 tonnes of WO3 per annum

 

A study is underway to define the mine plan, metallurgical process, infrastructure and capital and operating costs for Stage 2 - Fast Track Mine. Stage 2 is expected to be able to leverage off the extensive existing infrastructure including roads and power, the tailings plant operations and the already open mining benches adjacent to the current pit. Definition work is expected to be completed by the end of 2014 and approvals achieved in 2015.

 

The overall scale and mine footprint for Stage 3 - Full Mine development will also be advanced and optimised during this period of time.

 

Michael Masterman, Chairman of W, said: "A staged development, which is in line with our strategy, keeps initial mine capital costs low and provides a strong bridge from tailings to initial mining and then full scale mine development. Financing plans, including customer alliances and potential joint ventures, are proceeding in parallel with the time critical mine definition and approvals work."

 

Commenting on tailings ramp up, Michael Masterman said: "The ramp up process for the La Parrilla tailings has been an invaluable source of data and insight for the mine development planning. We have achieved target product specifications of 60%+ WO3 quickly and have identified a number of important areas for process design improvements and operating efficiencies which will need to be progressively implemented. Tailings ramp up remains a challenge, focus and priority for the management team but our progress and the obvious synergies between the tailings operation and an early stage mining operation warrant timely definition and approvals work."

 

The latest investor presentation has been uploaded on the W website at http://www.wresources.co.uk/category/investors/presentations/  and contains a schematic on the staging on page 15.

 

Recent analysts' reports from Northland and Edison (http://www.wresources.co.uk/category/media/w-news/) provide third party updates on W's progress.

 

Enquiries:

W Resources Plc

Grant Thornton UK LLP

Michael Masterman

Colin Aaronson / Melanie Frean / Jen Clarke

T: +44 (0) 20 7193 7463

T: +44 (0) 20 7383 5100

www.wresources.co.uk

SI Capital

Gable Communications

Andy Thacker / Nick Emerson

John Bick

T: +44 (0) 1483 413500

T: +44 (0) 20 7193 7463

www.sicapital.co.uk

M: +44 (0) 7872 061007

 

About La Parrilla

The La Parrilla project site is situated in the Extremadura region of southwest Spain, in the Provinces of Caceres-Badajoz, approximately 310 km southwest of Madrid. The site is accessed directly from the highway along a 3 km asphalt road and is serviced by electricity and water. The project comprises a tungsten mine and a tungsten tailings project. The mine resource estimated by Golder in June 2013 is 46.92 million tonnes at 0.09% WO3, making it one of the largest tungsten deposits in the western world.

Annual plant feed will be c330,000 tonnes and annual production is anticipated to be 450 tonnes of tungsten trioxide (WO3) and 26 tonnes of tin (Sn), which will deliver over €7million per annum in revenue at current tungsten and tin prices.

 

Technical information in this report and on the W website has been prepared in accordance with the JORC Code and approved for inclusion by Mr Fernando de la Fuente, who is a "qualified person" in respect of the AIM Rules for Companies with over 39 years' experience in the Exploration and Mining Geology industry. Mr de la Fuente holds a B.Sc. in Geology and a MSc in Geology from the University of Granada in Spain. He is also a member of the Spanish College of Geologists (Number 49), the Spanish Society of Mineralogy, founder member of the Spanish Society of Geology, member of the Spanish Association of Applied Geology to Mineral Deposits, member of the Society for Mining, Metallurgy and Exploration, Inc., member of PDAC.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUGUPCBUPCUBR
Date   Source Headline
21st Jun 201710:12 amRNSTPI Investor Evening
16th Jun 20179:57 amRNSPlacing to Directors to raise £100,000
14th Jun 20178:54 amRNSPlacing to Raise £650,000
14th Jun 20177:00 amRNSLa Parrilla Maiden JORC Reserves
30th May 20177:00 amRNSNotice of Annual General Meeting
17th May 20177:00 amRNSFinal Application for La Parrilla Grant
16th May 20179:41 amRNSDevelopment and Financing of La Parrilla Update
11th May 20177:00 amRNSIncrease in Grades and Quality of La Parrilla
3rd May 201712:20 pmRNSFinal Results for the Year Ended 31 December 2016
27th Apr 201711:37 amRNSChange to Significant Shareholder
12th Apr 20177:00 amRNSJig and Mill Contract Including Vendor Finance
9th Mar 20177:00 amRNSStrategic Review and Placing to raise £750k
19th Jan 20177:00 amRNSLa Parrilla Equipment Finance, Grants ,Development
17th Jan 20177:00 amRNSSão Martinho SMD-009 Hits 56.4m of Gold
2nd Dec 20161:14 pmRNSGrant of Share Options
18th Nov 20167:00 amRNSFirst Hole at São Martinho Intersects Gold
1st Nov 201611:52 amRNSPlacing to Raise £1 million
19th Oct 20167:00 amRNSLa Parrilla Commences Tungsten Shipments
17th Oct 20167:00 amRNSHigh Tin and Tungsten Grades at La Parrilla FTM
30th Sep 20167:00 amRNSHalf Yearly Report
26th Sep 20167:00 amRNSSão Martinho Gold Drilling Commences
23rd Sep 20169:42 amRNSInvestor Presentation - September 2016
22nd Sep 20167:00 amRNSProduction Commences at La Parrilla
1st Sep 20167:00 amRNSHigh Tungsten and Tin Grades from La Parrilla
19th Aug 20167:00 amRNSInvestor Presentation - 22 September 2016
17th Aug 20161:31 pmRNSPlacing Completes Finance Package for First Phase
16th Aug 20167:00 amRNSFinance & Offtake Package Secured for La Parrilla
27th Jul 20167:00 amRNSMining Starts at La Parrilla with First Mine Blast
25th Jul 201612:01 pmRNSNew Portuguese Licence Granted
20th Jul 20167:00 amRNSLa Parrilla Mine update
1st Jul 201610:45 amRNSIssue of Equity: Performance Shares
29th Jun 201612:59 pmRNSResults of Annual General Meeting
16th Jun 20161:32 pmRNSExercise of Warrants
9th Jun 20167:00 amRNSSão Martinho Gold Deposit Maiden JORC Estimate
1st Jun 20167:00 amRNSNotice of Annual General Meeting
27th May 20167:30 amRNSFinal Results for the Year Ended 31 December 2015
28th Apr 20169:56 amRNSWRES to present at Mining Capital Conference
18th Apr 20167:00 amRNSLa Parrilla Strong Metal Recovery Results
15th Mar 20167:00 amRNSPlacing to Raise additional £100k
11th Mar 20167:00 amRNSPlacing to raise £750,000
7th Mar 20167:00 amRNSLa Parrilla Scalable Development
2nd Mar 201611:35 amRNSResults at São Martinho and Tarouca
19th Feb 20167:00 amRNSInvestor Presentation - 2 March 2016
5th Feb 20167:49 amRNSLa Parrilla JORC estimate
21st Jan 20167:00 amRNSShare dealing
16th Dec 20152:42 pmRNSStrong Assay Results from La Parrilla Drilling
7th Dec 20157:00 amRNSDrilling at La Parrilla results
25th Nov 201511:03 amRNSLa Parrilla Mine Development Approval Granted
5th Nov 20157:00 amRNSPlacing to Raise £600k
27th Oct 20159:01 amRNSIncreased JORC Indicated Resource at Regua

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.