La Parrilla mine development plan

8 Sep 2014 10:43

RNS Number : 0640R
W Resources PLC
08 September 2014
 



 

 

 

 

 

 

 

 

 

08 September 2014

 

 

 

 

W Resources Plc

("W" or the "Company")

 

 

Staged Approach to La Parrilla Mine Development

W Resources Plc (AIM:WRES), the tungsten, copper and gold production, exploration and development company with assets in Spain and Portugal, is pleased to provide an update on current planning for development and financing of the La Parrilla mine following on from recent success in completing the La Parrilla tailings facility.

 

The La Parrilla mine is a world scale tungsten mine development with JORC compliant resources of 47 mt at 0.09% WO3. W Resources plans to develop the tailings and mine in a staged program to maximise use of existing infrastructure, keeping initial capital costs low and targeting high rate of return on invested capital.

 

The plan is to develop La Parrilla in three stages:

- Stage 1: La Parrilla Tailings completed in March 2014 and in production

- Stage 2: Fast Track Mine in the area adjacent to the current pit utilising existing tailings and power, water and road infrastructure

- Stage 3: Large scale La Parrilla Mine development to a current target design level of 2,300 tonnes of WO3 per annum

 

A study is underway to define the mine plan, metallurgical process, infrastructure and capital and operating costs for Stage 2 - Fast Track Mine. Stage 2 is expected to be able to leverage off the extensive existing infrastructure including roads and power, the tailings plant operations and the already open mining benches adjacent to the current pit. Definition work is expected to be completed by the end of 2014 and approvals achieved in 2015.

 

The overall scale and mine footprint for Stage 3 - Full Mine development will also be advanced and optimised during this period of time.

 

Michael Masterman, Chairman of W, said: "A staged development, which is in line with our strategy, keeps initial mine capital costs low and provides a strong bridge from tailings to initial mining and then full scale mine development. Financing plans, including customer alliances and potential joint ventures, are proceeding in parallel with the time critical mine definition and approvals work."

 

Commenting on tailings ramp up, Michael Masterman said: "The ramp up process for the La Parrilla tailings has been an invaluable source of data and insight for the mine development planning. We have achieved target product specifications of 60%+ WO3 quickly and have identified a number of important areas for process design improvements and operating efficiencies which will need to be progressively implemented. Tailings ramp up remains a challenge, focus and priority for the management team but our progress and the obvious synergies between the tailings operation and an early stage mining operation warrant timely definition and approvals work."

 

The latest investor presentation has been uploaded on the W website at http://www.wresources.co.uk/category/investors/presentations/  and contains a schematic on the staging on page 15.

 

Recent analysts' reports from Northland and Edison (http://www.wresources.co.uk/category/media/w-news/) provide third party updates on W's progress.

 

Enquiries:

W Resources Plc

Grant Thornton UK LLP

Michael Masterman

Colin Aaronson / Melanie Frean / Jen Clarke

T: +44 (0) 20 7193 7463

T: +44 (0) 20 7383 5100

www.wresources.co.uk

SI Capital

Gable Communications

Andy Thacker / Nick Emerson

John Bick

T: +44 (0) 1483 413500

T: +44 (0) 20 7193 7463

www.sicapital.co.uk

M: +44 (0) 7872 061007

 

About La Parrilla

The La Parrilla project site is situated in the Extremadura region of southwest Spain, in the Provinces of Caceres-Badajoz, approximately 310 km southwest of Madrid. The site is accessed directly from the highway along a 3 km asphalt road and is serviced by electricity and water. The project comprises a tungsten mine and a tungsten tailings project. The mine resource estimated by Golder in June 2013 is 46.92 million tonnes at 0.09% WO3, making it one of the largest tungsten deposits in the western world.

Annual plant feed will be c330,000 tonnes and annual production is anticipated to be 450 tonnes of tungsten trioxide (WO3) and 26 tonnes of tin (Sn), which will deliver over €7million per annum in revenue at current tungsten and tin prices.

 

Technical information in this report and on the W website has been prepared in accordance with the JORC Code and approved for inclusion by Mr Fernando de la Fuente, who is a "qualified person" in respect of the AIM Rules for Companies with over 39 years' experience in the Exploration and Mining Geology industry. Mr de la Fuente holds a B.Sc. in Geology and a MSc in Geology from the University of Granada in Spain. He is also a member of the Spanish College of Geologists (Number 49), the Spanish Society of Mineralogy, founder member of the Spanish Society of Geology, member of the Spanish Association of Applied Geology to Mineral Deposits, member of the Society for Mining, Metallurgy and Exploration, Inc., member of PDAC.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUGUPCBUPCUBR
Date   Source Headline
25th Mar 20204:36 pmRNSPrice Monitoring Extension
16th Mar 20208:30 amRNSOngoing Operations and Covid-19 Response
10th Mar 20207:00 amRNSRégua and La Parrilla Update. Director Retirement
10th Mar 20207:00 amRNS£756,000 Placing to Spanish Investors at 0.36p
18th Feb 20207:00 amRNSNew Loan Facility and Extremadura Grant Update
5th Feb 20209:55 amRNSRégua Commencement and Updated Régua JORC Resource
20th Jan 20207:00 amRNSConversion of Directors' Loans
9th Jan 20208:33 amRNSFirst Shipment from New Concentrator Plant
8th Jan 20207:00 amRNSNon-Executive Director Appointment
18th Dec 20197:00 amRNSAdditional $5 Million Facility. La Parrilla Update
5th Dec 20197:00 amRNSFinance Update
29th Nov 20192:48 pmRNSIssue of Shares and Financing Update
28th Nov 20197:00 amRNSLa Parrilla Production Update
15th Nov 20193:05 pmRNSLa Parrilla Ramp-Up Finance Update
8th Nov 20197:03 amRNSLa Parrilla First Concentrate and Financing Update
21st Oct 20197:00 amRNSFirst Ore Fed to La Parrilla Concentrator Plant
30th Sep 20198:00 amRNSHalf-year Report to 30 June 2019
16th Sep 20197:00 amRNSEUR1m placement to Spanish Investors
9th Sep 20194:14 pmRNSCorrection - Corporate and EUR 5.3 m Grant Update
9th Sep 201910:02 amRNSCorporate and EUR 5.3 m Grant Update
29th Aug 20197:00 amRNSLa Parrilla Concentrator Construction Complete
16th Aug 201911:39 amRNSDirector/PDMR Shareholding
14th Aug 20192:48 pmRNSDirector/PDMR Shareholding
7th Aug 20197:00 amRNSLa Parrilla Tungsten & Tin Mine Update
5th Aug 20195:12 pmRNSHolding(s) in Company
28th Jun 201912:42 pmRNSResult of AGM
28th Jun 20197:00 amRNSLa Parrilla Update
19th Jun 20197:01 amRNSHaulage and Crushing Contract Signed for Régua
19th Jun 20197:00 amRNSLa Parrilla and São Martinho Update
7th Jun 20197:00 amRNSLa Parrilla Mining Contract Awarded
3rd Jun 20192:46 pmRNSNotice of AGM and Annual Report
29th May 20198:12 amRNSJoint Broker Appointment
22nd May 20197:00 amRNSExercise of Warrants by Directors
21st May 20197:00 amRNSLa Parrilla Jig Commissioned with First Ore
9th May 20197:00 amRNSAdvance on 5.3m EUR Grant through Extremadura Bank
2nd May 20197:00 amRNSLa Parrilla Update and Mine Blast
30th Apr 201911:57 amRNSFinal Results for the Year Ended 31 December 2018
29th Apr 201912:15 pmRNSMajor Shareholding Notification
18th Apr 201911:00 amRNSPrice Monitoring Extension
18th Apr 20199:31 amRNSEarly Exercise of Warrants
16th Apr 20197:00 amRNSJig & Mill Plant Completed for Commissioning
1st Apr 20197:00 amRNSHigh Grade Tungsten Intersections at Régua
18th Mar 20197:00 amRNSUpdate on La Parrilla and on Portuguese assets
5th Feb 20197:00 amRNSLa Parilla Mine Update and Issue of Shares
20th Dec 20187:00 amRNSLa Parrilla Mine's First Crushed Ore
10th Dec 20187:00 amRNSMechanical Completion of La Parrilla Crusher Plant
3rd Dec 20187:00 amRNSFirst Tungsten Shipment from the La Parrilla Mine
27th Nov 201810:50 amRNSPlacing to Raise £1.5m
23rd Nov 20187:00 amRNSTPI Investor Evening - 10 December
20th Nov 20184:19 pmRNSGrant of Share Options

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.