La Parrilla mine development plan

8 Sep 2014 10:43

RNS Number : 0640R
W Resources PLC
08 September 2014
 



 

 

 

 

 

 

 

 

 

08 September 2014

 

 

 

 

W Resources Plc

("W" or the "Company")

 

 

Staged Approach to La Parrilla Mine Development

W Resources Plc (AIM:WRES), the tungsten, copper and gold production, exploration and development company with assets in Spain and Portugal, is pleased to provide an update on current planning for development and financing of the La Parrilla mine following on from recent success in completing the La Parrilla tailings facility.

 

The La Parrilla mine is a world scale tungsten mine development with JORC compliant resources of 47 mt at 0.09% WO3. W Resources plans to develop the tailings and mine in a staged program to maximise use of existing infrastructure, keeping initial capital costs low and targeting high rate of return on invested capital.

 

The plan is to develop La Parrilla in three stages:

- Stage 1: La Parrilla Tailings completed in March 2014 and in production

- Stage 2: Fast Track Mine in the area adjacent to the current pit utilising existing tailings and power, water and road infrastructure

- Stage 3: Large scale La Parrilla Mine development to a current target design level of 2,300 tonnes of WO3 per annum

 

A study is underway to define the mine plan, metallurgical process, infrastructure and capital and operating costs for Stage 2 - Fast Track Mine. Stage 2 is expected to be able to leverage off the extensive existing infrastructure including roads and power, the tailings plant operations and the already open mining benches adjacent to the current pit. Definition work is expected to be completed by the end of 2014 and approvals achieved in 2015.

 

The overall scale and mine footprint for Stage 3 - Full Mine development will also be advanced and optimised during this period of time.

 

Michael Masterman, Chairman of W, said: "A staged development, which is in line with our strategy, keeps initial mine capital costs low and provides a strong bridge from tailings to initial mining and then full scale mine development. Financing plans, including customer alliances and potential joint ventures, are proceeding in parallel with the time critical mine definition and approvals work."

 

Commenting on tailings ramp up, Michael Masterman said: "The ramp up process for the La Parrilla tailings has been an invaluable source of data and insight for the mine development planning. We have achieved target product specifications of 60%+ WO3 quickly and have identified a number of important areas for process design improvements and operating efficiencies which will need to be progressively implemented. Tailings ramp up remains a challenge, focus and priority for the management team but our progress and the obvious synergies between the tailings operation and an early stage mining operation warrant timely definition and approvals work."

 

The latest investor presentation has been uploaded on the W website at http://www.wresources.co.uk/category/investors/presentations/  and contains a schematic on the staging on page 15.

 

Recent analysts' reports from Northland and Edison (http://www.wresources.co.uk/category/media/w-news/) provide third party updates on W's progress.

 

Enquiries:

W Resources Plc

Grant Thornton UK LLP

Michael Masterman

Colin Aaronson / Melanie Frean / Jen Clarke

T: +44 (0) 20 7193 7463

T: +44 (0) 20 7383 5100

www.wresources.co.uk

SI Capital

Gable Communications

Andy Thacker / Nick Emerson

John Bick

T: +44 (0) 1483 413500

T: +44 (0) 20 7193 7463

www.sicapital.co.uk

M: +44 (0) 7872 061007

 

About La Parrilla

The La Parrilla project site is situated in the Extremadura region of southwest Spain, in the Provinces of Caceres-Badajoz, approximately 310 km southwest of Madrid. The site is accessed directly from the highway along a 3 km asphalt road and is serviced by electricity and water. The project comprises a tungsten mine and a tungsten tailings project. The mine resource estimated by Golder in June 2013 is 46.92 million tonnes at 0.09% WO3, making it one of the largest tungsten deposits in the western world.

Annual plant feed will be c330,000 tonnes and annual production is anticipated to be 450 tonnes of tungsten trioxide (WO3) and 26 tonnes of tin (Sn), which will deliver over €7million per annum in revenue at current tungsten and tin prices.

 

Technical information in this report and on the W website has been prepared in accordance with the JORC Code and approved for inclusion by Mr Fernando de la Fuente, who is a "qualified person" in respect of the AIM Rules for Companies with over 39 years' experience in the Exploration and Mining Geology industry. Mr de la Fuente holds a B.Sc. in Geology and a MSc in Geology from the University of Granada in Spain. He is also a member of the Spanish College of Geologists (Number 49), the Spanish Society of Mineralogy, founder member of the Spanish Society of Geology, member of the Spanish Association of Applied Geology to Mineral Deposits, member of the Society for Mining, Metallurgy and Exploration, Inc., member of PDAC.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUGUPCBUPCUBR
Date   Source Headline
28th Mar 20123:20 pmRNSIssue of Equity
7th Feb 20122:50 pmRNSCaspian announces £460,000 Placing
6th Feb 20129:30 amRNSOption Extension at La Parrilla Tungsten Mine
11th Jan 20127:00 amRNSDrilling Campaign Commences at La Parrilla
30th Dec 20117:00 amRNSCaspian Completes £210,000 Placing
19th Dec 201111:00 amRNSResult of General Meeting
30th Nov 20117:00 amRNSCaspian to acquire La Parrilla Tungsten Project
9th Sep 201111:48 amRNSHalf Yearly Report
1st Jul 201111:28 amRNSResult of AGM
24th Jun 201110:06 amRNSCaspian Completes £80,000 Placing
10th Jun 20117:00 amRNSAnnual Report and Notice of AGM
12th Apr 20114:51 pmRNSHolding in Company
29th Sep 20107:00 amRNSHalf Yearly Report
19th Jul 20104:50 pmRNSHolding in Company
9th Jul 201011:47 amRNSHolding in Company
7th Jul 20105:38 pmRNSDirector Shareholding
29th Jun 201011:18 amRNSResult of AGM
22nd Jun 201011:57 amRNSHolding in Company
14th Jun 20104:25 pmRNSOperational Update
14th Jun 20104:25 pmRNSCaspian Completes ?200,000 Placing
8th Jun 20103:07 pmRNSNotice of AGM and Annual Report
24th May 201011:00 amRNSFinal Results
9th Apr 20107:00 amRNSTrading Update
22nd Dec 20097:54 amRNSFirst Oil Shipment in Kentucky
30th Oct 20094:19 pmRNSIssue of Shares
12th Oct 20095:44 pmRNSStatement Regarding Share Price Movement
30th Sep 20093:45 pmRNSInterim Results
10th Jul 200911:54 amRNSTrading Update
29th Jun 200912:51 pmRNSResult of AGM and Issue of Equity
3rd Jun 20095:14 pmRNSCircular to Shareholders and Notice of AGM
28th May 20093:23 pmRNSIssue of Shares
22nd May 20093:29 pmRNSFinal Results
22nd May 20093:00 pmRNSDebt for Equity Swap Agreement
29th Apr 20099:23 amRNSTrading Update
11th Feb 200912:33 pmRNSKazakhstan Court Case Update and Trading Update
14th Jan 200912:47 pmRNSCaspian Completes ?42,000 Placement
14th Jan 20098:43 amRNSCaspian wins Initial Kazakhstan Court Case
25th Nov 200812:09 pmRNSCaspian Completes ?50,000 Placement
7th Nov 20088:42 amRNSDirectorate Change
26th Sep 200811:48 amRNSInterim Results
18th Sep 20087:00 amRNSExpands Black Gold Lease Holdings in Irvine Field
1st Sep 200812:52 pmRNSZhengeldy Regulatory Update
4th Aug 200811:27 amRNSResult of AGM
25th Jul 20087:00 amRNSDirector Shareholding
17th Jul 20081:51 pmRNSHolding in Company
9th Jul 20088:30 amRNSHolding in Company
8th Jul 200810:44 amRNSFuther Expansion into the USA
27th Jun 20088:00 amRNSApproval to Restart Productio
27th Jun 20087:00 amRNSAnnual Report and Accounts
28th May 20089:01 amRNSPlacing and USA Lease Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.