La Parrilla FTM Development Update

29 Sep 2015 11:01

RNS Number : 5387A
W Resources PLC
29 September 2015
 

 

29 September 2015

 

 

 

 

W Resources Plc

("W" or the "Company")

 

 

La Parrilla FTM Development Update

 

W Resources Plc (AIM:WRES), the tungsten, copper and gold mining, exploration, development and production company with assets located in Spain and Portugal, is pleased to provide an update on development work at its La Parrilla Fast Track Mine (FTM) located in Spain.

Strong progress has been made on the La Parrilla FTM and highlights include:

· Completion of 1,302 metres of diamond core drilling and 1,594 metres of grade control reverse circulation drilling in the FTM mining area

· Completion of the first phase of extensive metallurgical pilot testing and equipment testing

· Results to date indicate:

- Potential to reduce both capital and operating expenditures

- Potential for a 200% upgrade in WO3 content before the final concentration stages, which makes the product from La Parrilla comparable to some of the highest grade tungsten deposits globally

· Commencement of initial engineering tie in design

Assay preparation for the 2,900 metre infill and grade control programme is underway and logging results are positive. Assay results will be progressively reported in Q4 2015 and the upgraded JORC compliant mineral resource estimate is on track for issue in the next three to four months. Core and RC chip logging and analysis confirms the coarse grain "nuggetty" characteristics of the La Parrilla mineralisation, which supports low cost processing expectations.

Bulk sampling for the metallurgical programme from within the initial mining blocks has delivered grades of 0.251% for the initial 6 tonne sample. These grades are significantly higher than the design run of mine feed for the La Parrilla FTM development. The work is being conducted in leading test facilities in both Germany and Australia in order to ensure timely procurement of key long lead equipment.

Initial results from the metallurgical pilot programme continue to highlight the coarse grained nature of the ore and ease of separation at coarse sizes. In line with other global tungsten operations, pilot X-Ray ore sorting trials confirm 20% of the run of mine feed can be rejected at 25mm whilst recovering greater than 96% of the WO3. Pilot scale jig testing has confirmed 50% of the mass can be rejected during pre-concentration at 10mm whilst recovering more than 85% of the tungsten. This presents significant upside potential through reduction of both capital and operating expenditures by rejecting 60% of the run of mine feed prior to fine grinding. This provides nearly a 200% upgrade in WO3 content before final concentration stages, which makes La Parrilla project comparable in the high grade of feed to the concentrator to some of the best global tungsten projects.

In parallel to evaluating the base case process flowsheet, testing is underway to simplify the flowsheet even further. The natural brittleness (as distinct from the host rock) of scheelite presents a waste rejection opportunity, which can be efficiently exploited during processing. Further simplification of the flotation and electrostatic stages is also being investigated. These programmes aim to significantly reduce the capital and operating costs of the La Parrilla Project. The metallurgical programme is on track for completion in Q4 2015 and results will be reported shortly thereafter. Initial engineering at the La Parrilla site has commenced to define the tie-in strategy and the mechanical upgrades required to accommodate the key equipment to be added to the existing La Parrilla concentrator plant.

 

Commenting on the development programme, Mr Michael Masterman, Chairman of W Resources said: "La Parrilla continues to build momentum on the technical, approval and finance fronts. We expect strong results from both the drilling and metallurgical programmes, and project economics, which should allow us to deliver a low operational cost project. Final mining authorisation is on track for Q4 2015 and the priority of the team is on financing and development preparation."

 

 

Enquiries:

W Resources Plc

Michael Masterman

T: +44 (0) 20 7193 7463

www.wresources.co.uk

Grant Thornton UK LLP

Colin Aaronson / Jen Clarke / Harrison Clarke

T: +44 (0) 20 7383 5100

SI Capital - Joint Broker

Andy Thacker / Nick Emerson

T: +44 (0) 1483 413500

www.sicapital.co.uk

Gable Communications

Justine James

T: +44 (0) 20 7193 7463

M: +44 (0) 7525 324431

Northland Capital Partners - Joint Broker

John Howes / Abigail Wayne (Corporate Broking)

T: +44 (0) 20 7382 1100

www.northlandcp.co.uk

 

About La Parrilla

The La Parrilla project site is situated in the Extremadura region of southwest Spain, in the Provinces of Caceres-Badajoz, approximately 310 km southwest of Madrid. The site has exceptional infrastructure in place, which is accessed directly from the highway along a 3 km asphalt road and is serviced by electricity and water. The project comprises a tungsten mine and a tungsten tailings project. The mine resource estimated by Golder in June 2013 is 46.92 million tonnes at 0.09% WO3, making it one of the largest tungsten deposits in the western world.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCEAENNAEESEFF
Date   Source Headline
26th May 20227:00 amRNSCancellation - W Resources plc
25th May 202212:33 pmRNSDelisting from AIM
23rd May 20225:30 pmRNSW Resources
23rd May 20227:00 amRNSDrawdown from BlackRock Additional Loan Facility
25th Apr 20227:02 amRNSResignation of Nomad and Broker
8th Apr 202212:36 pmRNSHolding(s) in Company
5th Apr 20227:40 amRNSStatement re. Suspension
5th Apr 20227:30 amRNSSuspension - W Resources Plc
18th Mar 20227:00 amRNSLa Parrilla Update
2nd Mar 20227:00 amRNSBlackRock Additional US$5.5m Loan Facility
24th Feb 20227:00 amRNSFinance Update
18th Feb 20225:30 pmRNSFinance Update
15th Feb 202211:06 amRNSSecond Price Monitoring Extn
15th Feb 202211:01 amRNSPrice Monitoring Extension
15th Feb 20228:16 amRNSProduction Report and Finance Update
31st Jan 20227:00 amRNSTotal Voting Rights
11th Jan 20228:01 amRNSHolding(s) in Company
5th Jan 20227:00 amRNSLa Parrilla Update and Placing for £0.83m
1st Dec 202110:45 amRNSTotal Voting Rights
15th Nov 20212:12 pmRNSPlacing to Raise £750,000
1st Nov 20217:03 amRNSRégua Awarded Mining Licence and Portugal Update
21st Oct 20217:00 amRNSQ3 2021 Production Report
11th Oct 20217:00 amRNSAppointment of Non-executive Director
11th Oct 20217:00 amRNSBoard Change and Management Update
5th Oct 20215:31 pmRNSTotal Voting Rights
30th Sep 20217:00 amRNSHalf-year Report to 30 June 2021
24th Sep 20212:00 pmRNSPrice Monitoring Extension
24th Sep 20217:00 amRNSAtlas Conversion Notice & Total Voting Rights
15th Sep 20217:00 amRNSLa Parrilla Update
13th Sep 20217:00 amRNSAtlas Conversion Notice and Total Voting Rights
31st Aug 202112:00 pmRNSTotal Voting Rights
27th Aug 202111:12 amRNSPDMR Shareholding and Total Voting Rights
9th Aug 20217:00 amRNSLa Parrilla Update
4th Aug 20218:35 amRNSAtlas Conversion Notice and Total Voting Rights
15th Jul 20217:19 amRNSQ2 2021 Production Report
30th Jun 202111:58 amRNSResult of AGM
30th Jun 20217:00 amRNSTotal Voting Rights
28th Jun 20217:00 amRNSHolding(s) in Company
24th Jun 202111:30 amRNSAGM Arrangements
18th Jun 202111:43 amRNSDirector Subscription and additional share issues
16th Jun 20217:00 amRNSLa Parrilla: Completion of the 500,000m3 dam
4th Jun 20217:00 amRNSFinal Results and Notice of AGM
2nd Jun 20217:00 amRNSHolding(s) in Company
2nd Jun 20217:00 amRNSTotal Voting Rights
17th May 20214:40 pmRNSSecond Price Monitoring Extn
17th May 20214:36 pmRNSPrice Monitoring Extension
17th May 20217:00 amRNSPlacing to Raise £2.5m. Total Voting Rights
10th May 20217:00 amRNSExtremadura Government Grant Received
30th Apr 20217:00 amRNSTotal Voting Rights
23rd Apr 20217:00 amRNSLa Parrilla Management Team and Shipments Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.