Jig & Mill Plant Completed for Commissioning

16 Apr 2019 07:00

RNS Number : 3117W
W Resources PLC
16 April 2019
 

 

 

 

 

 

 

 

16 April 2019

 

W Resources Plc

("W" or the "Company")

 

Jig & Mill Plant Completed for Commissioning

Large Scale Concentrator Construction Advancing

W Resources Plc (AIM:WRES), the tungsten, copper and gold mining company with assets in Spain and Portugal, is pleased to confirm that commissioning of the Jig and Mill Plant has commenced at La Parrilla in Spain.

The Jig and Mill Plant will upgrade the La Parrilla ore, efficiently reject barren material, and prepare material for feed to the Concentrator Plant. W will feed 100% of the output of the Jig and Mill Plant once fully commissioned to the existing Concentrator Plant with upgraded and milled mine feed allowing a significant upgrade in production rates.

In parallel, the new large scale Concentrator Plant has advanced over the last three weeks with 90% of all structural steel and primary equipment now on-site and being installed (link to time lapse video - https://youtu.be/tAFIXGMv9Lg). The large Concentrator Plant is scheduled for construction completion this quarter.

The mine is primed for scale-up with preparatory grade control drilling completed and the ramp from the Fast Track Mine ("FTM") area to the Crusher Plant also completed. The first hard rock blasting of the 10m benches in the FTM area is also scheduled for this month. The mining contract will be executed this month and the mining fleet mobilisation is underway following the arrival of a Komatsu HD605 rigid truck.

Michael Masterman, Chairman of W Resources, commented: "The commencement of commissioning the La Parrilla Jig and Mill Plant following construction completion is a very important milestone as we advance to full completion of the 2 million tonne per annum plant. We expect to be able to feed crushed ore to the Jig and Mill Plant in late April and then process it through our existing Concentrator Plant. This will allow a significant increase in near term tungsten and tin production capacity and also allows us to ensure smooth autonomous operation of the Jig and Mill Plant ahead of commissioning of the new large scale Concentrator Plant later this quarter.

"The Concentrator Plant construction has accelerated rapidly following delivery of the bulk of the structural steel and is scheduled for mechanical completion this quarter. The contractor, allmineral Aufbereitungstechnik GmbH & Co. KG ("allmineral") of Germany, is on a fixed price fixed schedule contract and whilst there has been a delay in the delivery of steel which has had a negative impact on the schedule of the Jig and Mill and Concentrator Plants, there is no adverse impact on budget as the cost of the plants are fixed. Overall the project continues to track below budget including contingency."

The information communicated within this announcement is deemed to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014. Upon the publication of this announcement, this inside information is now considered to be in the public domain.

Enquiries:

W Resources Plc

Grant Thornton UK LLP

Michael Masterman

Colin Aaronson / Seamus Fricker

T: +44 (0) 20 7193 7463

T: +44 (0) 20 7383 5100

www.wresources.com

Turner Pope Investments (TPI) Ltd

Gable Communications

Andy Thacker

Justine James

T: +44 (0) 203 621 4120

T: +44 (0) 20 7193 7463

www.turnerpope.com

M: +44 (0) 7525 324431

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
MSCEALLKFFXNEEF
Date   Source Headline
7th Oct 201511:02 amRNSCAA / Portalegre Licence Expanded
30th Sep 20159:00 amRNSHalf Yearly Report
29th Sep 201511:01 amRNSLa Parrilla FTM Development Update
9th Sep 20159:17 amRNSHolding(s) in Company
26th Aug 20152:49 pmRNSChanges to Significant Shareholders
10th Aug 20157:00 amRNSRégua drilling update
14th Jul 20157:00 amRNSEnvironmental Approval for La Parrilla
10th Jul 20157:00 amRNSFast Track Mine Infill Drilling Advances
26th Jun 201511:11 amRNSPlacing and Appointment of Broker
19th Jun 20151:30 pmRNSResult of AGM
16th Jun 20157:00 amRNSLa Parrilla Definition Study Completed
5th Jun 20157:00 amRNSFast Track Mine Infill Drilling Advances
26th May 20157:01 amRNSNotice of AGM
22nd May 20157:00 amRNSFinal Results for the Year Ended 31 December 2014
12th May 20157:00 amRNSUpdate on CAA / Portalegre
28th Apr 20157:00 amRNSExcellent Drilling Results Continue at Regua
13th Apr 20159:51 amRNSBergen Facility Fully Repaid
26th Mar 20152:17 pmRNSAdditional Placing of 200,000 GBP
20th Mar 20158:39 amRNSCorrection: Repayment of Bergen Facility
20th Mar 20157:00 amRNSRepayment of Bergen Facility and Placing
9th Mar 20159:28 amRNSRegua Project Update
13th Feb 201510:59 amRNSLa Parrilla Mine and Tailings Update
6th Feb 20159:25 amRNSChanges to Significant Shareholders
20th Jan 20151:09 pmRNSPlacing to Raise £1.4m
29th Dec 201412:31 pmRNSDirector Dealing
24th Dec 201411:11 amRNSIssue of Equity
24th Dec 20147:00 amRNSLa Parrilla Operations and Development Update
18th Dec 20147:00 amRNSDirectorate Change
15th Dec 20147:00 amRNSLa Parrilla Mine Connects to Spanish Grid
4th Dec 20147:00 amRNSCAA / Portalegre Drilling Campaign Commences
24th Nov 20147:00 amRNSRegua Development Campaign Commences
19th Nov 20147:00 amRNSLa Parrilla Tailings Plant Improvement Update
4th Nov 20147:00 amRNSDirector Dealing
30th Oct 20147:00 amRNSStrong Trenching Exploration Results
27th Oct 20147:00 amRNSBergen First Closing Completed
22nd Oct 20147:00 amRNSTrading and operations update
16th Oct 201410:56 amRNSConvertible security & private placement facility
30th Sep 20147:00 amRNSInterim results to 30 June 2014
17th Sep 20147:00 amRNSTarouca Drilling Programme Completion
15th Sep 20141:15 pmRNSLa Parrilla Tailings Update
8th Sep 201410:43 amRNSLa Parrilla mine development plan
11th Aug 20147:00 amRNSFirst Tungsten Shipment Cash Proceeds
8th Aug 20145:20 pmRNSDirector Shareholding
29th Jul 20141:35 pmRNSPlacing to raise £1.2 million
28th Jul 20147:00 amRNSTarouca Drilling Update
10th Jul 20147:00 amRNSProduction Ramp-up at La Parrilla Tailings
27th Jun 20143:32 pmRNSShare transfer
23rd Jun 20147:00 amRNSTrial Mining Licence Awarded at Régua
20th Jun 201412:41 pmRNSResult of AGM
27th May 20144:44 pmRNSNotice of AGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.