Jig & Mill Plant Completed for Commissioning

16 Apr 2019 07:00

RNS Number : 3117W
W Resources PLC
16 April 2019
 

 

 

 

 

 

 

 

16 April 2019

 

W Resources Plc

("W" or the "Company")

 

Jig & Mill Plant Completed for Commissioning

Large Scale Concentrator Construction Advancing

W Resources Plc (AIM:WRES), the tungsten, copper and gold mining company with assets in Spain and Portugal, is pleased to confirm that commissioning of the Jig and Mill Plant has commenced at La Parrilla in Spain.

The Jig and Mill Plant will upgrade the La Parrilla ore, efficiently reject barren material, and prepare material for feed to the Concentrator Plant. W will feed 100% of the output of the Jig and Mill Plant once fully commissioned to the existing Concentrator Plant with upgraded and milled mine feed allowing a significant upgrade in production rates.

In parallel, the new large scale Concentrator Plant has advanced over the last three weeks with 90% of all structural steel and primary equipment now on-site and being installed (link to time lapse video - https://youtu.be/tAFIXGMv9Lg). The large Concentrator Plant is scheduled for construction completion this quarter.

The mine is primed for scale-up with preparatory grade control drilling completed and the ramp from the Fast Track Mine ("FTM") area to the Crusher Plant also completed. The first hard rock blasting of the 10m benches in the FTM area is also scheduled for this month. The mining contract will be executed this month and the mining fleet mobilisation is underway following the arrival of a Komatsu HD605 rigid truck.

Michael Masterman, Chairman of W Resources, commented: "The commencement of commissioning the La Parrilla Jig and Mill Plant following construction completion is a very important milestone as we advance to full completion of the 2 million tonne per annum plant. We expect to be able to feed crushed ore to the Jig and Mill Plant in late April and then process it through our existing Concentrator Plant. This will allow a significant increase in near term tungsten and tin production capacity and also allows us to ensure smooth autonomous operation of the Jig and Mill Plant ahead of commissioning of the new large scale Concentrator Plant later this quarter.

"The Concentrator Plant construction has accelerated rapidly following delivery of the bulk of the structural steel and is scheduled for mechanical completion this quarter. The contractor, allmineral Aufbereitungstechnik GmbH & Co. KG ("allmineral") of Germany, is on a fixed price fixed schedule contract and whilst there has been a delay in the delivery of steel which has had a negative impact on the schedule of the Jig and Mill and Concentrator Plants, there is no adverse impact on budget as the cost of the plants are fixed. Overall the project continues to track below budget including contingency."

The information communicated within this announcement is deemed to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014. Upon the publication of this announcement, this inside information is now considered to be in the public domain.

Enquiries:

W Resources Plc

Grant Thornton UK LLP

Michael Masterman

Colin Aaronson / Seamus Fricker

T: +44 (0) 20 7193 7463

T: +44 (0) 20 7383 5100

www.wresources.com

Turner Pope Investments (TPI) Ltd

Gable Communications

Andy Thacker

Justine James

T: +44 (0) 203 621 4120

T: +44 (0) 20 7193 7463

www.turnerpope.com

M: +44 (0) 7525 324431

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
MSCEALLKFFXNEEF
Date   Source Headline
25th Mar 20204:36 pmRNSPrice Monitoring Extension
16th Mar 20208:30 amRNSOngoing Operations and Covid-19 Response
10th Mar 20207:00 amRNSRégua and La Parrilla Update. Director Retirement
10th Mar 20207:00 amRNS£756,000 Placing to Spanish Investors at 0.36p
18th Feb 20207:00 amRNSNew Loan Facility and Extremadura Grant Update
5th Feb 20209:55 amRNSRégua Commencement and Updated Régua JORC Resource
20th Jan 20207:00 amRNSConversion of Directors' Loans
9th Jan 20208:33 amRNSFirst Shipment from New Concentrator Plant
8th Jan 20207:00 amRNSNon-Executive Director Appointment
18th Dec 20197:00 amRNSAdditional $5 Million Facility. La Parrilla Update
5th Dec 20197:00 amRNSFinance Update
29th Nov 20192:48 pmRNSIssue of Shares and Financing Update
28th Nov 20197:00 amRNSLa Parrilla Production Update
15th Nov 20193:05 pmRNSLa Parrilla Ramp-Up Finance Update
8th Nov 20197:03 amRNSLa Parrilla First Concentrate and Financing Update
21st Oct 20197:00 amRNSFirst Ore Fed to La Parrilla Concentrator Plant
30th Sep 20198:00 amRNSHalf-year Report to 30 June 2019
16th Sep 20197:00 amRNSEUR1m placement to Spanish Investors
9th Sep 20194:14 pmRNSCorrection - Corporate and EUR 5.3 m Grant Update
9th Sep 201910:02 amRNSCorporate and EUR 5.3 m Grant Update
29th Aug 20197:00 amRNSLa Parrilla Concentrator Construction Complete
16th Aug 201911:39 amRNSDirector/PDMR Shareholding
14th Aug 20192:48 pmRNSDirector/PDMR Shareholding
7th Aug 20197:00 amRNSLa Parrilla Tungsten & Tin Mine Update
5th Aug 20195:12 pmRNSHolding(s) in Company
28th Jun 201912:42 pmRNSResult of AGM
28th Jun 20197:00 amRNSLa Parrilla Update
19th Jun 20197:01 amRNSHaulage and Crushing Contract Signed for Régua
19th Jun 20197:00 amRNSLa Parrilla and São Martinho Update
7th Jun 20197:00 amRNSLa Parrilla Mining Contract Awarded
3rd Jun 20192:46 pmRNSNotice of AGM and Annual Report
29th May 20198:12 amRNSJoint Broker Appointment
22nd May 20197:00 amRNSExercise of Warrants by Directors
21st May 20197:00 amRNSLa Parrilla Jig Commissioned with First Ore
9th May 20197:00 amRNSAdvance on 5.3m EUR Grant through Extremadura Bank
2nd May 20197:00 amRNSLa Parrilla Update and Mine Blast
30th Apr 201911:57 amRNSFinal Results for the Year Ended 31 December 2018
29th Apr 201912:15 pmRNSMajor Shareholding Notification
18th Apr 201911:00 amRNSPrice Monitoring Extension
18th Apr 20199:31 amRNSEarly Exercise of Warrants
16th Apr 20197:00 amRNSJig & Mill Plant Completed for Commissioning
1st Apr 20197:00 amRNSHigh Grade Tungsten Intersections at Régua
18th Mar 20197:00 amRNSUpdate on La Parrilla and on Portuguese assets
5th Feb 20197:00 amRNSLa Parilla Mine Update and Issue of Shares
20th Dec 20187:00 amRNSLa Parrilla Mine's First Crushed Ore
10th Dec 20187:00 amRNSMechanical Completion of La Parrilla Crusher Plant
3rd Dec 20187:00 amRNSFirst Tungsten Shipment from the La Parrilla Mine
27th Nov 201810:50 amRNSPlacing to Raise £1.5m
23rd Nov 20187:00 amRNSTPI Investor Evening - 10 December
20th Nov 20184:19 pmRNSGrant of Share Options

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.