Lesedi Project Update

7 Feb 2022 07:00

RNS Number : 8152A
Tlou Energy Ltd
07 February 2022
 

7 February 2022

 

Tlou Energy Limited

("Tlou" or "the Company")

 

Award of 10MW Generation Licence and Project Update

 

 

Tlou is developing clean energy solutions for Botswana and the sub-Saharan region.

Key points

Ø Transmission Line construction set to commence

Ø 10MW Generation Licence awarded

 

Transmission Line

Tlou is pleased to announce that work is set to commence on the transmission line and substations to connect the Lesedi power project ("Lesedi") to the electricity grid.

 

As announced late last year, funding has been secured for the construction of the transmission line and substations from our largest shareholder (Botswana Public Officers Pension Fund) and since that time the relevant contractors have been updating their tenders to reflect any cost adjustments since their original submissions. This process is largely complete and following final signatures the work is set to commence.

 

Project Construction

The Lesedi project is located approximately 100Km from the existing electricity grid. The development will include the erection of wooden poles fitted with an overhead 66kV transmission line. In addition, substations will be installed at Lesedi and close to Serowe. The Lesedi substation will integrate the generation assets with the transmission line and the Serowe substation will tie in with Botswana Power Corporation's existing infrastructure.

The transmission line route has been surveyed and full environmental approval is in place. The line will predominantly cross flat, arid terrain with the last ~5 Km being through the outskirts of the Serowe township.

 

As previously announced, experienced contractors are being used for the project with construction of the overhead lines by Zismo Engineering (Pty) Ltd ("Zismo") and by OptiPower for the construction of substations.

 

· Zismo is a Botswana based Electrical Engineering, Contracting, Automation and Refurbishment Company. Further information is available at http://zismoengineering.com.

 

· OptiPower is a division of Murray & Roberts Ltd. Based in South Africa, OptiPower's core business includes the construction of substations, power lines and fibre optic networks. See https://optipower.co.za for further details.

 

10MW Generation Licence

The Company recently received a 10MW Electricity Generation License from the Botswana Energy Regulatory Authority (BERA).

 

The licence has a term of 15 years and is for the generation of 10MW of power at the Lesedi project for sale to Botswana Power Corporation (BPC).

 

Project Timetable

A series of key milestones have been achieved in the past year allowing the Company to progress into the development phase and towards first revenue. A tentative timetable towards this target is set out below. This is not an exhaustive list and is subject to change and funding.

 

Proposed Timetable (TL = Transmission Line; SS = Substations; H2 = Hydrogen)

Date

Detail

1Q22

TL & SS - Mobilisation of plant & equipment, site establishment, procurement and engineering

2Q22

H2 - Hydrogen & Solid Carbon Protype unit to be completed

TL & SS - Commence installation of electricity poles

Gas-to-power - Ground works on Central Processing Facility

3Q22

H2 - Hydrogen & Solid Carbon Prototype to arrive at Lesedi

SS - Civil works, steel structures assembly, installation, and earthing

Solar - Purchase and installation of Solar PV

4Q22

SS -Electrical and mechanical works

TL - Stringing, tension, and regulation

Gas-to-power - Purchase of power generators

H2 - Initial results from the Hydrogen & Solid Carbon Prototype

1H23

TL & SS - Practical completion

TL & SS - Testing and commissioning

2H23

TL & SS - Handover to Tlou

Gas-to-power - Sale of first electricity to BPC

 

Lesedi Gas production

The Lesedi gas production wells continue to steadily perform. The Lesedi 3P ("L3") production pod was shut-in for approximately 18 months during the pandemic and was recently brought back into production following the resumption of full operations. Since resumption, L3 has already recommenced flowing gas which is a very positive indicator and the Lesedi 4P ("L4") production pod also continues to flow sustained gas. Cumulative flow rates are encouraging and we look forward to providing substantive numbers to the market as soon as practicable.

 

By Authority of the Board of Directors

Mr. Anthony Gilby

Managing Director

 

The information contained within this announcement is deemed to constitute inside information as stipulated under the retained EU law version of the Market Abuse Regulation (EU) No. 596/2014 (the "UK MAR") which is part of UK law by virtue of the European Union (withdrawal) Act 2018. The information is disclosed in accordance with the Company's obligations under Article 17 of the UK MAR. Upon the publication of this announcement, this inside information is now considered to be in the public domain.

****

For further information regarding this announcement please contact:

Tlou Energy Limited

+61 7 3040 9084

Tony Gilby, Managing Director

Solomon Rowland, General Manager

Grant Thornton (Nominated Adviser)

+44 (0)20 7383 5100

Harrison Clarke, Colin Aaronson, Ciara Donnelly

Shore Capital (Broker)

+44 (0)20 7408 4090

Toby Gibbs, John More

Public Relations

Ashley Seller

+61 418 556 875

 

Forward-Looking Statements

This announcement may contain certain forward-looking statements. Actual results may differ materially from those projected or implied in any forward-looking statements. Such forward-looking information involves risks and uncertainties that could significantly affect expected results. No representation is made that any of those statements or forecasts will come to pass or that any forecast results will be achieved. You are cautioned not to place any reliance on such statements or forecasts. Those forward-looking and other statements speak only as at the date of this announcement. Save as required by any applicable law or regulation, Tlou Energy Limited undertakes no obligation to update any forward-looking statements.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDDXGDDIDGDGDL
Date   Source Headline
12th Apr 20197:00 amRNSAllotment of Placement shares
8th Apr 20197:00 amRNSAUD$1.2 million equity raising at premium
1st Apr 20197:08 amRNSNew Prospecting Licence Area
18th Mar 20197:00 amRNSField Operations Update
13th Mar 20197:00 amRNSTender Technical Stage Decision Approved
26th Feb 20197:00 amRNSInterim Results
25th Feb 20197:00 amRNSProduction testing underway at Lesedi
12th Feb 20197:00 amRNSFirst development pod successfully completed
6th Feb 20194:30 pmRNSASX query and response
23rd Jan 20197:00 amRNSOPERATIONAL REPORT - QUARTER ENDING 31 DEC 2018
15th Jan 20197:00 amRNSRecommencement of Drilling and Operational Update
4th Dec 20187:00 amRNSTop-hole drilling successfully completed at Lesedi
20th Nov 20187:00 amRNSOperations Update - Excellent Progress at Lesedi
6th Nov 20187:00 amRNSOperations Update
30th Oct 20187:00 amRNSOPERATIONAL REPORT - QUARTER ENDED 30 SEPT 2018
22nd Oct 20187:00 amRNSOperations Update
19th Oct 201812:42 pmRNSIssue of Performance Rights
17th Oct 20187:00 amRNSResults of AGM and Chairman's Address
10th Oct 20182:26 pmRNSTender Submitted
17th Sep 20187:10 amRNSOperations Update
17th Sep 20187:00 amRNSNotice of Annual General Meeting
6th Sep 20181:56 pmRNSChange to RFP submission date
30th Aug 20187:00 amRNSFinal Results
28th Aug 20187:00 amRNSConference Presentation
13th Aug 20181:26 pmRNSOperations Update and RFP bidders meeting
31st Jul 20187:00 amRNSHoldings in Company
31st Jul 20187:00 amRNSSouthern African Power Market Study
27th Jul 20187:05 amRNSGovernment Releases Re-tender of 100MW RFP
25th Jul 201811:43 amRNSOPERATIONAL REPORT - QUARTER ENDING 30 JUNE 2018
18th Jul 20182:18 pmRNSOperations Update
13th Jul 20187:00 amRNSDirectors participation in the Entitlement Offer
11th Jul 20187:00 amRNSEntitlement Offer Closes
28th Jun 20187:00 amRNSOperations Update
20th Jun 20187:38 amRNSEntitlement Offer - Dispatch of Booklet
8th Jun 20187:49 amRNSEntitlement Offer - Letters to Shareholders
6th Jun 20189:47 amRNSEquity Placement and Entitlement Offer
17th May 20187:00 amRNSCorporate Presentation
23rd Apr 20187:00 amRNSOPERATIONAL REPORT - QUARTER ENDING 31 MARCH 2018
22nd Feb 20188:02 amRNSInterim Results
20th Feb 20189:45 amRNSFurther material increase in Gas Reserves
15th Feb 201811:22 amRNS100 MW Request for tender debrief meeting
12th Feb 20184:18 pmRNSGovernment Request for Re-tender of 100MW RFP
23rd Jan 20187:00 amRNSOPERATIONAL REPORT - QUARTER ENDING 31 DECEMBER
22nd Dec 201711:53 amRNSHolding(s) in Company
20th Dec 201712:33 pmRNSHolding(s) in Company
19th Dec 20177:00 amRNSCore-hole Drilling Operations Update
18th Dec 20177:00 amRNSIssue of Shares - Performance Rights Plan
12th Dec 20177:00 amRNSListing on BSE approved and issue of share capital
4th Dec 201712:51 pmRNSExercise of Options
28th Nov 20177:00 amRNSSeismic Survey and Core-hold Operations Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.