Production testing underway at Lesedi

25 Feb 2019 07:00

RNS Number : 9331Q
Tlou Energy Ltd
25 February 2019
 

25 February 2019

 

Tlou Energy Limited

("Tlou" or "the Company")

 

Production testing underway at Lesedi

 

 

Tlou Energy Limited, the ASX, AIM and BSE listed company focused on delivering power in Botswana and southern Africa through the development of coal bed methane ('CBM'), has commenced production testing at its Lesedi 3 development pod. Excellent progress is also being made on drilling operations at the second development pod, Lesedi 4.

 

Highlights

· The Lesedi 3 development pod has been completed with surface production equipment now installed and operational;

· The Lesedi 4A lateral well has been successfully drilled;

· Drilling is underway at the Lesedi 4B lateral well, being the final well in the current program;

· The Company will provide further updates as both production testing and drilling operations progress.

 

Operations update

Drilling operations at the Lesedi 3 development pod were completed earlier this month. Production equipment has been installed and production testing is now underway. Production testing involves de-watering and lowering of the pressure in the coal seam to achieve gas flow. Testing procedures will continue over the coming months with initial performance data expected in Q2 2019.

 

Drilling has also been completed on the first of two lateral sections (Lesedi 4A) of the Lesedi 4 development pod. Lesedi 4A was drilled ~1,435m measured depth and successfully intersected with vertical production well Lesedi 4P. Drilling of the second lateral well (Lesedi 4B) is ongoing. This well is planned to be the final well in the current drilling phase. The Company will provide further updates as the drilling operations progress.

 

Background to the development well drilling program

The Company commenced drilling of development wells at its gas field in late 2018. The wells are being drilled as 'dual lateral pods', comprising a single vertical production well intersected by two lateral wells. The lateral wells are being drilled through the gassy coal seam with gas extracted from this coal produced through the vertical production well where it can be gathered and used for power generation. Pod One is designated 'Lesedi 3' and comprises a vertical production well ('Lesedi 3P') and two lateral wells ('Lesedi 3A' & 'Lesedi 3B'). Pod Two is designated 'Lesedi 4'.

 

The development drilling program is being conducted in accordance with health and safety requirements and is consistent with the Company's approved environmental impact statement. If results are positive, these wells will form part of the Company's initial gas-to-power project which will include installation of transmission lines and grid connection.

 

Other

The gas-to-power tender submitted by the Company to the government of Botswana (as per the market announcement on 10 October 2018) is still being assessed by government. The Company remains confident that an update will be provided in the near term.

 

****

For further information regarding this announcement please contact:

 

Tlou Energy Limited

+61 7 3012 9793

Tony Gilby, Managing Director

Solomon Rowland, General Manager

Grant Thornton (Nominated Adviser)

+44 (0)20 7383 5100

Samantha Harrison, Colin Aaronson, Harrison Clarke, Seamus Fricker

Shore Capital (Broker)

+44 (0) 207 408 4090

Jerry Keen, Toby Gibbs, Mark Percy

FlowComms Limited (Investor Relations)

+44 (0) 7891 677 441

Sasha Sethi

 

Company Information

Tlou Energy is focused on delivering Gas-to-Power solutions in Botswana and southern Africa to alleviate some of the chronic power shortage in the region. Tlou is developing projects using coal bed methane ('CBM') natural gas. Botswana has a significant energy shortage and generally relies on imported power and diesel generation to fulfil its power requirements. As 100% owner of the most advanced gas project in the country, the Lesedi CBM Project, Tlou Energy provides investors with access to a compelling opportunity using domestic gas to produce power and displace expensive diesel and imported power.

 

The Company is listed on the Australian Securities Exchange, London's AIM market and the Botswana Stock Exchange and is led by an experienced Board, management and advisory team including individuals with successful track records in the CBM industry.

 

Since establishment, the Company has significantly de-risked the project in consideration of its goal to become a significant gas-to-power producer. The Company flared its first gas in 2014 and has a 100% interest in a Mining Licence and nine Prospecting Licences covering an area of ~8,300 Km2 in total. The Lesedi and Mamba Projects already benefit from significant independently certified 2P gas Reserves of ~41 BCF. In addition, 3P gas Reserves of ~427 BCF and Contingent Gas Resources of ~3,044 BCF provide significant additional potential.

 

The Company is planning an initial scalable gas-to-power project. Following successful implementation of this first scalable project, the Company looks forward to evaluating longer-term prospects for the delivery of electricity generated from CBM in Botswana to neighbouring countries.

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDSEAFELFUSELE
Date   Source Headline
31st Dec 20247:00 amRNSCancellation - Tlou Energy Limited
20th Dec 20246:00 pmRNSTlou Energy
26th Nov 20247:00 amRNSResult of AGM and Update on AIM Cancellation
22nd Nov 20247:00 amRNSLesedi Project Update
7th Nov 20247:00 amRNSDirector/PDMR Shareholding
5th Nov 20247:00 amRNSHistorical RPT and New Loan Agreement
30th Oct 20247:00 amRNSQuarterly Activities Report q/e 30 September 2024
28th Oct 20247:01 amRNSNotice of AGM
28th Oct 20247:00 amRNSProposed Cancellation of Admission to AIM
26th Sep 20247:00 amRNSFinal Results
27th Aug 20247:00 amRNSNotice of GM
23rd Aug 20247:00 amRNSA$1m Placement
31st Jul 20247:00 amRNSMezzanine Debt Facility term sheet
26th Jul 20247:00 amRNSQuarterly Activities Report q/e 30 June 2024
29th Apr 20247:00 amRNSFurther Placement of Entitlement Offer Shortfall
26th Apr 20247:00 amRNSQuarterly Activities Report q/e 31 March 2024
26th Mar 20247:00 amRNSPlacement of Entitlement Offer Shortfall
8th Mar 20247:00 amRNSInterim Results
23rd Feb 20247:00 amRNSLesedi Project Update
5th Feb 20247:00 amRNSResults of Entitlement Offer
24th Jan 20247:00 amRNSQuarterly Activities Report q/e 31 December 2023
8th Jan 20247:00 amRNSNon-Renounceable Entitlement Offer Extension
22nd Dec 202311:18 amRNSResult of General Meeting
15th Dec 20237:00 amRNSNon-Renounceable Entitlement Offer
27th Nov 20237:00 amRNSFirst Gas Flow from Lesedi 6 Production Pod
24th Nov 20239:00 amRNSNotice of General Meeting
6th Nov 20237:00 amRNSA$3m Loan Agreement
31st Oct 20237:00 amRNSResults of AGM and Chairman's Address
27th Oct 20237:00 amRNSQuarterly Activities Report q/e 30 September 2023
6th Oct 20237:00 amRNSCompletion of Private Placement
29th Sep 20238:31 amRNSFinal Results
29th Sep 20237:00 amRNSNotice of AGM
11th Sep 20239:19 amRNSDate of 2023 Annual General Meeting
11th Sep 20237:00 amRNSLesedi Drilling and Project Update
25th Jul 20237:00 amRNSQuarterly Activities Report q/e 30 June 2023
22nd Jun 20233:22 pmRNSUpdate - Results of Entitlement Offer
20th Jun 20237:22 amRNSResults of Entitlement Offer
14th Jun 20237:00 amRNSDrilling and Operational Update
12th Jun 20234:23 pmRNSPublication of Supplementary Prospectus
5th Jun 20237:38 amRNSEntitlement Offer – Extension of Closing Date
23rd May 20239:43 amRNSDespatch of Prospectus to Eligible Shareholders
12th May 20237:00 amRNSPartially Underwritten Entitlement Offer
2nd May 20237:00 amRNSA$2m Loan Agreement Signed
28th Apr 20237:00 amRNSQuarterly Activities Report
13th Apr 20237:09 amRNSLesedi 6 Production Well Drilling
27th Mar 20237:13 amRNSA$200k placement
15th Mar 20237:00 amRNSGas Production Well and Core-hole Drilling
9th Mar 20237:00 amRNSInterim Results
23rd Feb 20232:25 pmRNSInterview with Proactive Investors
27th Jan 20237:00 amRNSOperational Report Quarter ended 31 December 2022

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.