The latest Investing Matters Podcast episode featuring financial educator and author Jared Dillian has been released. Listen here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksTharisa Regulatory News (THS)

Share Price Information for Tharisa (THS)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 69.00
Bid: 68.00
Ask: 70.00
Change: 0.50 (0.73%)
Spread: 2.00 (2.941%)
Open: 68.50
High: 69.00
Low: 69.00
Prev. Close: 68.50
THS Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Third quarter FY2017 Production Report

10 Jul 2017 07:00

RNS Number : 4535K
Tharisa PLC
10 July 2017
 

 

Tharisa plc

(Incorporated in the Republic of Cyprus with limited liability)

(Registration number HE223412)

JSE share code: THA

LSE share code: THS

ISIN: CY0103562118

('Tharisa')

 

Third quarter production report for the period ended 30 June 2017

Another record quarter for Tharisa

 

Highlights for the three months ended 30 June 2017

· Record quarterly reef mined of 1 275.2 kt continues to exceed the required run rate of 4.8 Mtpa on an annualised basis

· Record chrome concentrate production of 333.9 kt, up 6.1% quarter on quarter

· Record specialty chrome production of 87.1 kt, 26.1% of total chrome production and up 15.5% quarter on quarter

· PGM production of 35.4 koz, up 3.2% quarter-on-quarter

· Record PGM recoveries at 81.3% and chrome recoveries at 66.0% exceeding targeted recoveries of 80.0% and 65.0% respectively

 

Commenting on Q3 production, Tharisa CEO Phoevos Pouroulis, said:

"Tharisa Minerals has again shown incremental improvements in production volumes and recoveries. We continue to examine ways to further optimise our operations and look forward to achieving our targeted recoveries and production outlook for the financial year."

 

Safety

Safety remains a top priority and Tharisa continues to strive for zero harm at its operations. There were no lost time injuries during the quarter and consequently we recorded an improved LTIFR of 0.08 per 200 000 man hours worked.

  

Production update

The production update for the quarter ended 30 June 2017 is as follows:

 

 

Quarter ended 30 June 

2017

Quarter ended 31 March 

2017

 

Quarter on quarter movement

%

Quarter ended 30 June 2016

Nine months

ended

30 June

2017

 

 

 

 

 

 

 

Reef mined

kt

1 275.2

1 219.2

4.6 

1 235.4

3 724.3

Stripping ratio

m³ waste/m³ reef

6.9

7.5

 

7.4

7.8

Reef milled

kt

1 199.1

1 211.3

(1.0)

1 192.2

3 616.8

PGM flotation feed tonnes

kt

866.0

897.9

(3.6)

929.6

2 648.9

PGM rougher feed grade

g/t

1.57

1.56

0.6 

1.64

1.55

6E PGMs produced

koz

35.4

34.3

3.2 

33.5

104.6

PGM recovery

%

81.3

76.2

6.7 

68.5

79.3

Average PGM contained metal basket price

US$/oz

792

783

1.1

745

771

Average PGM contained metal basket price

ZAR/oz

10 443

10 355

0.8

11 162

10 352

 

 

 

 

 

 

 

Cr₂O₃ ROM grade

%

17.8

17.5

1.7 

17.7

17.6

Chrome recovery

%

66.0

62.5

5.6 

61.6

64.3

Chrome yield

%

27.8

26.0

6.9 

25.8

26.8

Chrome concentrates produced

kt

333.9

314.6

6.1 

307.1

970.7

Metallurgical grade

kt

246.8

239.2

3.2 

225.6

731.1

Specialty grades

kt

87.1

75.4

15.5 

81.5

239.6

 

 

 

 

 

 

 

Metallurgical grade chrome concentrate contract price

US$/t CIF China

147

338

(56.5)

105

212

Metallurgical grade chrome concentrate contract price

ZAR/t CIF China

1 892

4 430

(57.3)

1 589

2 844

Average exchange rate

ZAR:US$

13.2

13.2

15.0

13.5

 

 

Mining

Reef mined from the open pit totalled a record 1 275.2 kt for the quarter. This is a 5% improvement on the 1 219.2 kt mined in Q2 and brings the monthly average to 413.8 kt over the first nine months of FY2017. The increase in production is mainly attributable to a focus on continuous improvement initiatives particularly in the drill and blast operations. The benefits of these initiatives, in terms of the availability and utilisation of mining equipment, should continue into Q4.

 

Total waste of approximately 2.5 Mm3 was moved during the quarter at a stripping ratio of 6.9 on a m3:m3 basis. The waste stripping remained below the LOM average of 9.7 as the team's focus remained on interburden stripping to ensure access to the reef horizons. The lower stripping ratio was also due to the planned pit extension following the road diversion. The benefits of the shorter waste hauling distances associated with the road diversion will be delivered in the latter part of Q4. It is forecast that stripping for Q4 will be above 9 m3:m3.

 

In addition to the focus on increasing waste stripping ahead of ore mining to ensure sustained access to the reef horizons, there is a continued emphasis on mining consistent reef grades for feed into the processing plants.

  

Processing

During the quarter 1 199.1 kt of ore was milled, resulting in PGM production of 35.4 koz on a 6E basis and record chrome production of 333.9 kt, 87.1 kt (26.1%) of which are specialty grade concentrates.

The chrome feed grade improved by 2% while the 6E PGM rougher feed grade remained consistent compared to the previous quarter. The marginally lower mill throughput for Q3 was due to the timing of the planned maintenance during the quarter.

The continuous improvement initiatives focused on crusher throughput and improved crusher run time. The positive impact of these initiatives on plant throughput was evidenced towards the end of Q3 and will flow into Q4. Despite the marginally lower throughput, the total PGM and chrome production increased by 3% and 6% respectively when compared to Q2.

 

Both PGM and chrome recoveries exceeded target during the quarter with PGM recoveries at 81.3%, against a target of 80%, and chrome recoveries at 66.0%, against a target of 65%.

 

The high energy flotation successfully implemented at the Voyager PGM recovery circuit has been incorporated into the PGM recovery circuit of the Genesis Plant and is scheduled to be completed by the end of July 2017. This will contribute to improved PGM production in Q4, although production may be partially impacted by the planned oxidized ore being mined as the open pit is extended through the road diversion area.

  

Market update

The average per ounce PGM basket price for the three months ended June 2017 was US$792 (ZAR10 443), which is US$9 an ounce higher than the US$783 (ZAR10 355) price achieved in the quarter ended March 2017.

 

While contracted metallurgical grade chrome concentrate prices decreased to US$147 per tonne from US$338 per tonne, there are signs that prices have found a floor and there is increased price stability within the chrome concentrate market. Despite Chinese port stock levels of 2.46 Mt, liquidity has returned on the back of continued stainless steel demand and consumption out of China. The fundamentals of the global stainless steel market remain sound with continued growth forecast in 2017, further supporting strong demand for chrome units in the form of ferrochrome and chrome ores. Specialty chrome concentrates, which comprise 26.1% of total chrome concentrate production and which supplies the chemical and foundry markets, continue to attract a premium above the contracted metallurgical chrome concentrate prices.

  

Transition to owner mining model

Tharisa Minerals entered into a binding term sheet with MCC Contracts Proprietary Limited (MCC) on 10 May 2017 in terms of which Tharisa Minerals will purchase, subject to the fulfilment of certain conditions precedent, certain of MCC's existing equipment, strategic components, site infrastructure and spare parts, and transfer the employees currently deployed at its Tharisa Mine in South Africa.

 

On 6 July 2017, shareholders were advised that the transaction had been unconditionally approved by the South African Competition Commission. The effective date of the transaction will be the date immediately following the fulfilment or waiver, as applicable, of the remaining conditions precedent, or such later date as may be agreed between the parties. The long stop date for fulfilment of these conditions is 30 September 2017.

 

The change in the operating model is expected to have both cost and operational benefits as well as providing financial flexibility, thereby cementing Tharisa's low-cost high margin position.

  

New Mining Charter

The Mining Charter was first introduced in 2004 as a regulatory instrument aimed at initiating transformation in the South African mining sector. Tharisa Minerals complies with the requirements of the Mining Charter. The Mining Charter III was gazetted on 15 June 2017. The Group is studying and assessing the regulations and the way forward to ensure compliance. Tharisa remains committed to transformation in the mining industry.

  

Outlook

PGM and chrome production remains on track to meet the FY2017 production guidance of approximately 147.4 koz PGMs on a 6E basis and 1.3 Mt chrome concentrates, of which 300 kt will be specialty grade chrome concentrates.

 

The above information has not been reported on or reviewed by Tharisa's auditors.

 

Paphos, Cyprus

10 July 2017

 

JSE Sponsor

Investec Bank Limited

 

Investor Relations contact:

Tharisa plc

Sherilee Lakmidas

+27 11 996 3538

+27 79 276 2529

slakmidas@tharisa.com

 

Broker contacts:

Peel Hunt LLP (Joint Broker)

Matthew Armitt / Ross Allister

+44 207 7418 8900

 

BMO Capital Markets Limited (Joint Broker)

Jeffrey Couch/Neil Haycock/Thomas Rider

+44 020 7236 1010

 

Financial PR contacts:

Bobby Morse/Anna Michniewicz

+44(0) 20 7466 5000

tharisa@buchanan.uk.com

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCEANXXESLXEEF
Date   Source Headline
15th Apr 20241:30 pmRNSTransaction in Own Shares
10th Apr 20247:00 amRNSQ2 FY2024 Production Results
4th Apr 20247:08 amRNSTransaction in Own Shares
26th Mar 20247:00 amRNSUS$5 Million General Share Repurchase
22nd Feb 20247:00 amRNSResults of AGM and dividend conversion rates
23rd Jan 20247:00 amRNSChange of independent auditors - FY2024
11th Jan 20247:00 amRNSTharisa Q1 FY2024 production report
22nd Dec 20237:00 amRNSDistribution of Annual Report and Notice of AGM
21st Dec 20239:15 amRNSRetirement and appointment of INED
14th Dec 20237:00 amRNSAnnual Financial Report
13th Dec 20237:00 amRNSRelease date of Annual Results FY2023
6th Dec 20237:00 amRNSTrading Statement
17th Oct 20237:00 amRNSTharisa Q4 FY2023 Production Report
3rd Oct 20239:30 amRNSKaro Mining Holdings VFEX update 30 June 2023
28th Sep 20237:00 amRNSDirectorate Change
1st Aug 20232:15 pmRNSTransfer of treasury shares/Total voting rights
21st Jul 20232:00 pmRNSDealings by director of major subsidiary
12th Jul 20237:00 amRNS3rd Quarter Production Results
7th Jul 20232:10 pmRNSDealing in securities by directors
29th Jun 202311:00 amRNSDealings by directors and company secretary
19th May 20237:00 amRNSH1 FY2023 Results and dividend timetable
18th May 20237:00 amRNSTharisa H1FY2023 Results and Investor Presentation
16th May 20233:00 pmRNSTharisa Trading Statement H1 FY2023
13th Apr 20237:00 amRNSTharisa Production Report Q2 FY2023
11th Apr 20232:55 pmRNSDirector/PDMR Shareholding
3rd Apr 20237:00 amRNSTotal Voting Rights
27th Mar 20237:00 amRNSTHARISA SECURES $130 MILLION OFFTAKE-BASED FINANCE
23rd Feb 20238:00 amRNSResults of the AGM and dividend conversion rates
20th Feb 20237:00 amRNSDirector/PDMR Shareholding
2nd Feb 202312:00 pmRNSDirector/PDMR Shareholding
1st Feb 20232:15 pmRNSTotal Voting Rights
31st Jan 20238:00 amRNSDirector/PDMR Shareholding
11th Jan 20237:00 amRNSTharisa Production Report Q1 FY2023
22nd Dec 20227:00 amRNSNotice of AGM and no change statement
15th Dec 20229:43 amEQSTharisa ends the year in a 'net cash positive position'
12th Dec 20221:00 pmRNSKaro Project Result of private placement & listing
7th Dec 202212:00 pmRNSCONSTRUCTION COMMENCEMENT CEREMONY KARO PLATINUM
5th Dec 20227:00 amRNSAnnual Financial Report
5th Dec 20227:00 amRNSAnnual Financial Report - Results in ZAR
2nd Dec 202211:00 amRNSRelease of FY2022 results
30th Nov 20222:07 pmRNSKARO $50 million Bond issue Extension Closing date
29th Nov 20227:00 amRNSTrading FY2022
28th Oct 202211:00 amRNSKARO PLATINUM PROJECT - US$50 MILLION BOND ISSUE
24th Oct 202212:00 pmRNSLoss of life incident at Tharisa Mine
11th Oct 202212:00 pmRNSInvestorMeet - Tharisa production and Karo update
11th Oct 20227:00 amRNSProduction report Q4 FY2022
3rd Oct 20227:00 amRNSTotal Voting Rights
8th Sep 20222:00 pmRNSDealings by director of a major subsidiary
6th Sep 20223:00 pmRNSDealing in securities by Executive Chairman & CEO
12th Jul 20227:00 amRNSProduction report for Q3 FY2022

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.