George Frangeskides, Chairman at ALBA, explains why the Pilbara Lithium option ‘was too good to miss’. Watch the video here

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksTharisa Regulatory News (THS)

Share Price Information for Tharisa (THS)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 67.50
Bid: 67.00
Ask: 68.00
Change: 1.00 (1.49%)
Spread: 1.00 (1.493%)
Open: 67.50
High: 68.00
Low: 66.00
Prev. Close: 67.00
THS Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Production report for Q3 FY2022

12 Jul 2022 07:00

RNS Number : 0628S
Tharisa PLC
12 July 2022
 

Tharisa plc

(Incorporated in the Republic of Cyprus with limited liability)

(Registration number HE223412)

JSE share code: THA

LSE share code: THS

A2X share code: THA

ISIN: CY0103562118

LEI: 213800WW4YWMVVZIJM90

('Tharisa' or the 'Company')

 

PRODUCTION REPORT FOR THE THIRD QUARTER ENDED 30 JUNE 2022[1]

Tharisa, the platinum group metals (PGMs) and chrome co-producer dual-listed on the Johannesburg and London stock exchanges, announces production and cash balance numbers for Q3 FY2022.

Third Quarter Highlights

‒ Lost Time Injury Frequency Rate ('LTIFR') of 0.49 per 200 000-man hours worked

‒ Achieved 6 million fatality free shifts

‒ Strong mining and milling throughput leading to:

‒ PGM production at 42.1 koz (Q2 FY2022 44.1 koz), at a normalised rougher feed grade of 1.65 g/t (Q2 FY2022 1.74 g/t) with steady recoveries at 75.6% (Q2 FY2022 75.4%)

‒ Chrome production at 389.7 kt up from the previous quarter (Q2 FY2022 374.9 kt)

‒ Vulcan Plant ramp up reflected in steady improvement in chrome recoveries - throughput recoveries of 80% expected to be reached by year end

‒ Strong commodity prices and steady production during the quarter delivering strong cash balance increases

‒ PGM basket price of US$2 677/oz (Q2 FY2022 US$2 806/oz) down 4.6%

‒ Metallurgical grade chrome price up 39.5% at US$247/t (Q2 FY2022 US$177/t)

‒ Cash balance of US$112.6 million and a positive net cash position of US$48.0 million

‒ Successful registration of solar power project for 40-megawatt peak ('MWp') with environmental and development authority to further de-risk the operations from the dependence on the national power grid and reduce carbon emissions in line with our carbon reduction strategy

‒ Growth strategy remains firmly on track

 

Key Operating Numbers

Quarter ended 30 June 2022 

Quarter ended 31 March 2022 

Quarter on quarter movement % 

Quarter ended 30 June 2021 

Nine months ended 30 June 2022

Nine months ended 30 June 2021

Reef mined

kt

1 357.1

1 419.7

(4.4)

1 507.8

4 190.7

3 975.3

6E PGMs produced

koz

42.1

44.1

(4.5)

39.0

133.9

114.1

Chrome concentrates produced (excluding third party)

kt

389.7

374.9

3.9 

379.7

1 166.4

1 110.4

Average PGM contained metal basket price

US$/oz

2 677 

2 806

(4.6)

3 804

2 619 

3 159

Metallurgical grade chrome concentrate contract price

US$/t CIF China

247

177

39.5 

160

201

149

 

Phoevos Pouroulis, CEO of Tharisa, commented:

"The team at Tharisa has completed a commendable quarter, maintaining strong production output which, supported by the favourable commodity markets, ensures a healthy balance sheet that will allow us to continue implementing our strategy.

The global macrotrends are challenging but Tharisa Mine's life of more than sixty years gives us a strong foundation and the necessary financial resources to weather the headwinds of a tough economic climate, slowing growth, rising inflation, and weaker commodity markets.

As always, our focus remains on safety, operational excellence, and maintaining a low-cost profile. This quarter, our PGM and chrome output was strong once again, driven by the volume extracted from the Tharisa Mine open pit. Production from the Vulcan Plant is steadily increasing to nameplate capacity, proving that Tharisa's proprietary technology is working well.

With our investment in almost 10 MW of standby power generation we have had negligible disruption to our operations due to the challenges at Eskom and the subsequent power curtailments.

Notwithstanding the rail and port infrastructure challenges, the logistics team have successfully exported our chrome products via various channels and modalities.

Beyond South Africa, our growth strategy remains on track with the detailed engineering design work, upfront infrastructure, and placement of long lead capital items for the Karo Platinum project continuing to progress in parallel with the finalisation of the financing options.

Overall, this has been a supportive quarter for our organic and development growth."

 

Health & Safety

‒ The health and safety of our stakeholders remains a core value to the Company and Tharisa continues to strive for zero harm at its operations

‒ LTIFR of 0.49 per 200 000 man-hours worked

‒ Achieved 6 million fatality free shifts

Market Update

‒ The PGM market, while pricing overall lower compared to the beginning of the year, is holding up well supported by the continued tight supply-demand fundamentals of the various elements. Slowing economic growth will influence the demand side, however, slowdown in supply and no major new projects coming online within the next 24 months means any demand increase is expected to lead to price increases. Recycling continues to slow requiring shortfalls to be met from primary supply

‒ The quarter continued to be overshadowed by significant external factors including the war in Ukraine, concerns about inflationary cost pressures, supply chain constraints and zero Covid policy in China. Nonetheless, higher prices were achieved during the quarter for chrome against the backdrop of destocking of port inventory and robust ferrochrome & stainless-steel production in China. We expect a price retreat in the next quarter although implementation of various stimuli in China and / or supply disruptions would reduce the extent of such a threat

Operational Update

‒ Total reef mined of 1 357.1 kt (Q2 FY2022 1 419.7 kt)

‒ Stripping ratio of 14.2 m3: m3 (Q2 FY2022 12.7 m3: m3) ensuring flexibility is maintained and stockpile management optimised

‒ Tonnes milled maintained due to a strong mining performance while ROM stockpiles stand at two months, in line with the current mine schedule

‒ PGM output at 42.1 koz (Q2 FY2022 44.1 koz)

‒ Normalised grade at 1.65 g/t (Q2 FY2022 1.74 g/t)

‒ Recoveries at 75.6% (Q2 FY2022 75.4%)

‒ Chrome production of 389.7 kt up 3.9% from the previous quarter (Q2 FY2022 374.9 kt)

‒ Cr2O3 grade at 17.0% (Q2 FY2022 17.1%)

‒ Recoveries at 70.2% (Q2 FY2022 67.8%)

‒ Vulcan Plant technology proven to work well as overall chrome recoveries increase

Karo Platinum Update

‒ Key management positions are being filled

‒ Orders for long-lead items are being placed

‒ ESIA for concentrator and infrastructure has been submitted to the authorities

‒ Given inflationary pressures, the implementation team is reviewing the capex budgets

‒ Financing discussions continuing with multiple funding solutions being targeted

‒ National Project Status benefits being negotiated

Cash Balance and Debt Position

‒ Tharisa had a cash balance of US$112.6 million (31 March 2022 US$101.5 million) at the end of the quarter, and debt of US$64.6 million (31 March 2022 US$75.6 million) after an interim FY2022 dividend payment of US$8.8 million. The increased cash has resulted in a positive net cash position of US$48.0 million (31 March 2022 US$25.9 million)

Guidance

FY2022 production guidance maintained at between 165 koz and 175 koz PGMs (6E basis). Guidance for chrome production is reduced by 10% to between 1.55 Mt and 1.65 Mt due to lower chrome feed grade and slower Vulcan Plant ramp-up.

 

Quarter ended 30 June 2022 

Quarter ended 31 March 2022 

Quarter on quarter movement % 

Quarter ended 30 June 2021 

Nine months ended 30 June 2022

Nine months ended 30 June 2021

Reef mined

kt

1 357.1

1 419.7

(4.4)

1 507.8

4 190.7

3 975.3

Stripping ratio

m3: m3

14.2

12.7

11.8 

10.9

12.6

11.3

Reef milled

kt

1 367.1

1 362.2

0.4 

1 413.1

4 161.4

4 171.9

PGM flotation feed

kt

1 051.4

1 045.7

0.5 

1 072.3

3 166.4

3 176.5

PGM rougher feed grade

g/t

1.65

1.74

(5.2)

1.52

1.71

1.46

PGM recovery

%

75.6

75.4

0.3 

74.4

76.8

76.8

6E PGMs produced

koz

42.1

44.1

(4.5)

39.0

133.9

114.1

Platinum

koz

23.1

24.3

(4.9)

21.8

73.9

63.1

Palladium

koz

7.2

7.4

(2.7)

5.5

22.1

17.7

Rhodium

koz

4.0

4.2

(4.8)

3.9

12.8

11.1

Average PGM contained metal basket price

US$/oz

2 677 

2 806

(4.6)

3 804

2 619 

3 159

Platinum

US$/oz

958

1 026

(6.6)

1 185

994

1 105

Palladium

US$/oz

2 100

2 312

(9.2)

2 794

2 117

2 588

Rhodium

US$/oz

15 755

17 023

(7.4)

24 232

15 370

19 999

Average PGM contained metal basket price

ZAR/oz

41 531

42 784

(2.9)

53 801

40 299

46 733

Cr2O3 ROM grade

%

17.0

17.1

(0.6)

18.0

17.4

17.9

Chrome recovery

%

70.2

67.8

3.5 

63.0

67.8

62.8

Chrome yield

%

28.5

27.5

3.6 

26.9

28.0

26.6

Chrome concentrates produced (excluding third party)

kt

389.7

374.9

3.9 

379.7

1 166.4

1 110.4

Metallurgical grade

kt

307.0

295.0

4.1 

280.8

907.3

832.2

Specialty grades

kt

82.7

79.9

3.5 

98.9

259.1

278.2

Third party chrome production

kt

47.4

53.4

(11.2)

59.0

150.0

170.6

Metallurgical grade chrome concentrate contract price

US$/t CIF China

247

177

39.5 

160

201

149

Metallurgical grade chrome concentrate contract price

ZAR/t CIF China

3 900 

2 700

44.4 

2 274

3 112

2 220

Average exchange rate

ZAR:US$

15.6

15.2

2.6 

14.1

15.4

14.9

 

Paphos, Cyprus

 

12 July 2022

 

JSE Sponsor

Investec Bank Limited

Connect with us on LinkedIn and Twitter to get further news and updates about our business.

 

Investor Relations Contacts:

Ilja Graulich (Head of Investor Relations and Communications)

+27 11 996 3500

+27 83 604 0820

igraulich@tharisa.com

 

Financial PR Contacts:

Bobby Morse / Ariadna Peretz

+44 207 466 5000

tharisa@buchanan.uk.com 

 

Broker Contacts:

Peel Hunt LLP (UK Joint Broker)

Ross Allister / David McKeown / Alexander Allen

+44 207 7418 8900

 

 

BMO Capital Markets Limited (UK Joint Broker)

Thomas Rider / Pascal Lussier Duquette / Nick Macann

+44 207 236 1010

 

Berenberg (UK Joint Broker)

Matthew Armitt / Jennifer Lee / Detlir Elezi

+44 203 207 7800

 

Nedbank Limited (acting through its Corporate and Investment Banking division) (RSA Broker)

Carlyle Whittaker

+27 11 294 0061

 

About Tharisa

Tharisa is an integrated resource group critical to the energy transition and decarbonisation of economies. It incorporates mining, processing, exploration, and the beneficiation, marketing, sales, and logistics of PGMs and chrome concentrates, using innovation and technology as enablers. Its principal operating asset is the Tharisa Mine located in the south-western limb of the Bushveld Complex, South Africa. The mechanised mine has a 20-year open-pit life and the ability to extend operations underground by at least an additional 40 years. Tharisa also owns Karo Mining Holdings and Salene Chrome, development stage, low-cost, open-pit PGM and chrome assets respectively, located on the Great Dyke in Zimbabwe. The Company is committed to reducing its carbon emissions by 30% by 2030 and the development of a roadmap is continuing to be net carbon neutral by 2050. Tharisa plc is listed on the Johannesburg Stock Exchange (JSE: THA) and the Main Board of the London Stock Exchange (LSE: THS).


[1] Tharisa's financial year begins 01 October and ends on 30 September.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
DRLSFSFLFEESESW
Date   Source Headline
15th Apr 20241:30 pmRNSTransaction in Own Shares
10th Apr 20247:00 amRNSQ2 FY2024 Production Results
4th Apr 20247:08 amRNSTransaction in Own Shares
26th Mar 20247:00 amRNSUS$5 Million General Share Repurchase
22nd Feb 20247:00 amRNSResults of AGM and dividend conversion rates
23rd Jan 20247:00 amRNSChange of independent auditors - FY2024
11th Jan 20247:00 amRNSTharisa Q1 FY2024 production report
22nd Dec 20237:00 amRNSDistribution of Annual Report and Notice of AGM
21st Dec 20239:15 amRNSRetirement and appointment of INED
14th Dec 20237:00 amRNSAnnual Financial Report
13th Dec 20237:00 amRNSRelease date of Annual Results FY2023
6th Dec 20237:00 amRNSTrading Statement
17th Oct 20237:00 amRNSTharisa Q4 FY2023 Production Report
3rd Oct 20239:30 amRNSKaro Mining Holdings VFEX update 30 June 2023
28th Sep 20237:00 amRNSDirectorate Change
1st Aug 20232:15 pmRNSTransfer of treasury shares/Total voting rights
21st Jul 20232:00 pmRNSDealings by director of major subsidiary
12th Jul 20237:00 amRNS3rd Quarter Production Results
7th Jul 20232:10 pmRNSDealing in securities by directors
29th Jun 202311:00 amRNSDealings by directors and company secretary
19th May 20237:00 amRNSH1 FY2023 Results and dividend timetable
18th May 20237:00 amRNSTharisa H1FY2023 Results and Investor Presentation
16th May 20233:00 pmRNSTharisa Trading Statement H1 FY2023
13th Apr 20237:00 amRNSTharisa Production Report Q2 FY2023
11th Apr 20232:55 pmRNSDirector/PDMR Shareholding
3rd Apr 20237:00 amRNSTotal Voting Rights
27th Mar 20237:00 amRNSTHARISA SECURES $130 MILLION OFFTAKE-BASED FINANCE
23rd Feb 20238:00 amRNSResults of the AGM and dividend conversion rates
20th Feb 20237:00 amRNSDirector/PDMR Shareholding
2nd Feb 202312:00 pmRNSDirector/PDMR Shareholding
1st Feb 20232:15 pmRNSTotal Voting Rights
31st Jan 20238:00 amRNSDirector/PDMR Shareholding
11th Jan 20237:00 amRNSTharisa Production Report Q1 FY2023
22nd Dec 20227:00 amRNSNotice of AGM and no change statement
15th Dec 20229:43 amEQSTharisa ends the year in a 'net cash positive position'
12th Dec 20221:00 pmRNSKaro Project Result of private placement & listing
7th Dec 202212:00 pmRNSCONSTRUCTION COMMENCEMENT CEREMONY KARO PLATINUM
5th Dec 20227:00 amRNSAnnual Financial Report
5th Dec 20227:00 amRNSAnnual Financial Report - Results in ZAR
2nd Dec 202211:00 amRNSRelease of FY2022 results
30th Nov 20222:07 pmRNSKARO $50 million Bond issue Extension Closing date
29th Nov 20227:00 amRNSTrading FY2022
28th Oct 202211:00 amRNSKARO PLATINUM PROJECT - US$50 MILLION BOND ISSUE
24th Oct 202212:00 pmRNSLoss of life incident at Tharisa Mine
11th Oct 202212:00 pmRNSInvestorMeet - Tharisa production and Karo update
11th Oct 20227:00 amRNSProduction report Q4 FY2022
3rd Oct 20227:00 amRNSTotal Voting Rights
8th Sep 20222:00 pmRNSDealings by director of a major subsidiary
6th Sep 20223:00 pmRNSDealing in securities by Executive Chairman & CEO
12th Jul 20227:00 amRNSProduction report for Q3 FY2022

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.