Nimba Iron Ore Continues To Yield High Grades

24 Oct 2012 07:00

RNS Number : 3504P
Sable Mining Africa Limited
24 October 2012
 



Sable Mining Africa Ltd / Index: AIM / Epic: SBLM / Sector: Natural Resources

24 October 2012

Sable Mining Africa Limited ('Sable Mining' or 'the Company')

Nimba Iron Ore Project Continues To Yield High Grade Results

 

Sable Mining Africa Limited, the AIM listed exploration company, is pleased to announce further positive assay results from the Company's resource drilling campaign at the 123.5 sq km Nimba Iron Ore Project ('Nimba') in southeast Guinea.

 

Highlights:

·; Best grade of 64.69% Fe over a drilled width of 25.20m

·; Additional grades include:

o 30.81m at 61.05% Fe

o 25.42m at 63.63% Fe

o 21.00m at 60.43% Fe

·; Combined weighted average returned for thirteen Plateau 2 holes of 19.83m at 61.52% Fe

·; Importantly low contaminants continue with average contents of 3.58% SiO2, 2.85% Al2O3 and 0.09% P

·; Direct Shipping Ore ('DSO') potential of Nimba further reinforced by latest results

·; Drilling on-going and remains focussed on targeting additional haematite bearing intersections of canga material

 

Sable Mining CEO Andrew Groves said, "Nimba continues to yield excellent results which continue to suggest that Nimba is one of the premier DSO iron ore projects currently being independently developed in West Africa. The high grade nature, scale and proximity to infrastructure underpin the quality of this project and we look forward to the publication of a JORC resource for Plateau 2, one of three currently being targeted."

 

The current diamond drilling campaign commenced in April 2012, with these results reporting from a further eighteen holes. 16 of the 18 returned assays are from Plateau 2, with two results coming from Plateau 3. To date, the Company has reported on 54 holes from Nimba with results highlighting the high grade nature and DSO potential of the project, and underpinning the current exploration target of up to 200Mt of canga material.

 

Plateau 2:

 

The 35 sq km Plateau 2 remains the primary area of focus for the publication of a maiden resource. Of the 16 results returned for Plateau 2, 10 (P2.12-026, 029, 034 and 038 to 045) were from holes drilled into the main channel fill area of Target 1 (T1, also known as the 'Planetaya'). This is one of three areas being targeted on Plateau 2.

 

Two holes (P2.12-023 and 025) were drilled into the second target area on Plateau 2 ('T2'). These returned intersections of 16.50m and 21.00m at 58.97% Fe and 60.43% Fe respectively, both of which highlight the potential of this area for quality tonnage.

 

In addition one result was returned from a single hole (P2.12-033) drilled to test the potential of the third of the Plateau 2 target areas ('T3'). The Board believes this area also looks highly prospective with a drilled width of 25.10m being returned at a grade of 58.42% Fe.

Current drilling continues to focus on area T1, the first of the three channel fill canga targets on Plateau 2, where the Company is targeting a JORC compliant Maiden Resource by Q1 2013. The Board continues to believe these three areas combined have the potential to host in excess of 100Mt of high grade detrital canga material.

 

The results of these holes are summarised in Table 1 (thicknesses quoted are drilled widths):

 

Table 1 Assay Results for Plateau 2 Channel Canga zones, Nimba licence (Analysis by ALS Laboratories, Ireland for diamond drill hole composites)

 

BH ID

AREA DRILLED

FROM

TO

THICK (M)

% FE

%SiO2

%Al2O3

% P

P2.12-026

Channel edge T1

0.00

8.00

8.00

62.86

2.01

3.07

0.06

P2.12-029

Channel edge T1

0.00

3.67

3.67

61.17

3.37

2.69

0.09

P2.12-034

Channel T1

0.00

25.20

25.20

64.69

1.41

1.52

0.08

P2.12-038

Channel T1

0.00

25.42

25.42

63.63

1.40

2.18

0.09

P2.12-039

Channel T1

0.00

30.81

30.81

61.05

4.98

2.44

0.08

P2.12-041

Channel T1

0.00

26.90

26.90

61.37

4.07

2.97

0.12

P2.12-042

Channel T1

0.00

16.52

16.52

63.58

1.58

2.69

0.09

P2.12-043

Channel T1

0.00

14.05

14.05

56.90

3.47

7.03

0.09

P2.12-044

Channel T1

0.00

28.10

28.10

61.98

2.66

2.87

0.12

P2.12-045

Channel T1

0.00

16.50

16.50

63.74

1.66

2.58

0.08

P2.12-023

Channel edge T2

0.00

16.50

16.50

58.97

6.56

4.14

0.06

P2.12-025

Channel T2

0.00

21.00

21.00

60.43

4.64

2.41

0.08

P2.12-033

Channel T3

0.00

25.10

25.10

58.42

7.05

2.62

0.11

Weighted Average

19.83

61.52

3.58

2.85

0.09

 

The 13 drill holes completed in the channel zones of Target 1, 2 and 3 on Plateau 2 returned a combined weighted average of 61.52% Fe over an average drilled width of 19.83m. Contaminants were low, averaging 3.58% SiO2, 2.85% Al2O3 and 0.09% P.

In addition to the main canga channel fill being targeted, the drilling campaign has also continued to test the plateau between the primary targets for additional beneficiable material. Table 2 summarises the assay results of three additional holes designed to test these areas (thicknesses quoted are drilled widths):

Table 2 Assay Results for Plateau 2 Inter-channel Canga zones, Nimba licence (Analysis by ALS Laboratories, Ireland for diamond drill hole composites)

BH ID

AREA DRILLED

FROM

TO

THICK (M)

% FE

%SiO2

%Al2O3

% P

P2.12-024

Interchannel

0.00

2.50

2.50

45.81

8.71

12.58

0.07

P2.12-027

Interchannel

0.00

5.40

5.50

46.55

4.93

15.41

0.10

P2.12-028

Interchannel

0.00

12.29

12.29

49.87

10.73

9.56

0.06

Weighted average

6.76

48.47

8.91

11.51

0.07

 

Plateau 3:

 

The Company is very encouraged by the results returned for the initial drill holes on Plateau 3, where the two holes completed P3.12-001 and 002 returned a combined weighted average of 62.86% Fe over an average drilled width of 10.88m. As can be seen from Table 3 the first two holes completed have low contaminants, with 1.27% SiO2, 2.70%Al2O3 and 0.07%P respectively.

 

Table 3 Assay Results for Plateau 3

 

BH ID

AREA DRILLED

FROM

TO

THICK (M)

% FE

%SiO2

%Al2O3

% P

P3.12-001

Channel

0.00

12.15

12.15

64.47

0.96

1.74

0.06

P3.12-002

Channel

0.00

9.60

9.60

60.81

1.65

3.92

0.07

Weighted average

10.88

62.86

1.27

2.70

0.07

Note P3.12-001 was stopped early because of bad ground conditions

The Company has also completed a series of four metallurgical holes from the first channel canga target on Plateau 2. The metallurgical samples have been shipped to Amdel Pty Ltd's metallurgical laboratory in West Australia where the cores will undergo the requisite suite of tests required in anticipation of the planned JORC compliant Competent Persons Report ('CPR'). The latter will be undertaken by the recently appointed Xstract Mining Consultants, an Australia-based consultancy group (a wholly-owned subsidiary of the Calibre Group, the engineering services group) with significant expertise in iron ore. Ongoing work has included the drilling of industry standard 'twinned holes' designed to investigate lateral continuity and variations in sample recovery in the main ore bearing lithologies. 

The information in this announcement that relates to Mineral Exploration results and Mineral Resources, together with any related assessments and interpretations have been reviewed by Mark Biddulph, a qualified geologist. Mark Biddulph has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a qualified person as defined by the AIM Note for Mining and Oil & Gas Companies.

 

** ENDS **

For further information please visit www.sablemining.com or contact:

Andrew Groves

Sable Mining Africa Ltd

Tel: 020 7408 9200

Jonathan Wright

Seymour Pierce Ltd

Tel: 020 7107 8000

David Foreman

Seymour Pierce Ltd

Tel: 020 7107 8000

Richard Greenfield

GMP Securities

Tel: 020 7647 2836

Susie Geliher

St Brides Media & Finance Ltd

Tel: 020 7236 1177

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCXXLFLLBFXFBE
Date   Source Headline
7th Oct 201612:46 pmRNSResult of EGM
30th Sep 20167:00 amRNSPreliminary Results
14th Sep 201612:40 pmRNSSuspension - Sable Mining Africa Limited
14th Sep 201612:40 pmRNSResult of AGM and Notice of EGM
9th Aug 20164:00 pmRNSNotice of AGM
13th Jun 20161:16 pmRNSResponse to Media Speculation
3rd Jun 20164:02 pmRNSHolding(s) in Company
26th May 201611:14 amRNSResponse to Media Speculation
22nd Dec 20157:00 amRNSInterim Results
15th Dec 20154:35 pmRNSPrice Monitoring Extension
14th Dec 20154:35 pmRNSPrice Monitoring Extension
1st Dec 20157:00 amRNSBlock Listing Six Monthly Return
28th Sep 20157:00 amRNSPosting of Report & Accounts
21st Sep 20157:00 amRNSMoU on Zimbabwean Coal Power Station Development
28th Aug 20157:00 amRNSFinal Results
27th Aug 20157:00 amRNSSale of non-core assets for US$1.98 million
29th Jul 20157:01 amRNSMetallurgical Results at Nimba Iron Ore Project
20th Jul 20155:30 pmRNSHolding(s) in Company
18th Jun 20155:10 pmRNSResult of AGM
1st Jun 20157:00 amRNSBlock Listing Six Monthly Return
14th May 20157:00 amRNSNotice of AGM
18th Feb 20152:00 pmRNSHolding(s) in Company
4th Feb 20157:00 amRNSSignificant DSO Tonnage Increase at Nimba Project
26th Jan 20157:00 amRNSAgreement to Utilise Established Rail Corridor
23rd Jan 201510:30 amRNSStatement Regarding Share Price Movement
5th Jan 20154:40 pmRNSSecond Price Monitoring Extn
5th Jan 20154:35 pmRNSPrice Monitoring Extension
5th Jan 20154:01 pmRNSHolding(s) in Company
24th Dec 201412:40 pmRNSSecond Price Monitoring Extn
24th Dec 201412:35 pmRNSPrice Monitoring Extension
22nd Dec 20147:00 amRNSInterim Results
1st Dec 20147:00 amRNSBlock Listing Six Monthly Return
9th Oct 201411:17 amRNSMarket Update
7th Oct 20147:00 amRNSDirectorate Change
1st Oct 20144:40 pmRNSSecond Price Monitoring Extn
1st Oct 20144:35 pmRNSPrice Monitoring Extension
29th Sep 20143:00 pmRNSPosting of Annual Report & Accounts
17th Sep 20144:35 pmRNSPrice Monitoring Extension
17th Sep 20147:00 amRNSFinal Results
28th Aug 20144:40 pmRNSSecond Price Monitoring Extn
28th Aug 20144:35 pmRNSPrice Monitoring Extension
26th Aug 20144:40 pmRNSSecond Price Monitoring Extn
26th Aug 20144:35 pmRNSPrice Monitoring Extension
9th Jun 20144:40 pmRNSSecond Price Monitoring Extn
9th Jun 20144:35 pmRNSPrice Monitoring Extension
3rd Jun 20147:00 amRNSBlock Listing Six Monthly Return
30th May 20144:35 pmRNSPrice Monitoring Extension
13th May 20141:00 pmRNSResult of AGM
30th Apr 20144:40 pmRNSSecond Price Monitoring Extn
30th Apr 20144:35 pmRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.