Turbine Construction Contract with Lockheed Martin

30 Mar 2015 07:00

RNS Number : 7835I
Atlantis Resources Limited
30 March 2015
Β 

30 March 2015

Β 

ATLANTIS RESOURCES LIMITED

("Atlantis" or the "Company")

Β 

Turbine Construction Contract with Lockheed Martin

Β 

Atlantis, majority owner of the world's largest tidal stream energy project, MeyGen, announces today that it has executed a construction contract with global defence contractor Lockheed Martin, for the delivery of Atlantis' new 1.5 megawatt AR1500 turbine to fulfil the Company's MeyGen project turbine supply obligations. The 18 metre rotor diameter AR1500 turbine, scheduled for delivery dockside in Scotland in 2016, will be one of the largest capacity single rotor turbines ever built. The AR1500 turbine will have an active rotor pitching system and full nacelle yawing capability.

Β 

The Lockheed Martin turbine construction contract scope includes the manufacture of the steel turbine housing, the assembly of all the turbine modules (including the gearbox and generator) and the systems integration and quality assurance of the overall turbine delivery programme. Lockheed and Atlantis are working with the supply chain in Scotland to maximise local content for the AR1500.

Β 

This announcement marks the latest step in the Atlantis - Lockheed Martin relationship and builds on Lockheed Martin's contribution under the AR1500 detailed design contract. The yaw drive and variable pitch system that will be integrated into the AR1500 are being developed and manufactured by Lockheed Martin as part of their commitment under the existing technology partnership teaming agreement struck between Atlantis and Lockheed in 2013.

Β 

Atlantis is also pleased to announce that contractors will today commence horizontal directional drilling operations at the MeyGen site in Caithness, to create the bores for the cables which will link the onshore site at Ness of Quoys with the four subsea turbines. Construction works have been underway at the onshore site since January to prepare the necessary infrastructure for this important phase of the project.

Β 

Β 

Tim Cornelius, CEO of Atlantis, commented:

Β 

"This new multi-million pound contract with Lockheed Martin further develops the strong relationship that exists between the two companies who are at the forefront of tidal power generation. Lockheed Martin has been a strong partner and supporter of Atlantis for a number of years and we look forward to continuing to work alongside this global technology giant as we continue to deliver turbine systems for installation on the MeyGen project going forward. "

Β 

Β 

For further information please contact:

Β 

Atlantis Resources Limited

via FTI Consulting

Tim Cornelius, Chief Executive Officer

Duncan Black, Chief Financial Officer

Peel Hunt LLP (Nominated Adviser and Broker)

+44 (0) 20 7418 8900

Daniel Harris / Jock Maxwell MacDonald

FTI Consulting

+44 (0) 20 3727 1000

Ben Brewerton / Alex Beagley / Stephanie Blott / James Styles

Β 

Β 

Atlantis names Lockheed Martin as principal contractor to deliver AR1500 turbine to the MeyGen tidal power project

Β 

Β· Lockheed Martin awarded construction contract to build Atlantis' new 1.5MW AR1500 tidal turbine for the MeyGen project.

Β 

Β· Atlantis boosts strong partnership following initial collaboration on design optimisation of the AR1500.

Β 

Β· Construction continues on theΒ 398MW MeyGen project as horizontal drilling operations commence on-site.

Β 

Β 

Atlantis, majority owner of the world's largest tidal stream energy project, MeyGen, announces today that it has executed a construction contract with global defence contractor Lockheed Martin for the delivery of Atlantis' new 1.5 megawatt AR1500 turbine to fulfil the Company's MeyGen project turbine supply obligations.

Β 

The 18 metre rotor diameter AR1500 turbine, scheduled for delivery dockside in Scotland in 2016, will be one of the largest capacity single rotor turbines ever built. The AR1500 turbine will have anΒ active rotor pitching system and full nacelle yawing capability.

Β 

The Lockheed Martin turbine construction contract scope includes the manufacture of the steel turbine housing, the assembly of all the turbine modules (including the gearbox and generator) and the systems integration and quality assurance of the overall turbine delivery programme. Lockheed and Atlantis are working with the supply chain in Scotland to maximise local content for the AR1500.

Β 

This announcement marks the latest step in the Atlantis - Lockheed Martin relationship and builds on Lockheed Martin's contribution under the AR1500 detailed design contract. The yaw drive and variable pitch system that will be integrated into the AR1500 are being developed and manufactured by Lockheed Martin as part of their commitment under the existing technology partnership teaming agreement struck between Atlantis and Lockheed inΒ 2013.

Β 

Tim Cornelius, CEO of Atlantis, commented:

Β 

"This new multi-million pound contract with Lockheed Martin further develops the strong relationship that exists between the two companies who are at the forefront of tidal power generation. Lockheed Martin has been a strong partner and supporter of Atlantis for a number of years and we look forward to continuing to work alongside this global technology giant as we continue to deliver turbine systems for installation on the MeyGen project going forward."

Β 

Atlantis has also announced that contractors have commenced horizontal directional drilling operations at the MeyGen site in Caithness, to create the bores for the cables which will link the onshore site at Ness of Quoys with the four subsea turbines. Each of the four bores will be approximately 550m long, and is designed to contain a 4.4kV cable through which tidally generated energy can be exported from the turbines to the onshore grid connection. The drilling is expected to take four months and will be carried out by Manchester-based O'Connor Utilities Ltd. Construction works have been underway at the onshore site since January to prepare the necessary infrastructure for this important phase of the project.

Β 

MeyGen was one of the first tidal projects in the world to secure the necessary planning consent, lease agreement, grid connection and power purchase agreement in order to begin onshore and offshore construction. Construction of the first phase of the project is expected to take place throughout 2015 and 2016, with first power being delivered to the grid for sale in 2016.

Β 

This information is provided by RNS
The company news service from the London Stock Exchange
Β 
END
Β 
Β 
CNTPGUMCWUPAPUB
Date   Source Headline
31st Aug 20177:00 amRNSMeyGen Operation & Production Update
4th Aug 20177:00 amRNSManagement Change
25th Jul 20177:00 amRNSOcean energy Bond reaches full subscription
10th Jul 20177:00 amRNSMeyGen Operations Update
3rd Jul 20179:29 amRNSBond has achieved minimum subscription amount
29th Jun 201711:47 amRNSResult of Annual General Meeting
28th Jun 20179:18 amRNSBond breaks opening day subscription record
27th Jun 20177:00 amRNSLaunch of Bond
19th Jun 20177:00 amRNSWyre Tidal Project
15th Jun 20177:00 amRNSProposed Bond Launch
1st Jun 201710:33 amRNSHolding(s) in Company
31st May 20177:00 amRNSFinal Results
24th May 20177:00 amRNSResult of Placing
23rd May 20175:15 pmRNSProposed Placing
12th May 20178:13 amRNSStrategic Partnership Agreement with Hyundai
10th Apr 20177:00 amRNSMeyGen Update
29th Mar 20177:00 amRNSSupplier Agreement for Indonesian Tidal Power
23rd Mar 20177:00 amRNSMeyGen Phase 1A approaches 400MWh of generation
16th Mar 20177:00 amRNSAtlantis targeting French tidal power market
6th Mar 20177:00 amRNSMeyGen Update
24th Feb 20177:00 amRNSMeyGen Update
20th Feb 20177:00 amRNSAR1500 Turbine Deployed in Record Time at MeyGen
10th Feb 20177:00 amRNSAtlantis joins forces with Natural Energy Wyre
26th Jan 20177:00 amRNSAtlantis Energy joins forces with Ideol
20th Jan 20177:00 amRNSAppointment of Joint Broker
11th Jan 20177:00 amRNSAtlantis to establish new internal division
9th Jan 20177:00 amRNSAward of EUR20.3m grant from European Commission
15th Dec 20167:00 amRNSInvestment decision for Project Stroma - MeyGen
6th Dec 20169:13 amRNSMeyGen Update
15th Nov 20167:00 amRNSMeyGen Update - First Power Generation
9th Nov 20161:00 pmRNSResponse to BEIS statement on CfD
26th Oct 20167:00 amRNSMeyGen Update
7th Oct 20161:32 pmRNSMeyGen Update
30th Sep 20167:03 amRNSGrant of awards to Director
30th Sep 20167:02 amRNSSurrender of awards by a Director
30th Sep 20167:00 amRNSInterim Results
12th Sep 20167:00 amRNSOfficial Unveiling of MeyGen Project
9th Aug 20163:16 pmRNSCompletion of DEME Investment in TPSL
7th Jul 201611:50 amRNSOEEconfirms No implications for existing EUfunding
7th Jul 20167:00 amRNSMeyGen signs deal to combine wind and tidal power
30th Jun 201612:16 pmRNSResult of AGM
21st Jun 20167:00 amRNSMeyGen Project Energised at Ness of Quoys
20th Jun 20167:00 amRNSChange of Registered Office
27th May 20167:00 amRNSFinal Results
9th May 20167:00 amRNSCompletion of Acquisition
29th Apr 20167:00 amRNSTotal Voting Rights
27th Apr 20169:46 amRNSHolding(s) in Company
27th Apr 20169:45 amRNSHolding(s) in Company
20th Apr 20167:00 amRNSPlacing and Trading Update
11th Apr 20167:00 amRNSInvestment by DEME Concessions NV

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.