Turbine Construction Contract with Lockheed Martin

30 Mar 2015 07:00

RNS Number : 7835I
Atlantis Resources Limited
30 March 2015
 

30 March 2015

 

ATLANTIS RESOURCES LIMITED

("Atlantis" or the "Company")

 

Turbine Construction Contract with Lockheed Martin

 

Atlantis, majority owner of the world's largest tidal stream energy project, MeyGen, announces today that it has executed a construction contract with global defence contractor Lockheed Martin, for the delivery of Atlantis' new 1.5 megawatt AR1500 turbine to fulfil the Company's MeyGen project turbine supply obligations. The 18 metre rotor diameter AR1500 turbine, scheduled for delivery dockside in Scotland in 2016, will be one of the largest capacity single rotor turbines ever built. The AR1500 turbine will have an active rotor pitching system and full nacelle yawing capability.

 

The Lockheed Martin turbine construction contract scope includes the manufacture of the steel turbine housing, the assembly of all the turbine modules (including the gearbox and generator) and the systems integration and quality assurance of the overall turbine delivery programme. Lockheed and Atlantis are working with the supply chain in Scotland to maximise local content for the AR1500.

 

This announcement marks the latest step in the Atlantis - Lockheed Martin relationship and builds on Lockheed Martin's contribution under the AR1500 detailed design contract. The yaw drive and variable pitch system that will be integrated into the AR1500 are being developed and manufactured by Lockheed Martin as part of their commitment under the existing technology partnership teaming agreement struck between Atlantis and Lockheed in 2013.

 

Atlantis is also pleased to announce that contractors will today commence horizontal directional drilling operations at the MeyGen site in Caithness, to create the bores for the cables which will link the onshore site at Ness of Quoys with the four subsea turbines. Construction works have been underway at the onshore site since January to prepare the necessary infrastructure for this important phase of the project.

 

 

Tim Cornelius, CEO of Atlantis, commented:

 

"This new multi-million pound contract with Lockheed Martin further develops the strong relationship that exists between the two companies who are at the forefront of tidal power generation. Lockheed Martin has been a strong partner and supporter of Atlantis for a number of years and we look forward to continuing to work alongside this global technology giant as we continue to deliver turbine systems for installation on the MeyGen project going forward. "

 

 

For further information please contact:

 

Atlantis Resources Limited

via FTI Consulting

Tim Cornelius, Chief Executive Officer

Duncan Black, Chief Financial Officer

Peel Hunt LLP (Nominated Adviser and Broker)

+44 (0) 20 7418 8900

Daniel Harris / Jock Maxwell MacDonald

FTI Consulting

+44 (0) 20 3727 1000

Ben Brewerton / Alex Beagley / Stephanie Blott / James Styles

 

 

Atlantis names Lockheed Martin as principal contractor to deliver AR1500 turbine to the MeyGen tidal power project

 

· Lockheed Martin awarded construction contract to build Atlantis' new 1.5MW AR1500 tidal turbine for the MeyGen project.

 

· Atlantis boosts strong partnership following initial collaboration on design optimisation of the AR1500.

 

· Construction continues on the 398MW MeyGen project as horizontal drilling operations commence on-site.

 

 

Atlantis, majority owner of the world's largest tidal stream energy project, MeyGen, announces today that it has executed a construction contract with global defence contractor Lockheed Martin for the delivery of Atlantis' new 1.5 megawatt AR1500 turbine to fulfil the Company's MeyGen project turbine supply obligations.

 

The 18 metre rotor diameter AR1500 turbine, scheduled for delivery dockside in Scotland in 2016, will be one of the largest capacity single rotor turbines ever built. The AR1500 turbine will have an active rotor pitching system and full nacelle yawing capability.

 

The Lockheed Martin turbine construction contract scope includes the manufacture of the steel turbine housing, the assembly of all the turbine modules (including the gearbox and generator) and the systems integration and quality assurance of the overall turbine delivery programme. Lockheed and Atlantis are working with the supply chain in Scotland to maximise local content for the AR1500.

 

This announcement marks the latest step in the Atlantis - Lockheed Martin relationship and builds on Lockheed Martin's contribution under the AR1500 detailed design contract. The yaw drive and variable pitch system that will be integrated into the AR1500 are being developed and manufactured by Lockheed Martin as part of their commitment under the existing technology partnership teaming agreement struck between Atlantis and Lockheed in 2013.

 

Tim Cornelius, CEO of Atlantis, commented:

 

"This new multi-million pound contract with Lockheed Martin further develops the strong relationship that exists between the two companies who are at the forefront of tidal power generation. Lockheed Martin has been a strong partner and supporter of Atlantis for a number of years and we look forward to continuing to work alongside this global technology giant as we continue to deliver turbine systems for installation on the MeyGen project going forward."

 

Atlantis has also announced that contractors have commenced horizontal directional drilling operations at the MeyGen site in Caithness, to create the bores for the cables which will link the onshore site at Ness of Quoys with the four subsea turbines. Each of the four bores will be approximately 550m long, and is designed to contain a 4.4kV cable through which tidally generated energy can be exported from the turbines to the onshore grid connection. The drilling is expected to take four months and will be carried out by Manchester-based O'Connor Utilities Ltd. Construction works have been underway at the onshore site since January to prepare the necessary infrastructure for this important phase of the project.

 

MeyGen was one of the first tidal projects in the world to secure the necessary planning consent, lease agreement, grid connection and power purchase agreement in order to begin onshore and offshore construction. Construction of the first phase of the project is expected to take place throughout 2015 and 2016, with first power being delivered to the grid for sale in 2016.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
CNTPGUMCWUPAPUB
Date   Source Headline
19th Dec 20187:00 amRNSCanadian FORCE Facility
19th Dec 20187:00 amRNSMeyGen Operational Update
5th Dec 20187:00 amRNSEUR1 million Grant Award to SIMEC Atlantis
23rd Nov 20184:36 pmRNSAcquisition of SIMEC Green Highland Renewables
21st Nov 201812:00 pmRNSFrench Tidal Power Agreement Signed
20th Nov 20182:05 pmRNSSecond Price Monitoring Extn
20th Nov 20182:00 pmRNSPrice Monitoring Extension
20th Nov 201811:05 amRNSSecond Price Monitoring Extn
20th Nov 201811:00 amRNSPrice Monitoring Extension
20th Nov 20189:06 amRNSSecond Price Monitoring Extn
20th Nov 20189:00 amRNSPrice Monitoring Extension
20th Nov 20187:00 amRNSHeads of Terms Signed with Equitix
6th Nov 20187:00 amRNSUskmouth FEED Contract
5th Nov 20187:00 amRNSUskmouth Power Station Conversion Project Update
30th Oct 20187:00 amRNSMeyGen Update
30th Oct 20187:00 amRNSJoint Venture with Development Agency of Normandy
22nd Oct 20187:00 amRNSMeyGen Operational Update
22nd Oct 20187:00 amRNSAppointment of Chief Operating Officer
24th Sep 20187:00 amRNSInterim Results
13th Sep 20187:00 amRNSSIMEC Atlantis Unveils World Record Tidal Turbine
3rd Sep 20187:00 amRNSGeneral Newport Update
13th Aug 20187:00 amRNSOperational Update
20th Jul 201812:22 pmRNSResult of AGM
11th Jul 20187:00 amRNSMeyGen Phase 1A Operational Update
27th Jun 20188:59 amRNSHolding(s) in Company
22nd Jun 20189:27 amRNSHolding(s) in Company
20th Jun 20183:59 pmRNSHolding(s) in Company
19th Jun 20183:43 pmRNSHolding(s) in Company
13th Jun 201812:35 pmRNSResult of Shareholder votes at General Meeting
22nd May 20182:05 pmRNSSecond Price Monitoring Extn
22nd May 20182:00 pmRNSPrice Monitoring Extension
22nd May 201810:30 amRNSSchedule One - Atlantis Resources Limited
22nd May 20187:30 amRNSRestoration - Atlantis Resources Limited
21st May 20181:01 pmRNSResult of Placing
21st May 20187:00 amRNSProposed Placing
12th Apr 20187:00 amRNSMeyGen Enters Operation Phase
3rd Apr 20187:00 amRNSUpdate on Bond Offer
13th Mar 20187:00 amRNSTransaction Update
31st Jan 20187:00 amRNSLaunch of Bond
5th Jan 20187:00 amRNSCanadian FORCE Facility
14th Dec 20177:30 amRNSSuspension - Atlantis Resources Limited
14th Dec 20177:05 amRNSProposed Acquisition
21st Nov 20177:00 amRNSWyre Tidal Project
20th Oct 20172:31 pmRNSAppointment of Nominated Adviser and Joint Broker
19th Oct 201710:13 amRNSUpdate on Director's Interests
18th Oct 20177:00 amRNSMeyGen Operation & Production Update
11th Oct 20172:10 pmRNSUpdate on Directors' Interests
9th Oct 20177:00 amRNS8 Turbine System Order for Atlantis in Indonesia
20th Sep 20177:00 amRNSInterim Results
11th Sep 20177:59 amRNSStatement on CfD Auction

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.