Turbine Construction Contract with Lockheed Martin

30 Mar 2015 07:00

RNS Number : 7835I
Atlantis Resources Limited
30 March 2015
 

30 March 2015

 

ATLANTIS RESOURCES LIMITED

("Atlantis" or the "Company")

 

Turbine Construction Contract with Lockheed Martin

 

Atlantis, majority owner of the world's largest tidal stream energy project, MeyGen, announces today that it has executed a construction contract with global defence contractor Lockheed Martin, for the delivery of Atlantis' new 1.5 megawatt AR1500 turbine to fulfil the Company's MeyGen project turbine supply obligations. The 18 metre rotor diameter AR1500 turbine, scheduled for delivery dockside in Scotland in 2016, will be one of the largest capacity single rotor turbines ever built. The AR1500 turbine will have an active rotor pitching system and full nacelle yawing capability.

 

The Lockheed Martin turbine construction contract scope includes the manufacture of the steel turbine housing, the assembly of all the turbine modules (including the gearbox and generator) and the systems integration and quality assurance of the overall turbine delivery programme. Lockheed and Atlantis are working with the supply chain in Scotland to maximise local content for the AR1500.

 

This announcement marks the latest step in the Atlantis - Lockheed Martin relationship and builds on Lockheed Martin's contribution under the AR1500 detailed design contract. The yaw drive and variable pitch system that will be integrated into the AR1500 are being developed and manufactured by Lockheed Martin as part of their commitment under the existing technology partnership teaming agreement struck between Atlantis and Lockheed in 2013.

 

Atlantis is also pleased to announce that contractors will today commence horizontal directional drilling operations at the MeyGen site in Caithness, to create the bores for the cables which will link the onshore site at Ness of Quoys with the four subsea turbines. Construction works have been underway at the onshore site since January to prepare the necessary infrastructure for this important phase of the project.

 

 

Tim Cornelius, CEO of Atlantis, commented:

 

"This new multi-million pound contract with Lockheed Martin further develops the strong relationship that exists between the two companies who are at the forefront of tidal power generation. Lockheed Martin has been a strong partner and supporter of Atlantis for a number of years and we look forward to continuing to work alongside this global technology giant as we continue to deliver turbine systems for installation on the MeyGen project going forward. "

 

 

For further information please contact:

 

Atlantis Resources Limited

via FTI Consulting

Tim Cornelius, Chief Executive Officer

Duncan Black, Chief Financial Officer

Peel Hunt LLP (Nominated Adviser and Broker)

+44 (0) 20 7418 8900

Daniel Harris / Jock Maxwell MacDonald

FTI Consulting

+44 (0) 20 3727 1000

Ben Brewerton / Alex Beagley / Stephanie Blott / James Styles

 

 

Atlantis names Lockheed Martin as principal contractor to deliver AR1500 turbine to the MeyGen tidal power project

 

· Lockheed Martin awarded construction contract to build Atlantis' new 1.5MW AR1500 tidal turbine for the MeyGen project.

 

· Atlantis boosts strong partnership following initial collaboration on design optimisation of the AR1500.

 

· Construction continues on the 398MW MeyGen project as horizontal drilling operations commence on-site.

 

 

Atlantis, majority owner of the world's largest tidal stream energy project, MeyGen, announces today that it has executed a construction contract with global defence contractor Lockheed Martin for the delivery of Atlantis' new 1.5 megawatt AR1500 turbine to fulfil the Company's MeyGen project turbine supply obligations.

 

The 18 metre rotor diameter AR1500 turbine, scheduled for delivery dockside in Scotland in 2016, will be one of the largest capacity single rotor turbines ever built. The AR1500 turbine will have an active rotor pitching system and full nacelle yawing capability.

 

The Lockheed Martin turbine construction contract scope includes the manufacture of the steel turbine housing, the assembly of all the turbine modules (including the gearbox and generator) and the systems integration and quality assurance of the overall turbine delivery programme. Lockheed and Atlantis are working with the supply chain in Scotland to maximise local content for the AR1500.

 

This announcement marks the latest step in the Atlantis - Lockheed Martin relationship and builds on Lockheed Martin's contribution under the AR1500 detailed design contract. The yaw drive and variable pitch system that will be integrated into the AR1500 are being developed and manufactured by Lockheed Martin as part of their commitment under the existing technology partnership teaming agreement struck between Atlantis and Lockheed in 2013.

 

Tim Cornelius, CEO of Atlantis, commented:

 

"This new multi-million pound contract with Lockheed Martin further develops the strong relationship that exists between the two companies who are at the forefront of tidal power generation. Lockheed Martin has been a strong partner and supporter of Atlantis for a number of years and we look forward to continuing to work alongside this global technology giant as we continue to deliver turbine systems for installation on the MeyGen project going forward."

 

Atlantis has also announced that contractors have commenced horizontal directional drilling operations at the MeyGen site in Caithness, to create the bores for the cables which will link the onshore site at Ness of Quoys with the four subsea turbines. Each of the four bores will be approximately 550m long, and is designed to contain a 4.4kV cable through which tidally generated energy can be exported from the turbines to the onshore grid connection. The drilling is expected to take four months and will be carried out by Manchester-based O'Connor Utilities Ltd. Construction works have been underway at the onshore site since January to prepare the necessary infrastructure for this important phase of the project.

 

MeyGen was one of the first tidal projects in the world to secure the necessary planning consent, lease agreement, grid connection and power purchase agreement in order to begin onshore and offshore construction. Construction of the first phase of the project is expected to take place throughout 2015 and 2016, with first power being delivered to the grid for sale in 2016.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
CNTPGUMCWUPAPUB
Date   Source Headline
29th Mar 20237:00 amRNSSAE update on Abundance Bonds and BESS project
23rd Feb 20237:00 amRNSBond repayment update & AIM Rule 26 website change
3rd Feb 20237:00 amRNSAppointment of Nominated and Financial Adviser
20th Jan 20232:39 pmRNSChange of Adviser
9th Dec 20222:05 pmRNSSecond Price Monitoring Extn
9th Dec 20222:00 pmRNSPrice Monitoring Extension
9th Dec 202211:05 amRNSSecond Price Monitoring Extn
9th Dec 202211:00 amRNSPrice Monitoring Extension
9th Dec 202210:29 amRNSBESS project receives conditional planning consent
8th Nov 20227:00 amRNSDelivery of MeyGen project continues at pace
31st Oct 20227:00 amRNSSAE tidal division secures new investment
30th Sep 20227:00 amRNSSAE releases interim results
23rd Sep 202210:37 amRNSTidal turbine re-deployment at MeyGen site
8th Sep 20224:40 pmRNSSecond Price Monitoring Extn
8th Sep 20224:35 pmRNSPrice Monitoring Extension
30th Aug 20229:05 amRNSSecond Price Monitoring Extn
30th Aug 20229:00 amRNSPrice Monitoring Extension
30th Aug 20227:00 amRNSSAE achieves milestone in BESS project delivery
25th Aug 20222:11 pmRNSBLOCK LISTING SIX MONTHLY RETURN
19th Aug 20227:00 amRNSDirector Change
18th Aug 20222:33 pmRNSResults of Annual General Meeting
5th Aug 202211:00 amRNSNotice of AGM
8th Jul 202211:05 amRNSSecond Price Monitoring Extn
8th Jul 202211:00 amRNSPrice Monitoring Extension
7th Jul 20222:06 pmRNSSecond Price Monitoring Extn
7th Jul 20222:00 pmRNSPrice Monitoring Extension
7th Jul 20229:00 amRNSPrice Monitoring Extension
7th Jul 20228:27 amRNSSAE successfully secures Government support
1st Jul 20222:06 pmRNSSecond Price Monitoring Extn
1st Jul 20222:00 pmRNSPrice Monitoring Extension
30th Jun 202212:38 pmRNSUpdate on Abundance Bonds
29th Jun 20222:06 pmRNSSecond Price Monitoring Extn
29th Jun 20222:01 pmRNSPrice Monitoring Extension
29th Jun 202211:05 amRNSSecond Price Monitoring Extn
29th Jun 202211:00 amRNSPrice Monitoring Extension
29th Jun 20229:05 amRNSSecond Price Monitoring Extn
29th Jun 20229:00 amRNSPrice Monitoring Extension
29th Jun 20227:00 amRNSFinal Results
10th Jun 20223:12 pmRNSSAE confirms amendment to Debenture Deed
25th May 20227:00 amRNSRequest to amend Debenture Deed
24th May 20229:05 amRNSSecond Price Monitoring Extn
24th May 20229:00 amRNSPrice Monitoring Extension
24th May 20227:00 amRNSSAE signs £40m contract for Battery Project
12th May 20222:06 pmRNSSecond Price Monitoring Extn
12th May 20222:00 pmRNSPrice Monitoring Extension
12th May 202211:05 amRNSSecond Price Monitoring Extn
12th May 202211:00 amRNSPrice Monitoring Extension
28th Apr 20229:00 amRNSPrice Monitoring Extension
28th Apr 20227:00 amRNSSAE develops new future for Uskmouth site
27th Apr 20227:00 amRNSSAE in discussions with Abundance Investment

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.