Final results

25 Jun 2024 07:00

RNS Number : 6507T
SIMEC Atlantis Energy Limited
25 June 2024
 

25 June 2024

 

SIMEC Atlantis Energy Limited

("SAE Renewables", "SAE" or the "Company")

 

Final results for the year ended 31 December 2023 and notice of AGM

 

SAE announces its audited final results for the year ended 31 December 2023. A complete version of the 2023 Annual Report and Accounts ("2023 Annual Report") can be found here: http://www.rns-pdf.londonstockexchange.com/rns/6507T_1-2024-6-24.pdf

 

The 2023 Annual Report, a notice of Annual General Meeting ("AGM") and a Proxy Form, have been posted to shareholders, and copies are available on the Company's website at www.saerenewables.com

 

The AGM will be held at the offices of Ashurst LLP, London Fruit & Wool Exchange, 1 Duval Square, London, E1 6PW at 11.00 a.m. on Thursday 18 July 2024.

 

The 2023 results reflect a transformational year for the business. SAE has delivered significant progress in the last 12 months against its targets and established a firm foundation to deliver an exciting pipeline of sustainable energy projects and move into becoming an owner and operator of these projects, ensuring long-term value for our shareholders. Our strategy directly supports UK government policy to improve energy security and achieve Net Zero by 2050.

 

2023 Financial Highlights include:

 

· The Group reported a profit of £23.2m, compared with a 2022 loss of £11.1m.

· Increase of 292% in Group revenue to £15.3m (2022: £3.9m).

· Revenues available to the Group, which excludes ring-fenced revenue earned by the MeyGen tidal array, rose to £10.7 million (2022: £nil) . The sale, at Uskmouth, of a ready-to-build 230MW BESS project with a grid connection for £10.0 million accounted for the majority of 2023 revenues, with the balance of £0.7 million being rental income from the Uskmouth site.

· Net Assets increased 678% to £44.2m (2022: £5.7m). The major increase in the valuation of the Group arises from the reassessment of the value and size of our battery storage projects.

· Increase in EBITDA to £8.3m (2022: EBITDA loss of £5.8m).

· Reduction of 30% in SAE's Group debt, excluding MeyGen debt, to £13.7m (2022: £19.7m). This followed the successful execution of the lease agreement for the 230MW BESS project with Uskmouth Energy Storage Limited. SAE also reached an agreement with its bondholders to rephase bond repayments out of 2024 and into periods commencing in December 2025 and culminating in a final £7.7 million repayment in December 2029.

· Reduction of 29% in Operating costs to £5.0m (2022: £7.0m).

 

Operational highlights include:

 

· Final payment received on 230MW/460MWh Uskmouth Battery Energy System Storage (BESS) projects, now under construction by Uskmouth Energy Storage Ltd.

· In December 2023, signed conditional land sales agreement with Electric Land for £9.9 million for the 230MW BESS. Milestone income to be received during 2024 and into 2025.

 

Post-period highlights

 

· Achieved planning approval for a new 120MW/240MWh BESS which repurposes the site of the Uskmouth power station former cooling towers.

· Commenced development of an additional 600MW/1,200MWh of BESS at the Uskmouth site.

· Submitted the planning application for the Mey BESS project, near Caithness in Scotland. SAE has an agreement option to lease the required land and has secured a modification of the MeyGen grid connection to increase capacity to 287MW with full import and export rights.

 

Duncan Black, Chairman of SAE Renewables, commented:

 

"I am excited about the future for SAE. We have the funding and visibility on future revenues we need to be able to deliver our development projects and service our debt. We have a pipeline of projects that would be the envy of many much larger companies, and we have a Board and Executive team who have a track record of successful delivery. I would sincerely like to thank all the members of our team whose hard work and dedication during the past 12 months has delivered outstanding results for SAE. To the stakeholders in our projects, bondholders, shareholders and governments - thank you for your continued support of our business."

 

Graham Reid, Chief Executive Officer of SAE Renewables, commented:

 

"During 2023, the business has met or exceeded all of its objectives. This provides a great platform from which we can embark on our new strategy: Building a Sustainable Future to 2035, advancing our transition towards becoming an Independent Power Producer."

 

 

 

 

 

For further information, please contact:

 

SAE Renewables

Sean Parsons, Director of External Affair

+44 (0)7739 832 446

Strand Hanson Limited (Nominated and Financial Adviser)

Richard Johnson

Rory Murphy

David Asquith

+44 (0)20 7409 3494

 

 

Zeus Capital Limited (Broker)

Louisa Waddell

Simon Johnson

 

+44 (0)20 3829 5000

 

Notes to Editors

SAE Renewables is a global developer, owner and operator of sustainable energy projects. SAE owns the world's flagship tidal stream project, MeyGen. SAE is also the owner of the Uskmouth Power Station site that is being repurposed into a sustainable energy park, initially housing one of the UK's largest battery energy storage projects. https://www.saerenewables.com/

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
FR SEWFLLELSELM
Date   Source Headline
29th Mar 20237:00 amRNSSAE update on Abundance Bonds and BESS project
23rd Feb 20237:00 amRNSBond repayment update & AIM Rule 26 website change
3rd Feb 20237:00 amRNSAppointment of Nominated and Financial Adviser
20th Jan 20232:39 pmRNSChange of Adviser
9th Dec 20222:05 pmRNSSecond Price Monitoring Extn
9th Dec 20222:00 pmRNSPrice Monitoring Extension
9th Dec 202211:05 amRNSSecond Price Monitoring Extn
9th Dec 202211:00 amRNSPrice Monitoring Extension
9th Dec 202210:29 amRNSBESS project receives conditional planning consent
8th Nov 20227:00 amRNSDelivery of MeyGen project continues at pace
31st Oct 20227:00 amRNSSAE tidal division secures new investment
30th Sep 20227:00 amRNSSAE releases interim results
23rd Sep 202210:37 amRNSTidal turbine re-deployment at MeyGen site
8th Sep 20224:40 pmRNSSecond Price Monitoring Extn
8th Sep 20224:35 pmRNSPrice Monitoring Extension
30th Aug 20229:05 amRNSSecond Price Monitoring Extn
30th Aug 20229:00 amRNSPrice Monitoring Extension
30th Aug 20227:00 amRNSSAE achieves milestone in BESS project delivery
25th Aug 20222:11 pmRNSBLOCK LISTING SIX MONTHLY RETURN
19th Aug 20227:00 amRNSDirector Change
18th Aug 20222:33 pmRNSResults of Annual General Meeting
5th Aug 202211:00 amRNSNotice of AGM
8th Jul 202211:05 amRNSSecond Price Monitoring Extn
8th Jul 202211:00 amRNSPrice Monitoring Extension
7th Jul 20222:06 pmRNSSecond Price Monitoring Extn
7th Jul 20222:00 pmRNSPrice Monitoring Extension
7th Jul 20229:00 amRNSPrice Monitoring Extension
7th Jul 20228:27 amRNSSAE successfully secures Government support
1st Jul 20222:06 pmRNSSecond Price Monitoring Extn
1st Jul 20222:00 pmRNSPrice Monitoring Extension
30th Jun 202212:38 pmRNSUpdate on Abundance Bonds
29th Jun 20222:06 pmRNSSecond Price Monitoring Extn
29th Jun 20222:01 pmRNSPrice Monitoring Extension
29th Jun 202211:05 amRNSSecond Price Monitoring Extn
29th Jun 202211:00 amRNSPrice Monitoring Extension
29th Jun 20229:05 amRNSSecond Price Monitoring Extn
29th Jun 20229:00 amRNSPrice Monitoring Extension
29th Jun 20227:00 amRNSFinal Results
10th Jun 20223:12 pmRNSSAE confirms amendment to Debenture Deed
25th May 20227:00 amRNSRequest to amend Debenture Deed
24th May 20229:05 amRNSSecond Price Monitoring Extn
24th May 20229:00 amRNSPrice Monitoring Extension
24th May 20227:00 amRNSSAE signs £40m contract for Battery Project
12th May 20222:06 pmRNSSecond Price Monitoring Extn
12th May 20222:00 pmRNSPrice Monitoring Extension
12th May 202211:05 amRNSSecond Price Monitoring Extn
12th May 202211:00 amRNSPrice Monitoring Extension
28th Apr 20229:00 amRNSPrice Monitoring Extension
28th Apr 20227:00 amRNSSAE develops new future for Uskmouth site
27th Apr 20227:00 amRNSSAE in discussions with Abundance Investment

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.