Restructuring of the Paradox project

14 Oct 2019 07:00

RNS Number : 7019P
Rose Petroleum PLC
14 October 2019
 

Prior to publication, the information contained within this announcement was deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 ("MAR"). With the publication of this announcement, this information is now considered to be in the public domain.

 

14 October 2019

 

Rose Petroleum plc

 

("Rose" or the "Company")

 

Restructuring of the Paradox project

 

Rose Petroleum plc (AIM: ROSE), a Rocky Mountain-focused oil and gas company, provides a further update on its project in the Paradox Basin, Utah, U.S. (the "project").

 

The Company is pleased to announce that it has negotiated a new agreement (the "Agreement") with its joint-venture ("JV") partner on the project, Rockies Standard Oil Corporation ("RSOC"). The project continues to offer substantial scale and value and is now, in the Board's view, better positioned for development.

 

The Agreement enables Rose to focus on a potentially highly economic core acreage position of circa 12,920 acres which contains 21 high-priority drilling targets and estimated 2C contingent recoverable resources, net to Rose, of 8.3 million barrels of oil equivalent ("mmboe"). This acreage position alone represents an estimated post-tax net present value to Rose of US$59m (at a 10% discount rate) ("NVP10"), a significant premium to the Company's current market capitalisation and demonstrative of the considerable potential of the project.

 

The agreement also allows Rose to reduce the overall cost of maintaining the project and, most importantly, gives the Company immediate ownership of the highest potential 12,920 lease acres, with a remaining nine year lease term on 5,240 of these acres, and a two year lease extension on the balance (subject to regulatory approval).

 

The Company's revised strategy to focus on the most attractive acreage is a logical step, informed by, amongst other things, the acquisition and analysis of the 3D seismic data covering the project area, the verification work undertaken by Schlumberger in 2018, and the positive feedback received from potential farm-in partners on how Rose can best optimise the project. Further details of the revised JV terms covering the remaining acreage are outlined below.

 

The Company also continues to work with the U.S. Department of Energy (the "DOE") and the University of Utah on a study related to improving production and raising the profile of oil drilling in the Northern Paradox Basin. Subject to contract, Rose may be eligible for a significant funding grant to assist in these efforts.

 

The Board's stated strategy for the Company is to build a balanced portfolio of assets, exhibiting both free cash flow and long-term development opportunities. The newly structured project sits squarely within this strategic vision and the Board looks forward to adding additional projects to the portfolio in the short-term.

 

 

 

Background

 

In the Company's interim financial statement, which was released to the market in September 2019, it was outlined that since joining Rose, the new operational team had undertaken a review of the project, including a detailed look at the historical activity carried out on the project and the ongoing farm-in process. The team also reviewed the timeframe and plan for spudding the first project well in line with the expectations of the U.S. Bureau of Land Management (" BLM"), who continue to push for the development of the project as soon as commercially possible and in spite of challenging market conditions. 

 

The clear conclusion from this review was that the scale and potential of the project are of sufficient magnitude to justify the Company's ongoing involvement in the project. The review also concluded that with more favourable positioning and better market conditions, investment from industry and financial partners can be achievable. Further, the review illustrated the need to balance the overall scale of the project with: 1) the current market backdrop; 2) timing obligations to the BLM; and 3) ongoing holding costs of the significantly sized acreage package.

 

On the basis of all of these factors, the Board elected to pursue a strategy for the project which included:

·; Focusing on the most attractive acreage (as identified by the 3D seismic acquisition undertaken by the Company);

·; Releasing acreage that the Company believes to be non-prospective or on too short a lease to merit further exploration work and / or expenditure; and

·; Actively acquiring further contiguous acreage in areas the Board considers to have the greatest potential.

 

Following this review, the Company entered into discussions with RSOC to restructure the JV in order that the project might be positioned and developed in line with this new strategy for the project.

 

New Agreement

 

The Agreement, which supersedes all previous arrangements with RSOC, enables Rose to gain an immediate 75% working interest ownership and operatorship of key acreage, replacing the earn-in structure in the original agreement with RSOC. The Agreement will see a reduction in annual lease costs and allows further time to develop and market the project, while maintaining a highly valuable acreage position that is drill-ready.

 

Under the Agreement, the Company will focus on the high quality 12,920 acre position of which 5,240 acres have a nine year lease term remaining (and a 12.75% royalty) and the residual 7,680 acres have a two year lease extension subject to regulatory approval (and a 20% royalty). These leases are almost entirely covered by the 3D seismic data previously obtained and contain 21 drilling targets from the base case development, including the fully permitted GV22-1 drill location. The gross Estimated Ultimate Recovery (EUR) from each of the wells targeting the Cane Creek reservoir zone is estimated to be 0.85mmboe.

 

Based on the 2018 Competent Person's Report (CPR) methodology, as applied by Gaffney Cline and Associates ("GCA"), the 12,920 acres contain estimated 2C contingent recoverable resources of 8.3mmboe net to Rose. This acreage position alone represents an estimated post-tax NPV10 to Rose of US$59m, highlighting the significant scale and financial potential of the newly restructured project.

 

The resource and valuation metrics do not include the additional exploration potential contained within a further five stacked, high-graded prospective zones on the acreage. Successful efforts in these zones may create a multi-zone play which could add substantial further value through resource addition and from development cost optimisations.

 

In return for this restructuring, Rose will maintain the obligation from the original earn-in agreement to carry RSOC for a 25% working interest on the first well drilled on the project (expected to be circa $1.9m). Rose has also agreed to carry RSOC for a 25% working interest for the acquisition of specific targeted leases in and around the core acreage area, in aggregate, up to a total of US$500,000, but it is the current view of Rose and RSOC that the final figure will be considerably lower and any payments would be incurred over an extended period of time. If Rose does not drill its first project well within a five year period, all leases, with the exception of the 5,240 leases with nine year lease terms, will be assigned back to RSOC.

 

Further, Rose has terminated its remaining farm-in rights over less prospective acreage and has reassigned those rights back to RSOC. This re-assignment is consistent with the Company's intent to focus its efforts on the area covered by the existing 3D seismic data.

 

Colin Harrington, Chief Executive Officer, stated:

 

"By focusing on highest potential acreage, the Company maintains a project of real scale and value while reducing its on-going running costs and extending project term. Most importantly, the Company will also gain immediate ownership of core acreage and will become Operator across the project. I believe this restructuring will make the project more attractive to potential investors as we continue with our farm-in process.

 

"I am delighted we have been able to negotiate the new agreement. I would like to thank our JV partner RSOC for their continued commitment to Rose and the project and we look forward to working with them to spud the first well as soon as is commercially possible. We also look forward to our continuing partnership with the DoE and University of Utah in their effort to fund research and support development of the Northern Paradox Basin.

 

"In the Board's view, the high-grading of the project will create a long-term future for the project, one which meets the Board's selection criteria and which will positively complement the Company's future balanced asset portfolio."

 

 

 

 

Contacts:

Rose Petroleum plc

Colin Harrington (CEO)

Chris Eadie (CFO)

 

 

Tel: +44 (0)20 7225 4599

Tel: +44 (0)20 7225 4599

Allenby Capital Limited - AIM Nominated Adviser

Jeremy Porter / James Reeve / Liz Kirchner

 

 

Tel: +44 (0)20 3328 5656

 

Turner Pope Investments - Joint Broker

Andy Thacker / Zoe Alexander

 

 

Tel: +44 (0)20 3657 0050

Cantor Fitzgerald Europe - Financial Adviser and Joint Broker

David Porter

 

 

Tel: +44 (0)20 7894 7686

 

Novum Securities Limited - Joint Broker

Colin Rowbury

 

Tel: +44 (0)20 7399 9427

 

Media enquiries:

Allerton Communications

Peter Curtain

 

 

Tel: +44 (0) 20 3633 1730

peter.curtain@allertoncomms.co.uk

 

Dr Gregor Maxwell, BSc Hons. Geology and Petroleum Geology, PhD, Technical Adviser to the board of Rose Petroleum plc, who meets the criteria of a qualified person under the AIM Note for Mining and Oil & Gas Companies - June 2009, has reviewed and approved the technical information contained within this announcement.

 

Note

1. Oil and Gas Prices

GCA's 2Q 2018 WTI and Henry Hub price scenario (Table 1) was used for its economic analysis of the project and included in the CPR. Based on information provided to GCA by the Company realised prices are expected to include a US$10 per barrel discount for crude and a US$0.50/Mscf discount for natural gas.

 Table 1: GCA 2Q 2018 WTI and Henry Hub Price Scenario

Year

WTI Price(US$/Bbl)

Henry Hub Price(US$/Mscf)

2019

59.21

2.79

2020

62.50

3.12

2021

63.75

3.39

2022

65.03

3.62

2023

66.33

3.81

2024

67.65

3.95

2025

69.01

4.08

2026

70.39

4.21

2027

71.79

4.30

2028

+2% p.a.

+2% p.a.

 

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
MSCLFFVIIELVLIA
Date   Source Headline
1st Jun 20107:00 amRNSAcquisition of Breccia Pipe Targets, US
26th May 20107:00 amRNSNI 43-101 Resource Report, Wate Uranium Pipe
26th Apr 20107:00 amRNSFinal Results
31st Mar 20107:00 amRNSUpdate on Copper Properties
1st Mar 20107:00 amRNSMaiden Resource Statement at Wate, Arizona
27th Jan 20107:00 amRNSAppointment of COO and 2010 Strategy
22nd Jan 20109:30 amRNSHolding(s) in Company
19th Jan 201012:01 pmRNSHolding(s) in Company
19th Jan 20107:00 amRNSAcquisition of New Uranium Property
14th Jan 20107:00 amRNSHolding(s) in Company
23rd Nov 20095:23 pmRNSHolding(s) in Company
18th Nov 20097:00 amRNSAdditional Uranium Drilling Intercepts, Arizona
11th Nov 20097:00 amRNSCopper-Gold Project, New Mexico
6th Nov 20096:12 pmRNSHolding(s) in Company
17th Sep 20097:00 amRNSAcquisition of New Uranium Package
9th Sep 20097:00 amRNSRenewal of Freeport Agreement
7th Sep 20097:00 amRNSHigh Grade Uranium Intercepts
3rd Sep 200911:22 amRNSHolding(s) in Company
1st Sep 200911:52 amRNSHolding(s) in Company
28th Aug 20097:00 amRNSHalf Yearly Report
22nd Jul 20094:39 pmRNSGrant of Options
20th Jul 20097:00 amRNSDirectorate Change
14th Jul 20097:00 amRNSChange of Adviser
25th Jun 20097:00 amRNSUranium Property Acquisition
5th Jun 200912:04 pmRNSHolding(s) in Company
5th Jun 200912:04 pmRNSHolding(s) in Company
14th May 200912:56 pmRNSResult of AGM
21st Apr 20097:00 amRNSAnnual Report and Financial Statements
9th Apr 20097:00 amRNSFinal Results
9th Mar 200911:07 amRNSHolding(s) in Company
26th Feb 20091:17 pmRNSResult of General Meeting
20th Feb 20097:00 amRNSHolding(s) in Company
6th Feb 20097:00 amRNSDirector/PDMR Shareholding
2nd Feb 20097:00 amRNSUranium Update
30th Jan 200912:32 pmRNSYuma King Agreement
26th Jan 20098:55 amRNSNotice of General Meeting
23rd Jan 20099:17 amRNSHolding(s) in Company
18th Dec 20083:17 pmRNSHolding(s) in Company
6th Nov 20087:00 amRNSUranium Update
24th Oct 20087:00 amRNSGrant of Options
17th Oct 20087:00 amRNSUpdate On Uranium Activities
14th Oct 20083:39 pmRNSHolding(s) in Company
22nd Sep 20087:00 amRNSHeads of Agreement
10th Sep 20087:00 amRNSInterim Results
9th Sep 20087:00 amRNSUranium One/VANE Minerals Joi
25th Jul 200810:07 amRNSHolding(s) in Company
15th Jul 20087:00 amRNSOperational Update
20th May 20082:29 pmRNSResult of AGM
14th May 20082:33 pmRNSHolding(s) in Company
21st Apr 20082:34 pmRNSAnnual Report and Accounts

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.