focusIR May 2024 Investor Webinar: Blue Whale, Kavango, Taseko Mines & CQS Natural Resources. Catch up with the webinar here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksPhoenix Copper. Regulatory News (PXC)

Share Price Information for Phoenix Copper. (PXC)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 19.25
Bid: 0.00
Ask: 0.00
Change: 0.00 (0.00%)
Spread: 0.50 (2.632%)
Open: 0.00
High: 0.00
Low: 0.00
Prev. Close: 19.25
PXC Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Empire Mine:16% increase in forecast Cu production

19 Apr 2018 07:00

RNS Number : 3901L
Phoenix Global Mining Ltd
19 April 2018
 

Phoenix Global Mining Ltd / Ticker: AIM:PGM / Sector: Mining

19 April 2018

Phoenix Global Mining Ltd ('Phoenix' or the 'Company')

Preliminary Economic Assessment Completed for the Empire Mine Project, Idaho

16% increase in forecast annual copper production

 

Phoenix Global Mining Ltd (LSE AIM: PGM), the AIM quoted, North American-focused base and precious metals exploration and development company, is pleased to announce the results of the Preliminary Economic Assessment (PEA) for its Empire Mine project in Custer County, Idaho, USA.

 

PEA Highlights:

 

· 8,124 Tonnes Annual Copper Production

· $65m average annual revenue, assuming $8,265 per tonne copper price across life of mine

· 8-Year Mine Life @ 0.24% Copper Cut-Off Grade

· 76% Heap Leach Copper Recovery

· $61.2m pre-production capex

· $4,068 per tonne Copper Cash Cost of Production

· $53.66 million after tax NPV (7.5% discount)

· 23.5% IRR after tax

· PEA is based on open pit oxide copper production only, and excludes any potential revenue from gold, silver or zinc

 

 

 

Dennis Thomas, the Company's CEO, said: "I am pleased to report on the successful completion of our PEA on the Empire Mine open pit oxide deposit. This is a significant milestone for the Company and brings us an important step closer to copper production.

 

The PEA shows an average copper cathode production rate of 8,124 tonnes a year from a 2 million tonne a year mine at a cash cost of production of US$1.85 per pound of copper, an increase of 16% in annual copper production from our original projections. The project has robust economics and the 2018/2019 work programme will provide the opportunity to not only grow the existing Empire copper oxide resource but also to address the potential economic benefits of the gold, silver and zinc that were reported in the updated November 2017 resources following the 2017 drilling programme. The PEA does not consider production of these potential by-products. We are also confident that the project economics will continue to improve as the operating and capital costs are further examined and refined through the course of the BFS and we look forward to updating shareholders as we progress through the BFS process

 

A Bankable Feasibility Study (BFS) work programme has been developed that will commence in Q3 this year and will build from the current PEA. The BFS will provide the necessary information to begin construction in 2019 with the goal of production by early 2021."

 

 

Preliminary Economic Assessment

Average annual copper production

8,124

Tonnes

Average annual revenue

65,010,500

US$

Average annual operating costs

33,051,375

US$

Average EBITDA

31,959,125

US$

Mine life

8

Years

Revenue per tonne of copper

8,002

US$ / tonne

Cash cost of production

4,068

US$ / tonne

Pre-production capital costs

61,207,000

US$

LOM cash flow pre-tax

134,580,000

US$

LOM cash flow after tax

117,940,000

US$

NPV (5%) pre-tax

82,800,000

US$

NPV (5%) after tax

70,580,000

US$

NPV (7.5%) pre-tax

64,210,000

US$

NPV (7.5%) after tax

53,660,000

US$

 

Project Overview

 

The Empire Project is located in southeast-central Idaho, in the Alder Creek Mining District and encompasses 109 contiguous mining claims, including 21 patented lode claims and 88 unpatented lode claims, covering 1774 acres (719 hectares). The Project consists of a skarn-hosted, open-pit, heap leach SX-EW copper resource and a deeper-rooted and past-producing high-grade copper, gold, silver and tungsten vein system. The subject of this PEA is the open-pit copper oxide resource.

Mineral Resources

The PEA is based on the previously reported November 7, 2017 Resource Update prepared by Hard Rock Consulting. This estimate encompasses the open-pit copper oxides occurring within an optimized pit-shell and includes 11,485 million tons in the Measured and Indicated category, grading 0.52% Cu above a cutoff grade of 0.184%, and 9,880 million tons of Inferred material above the same cutoff grading 0.41% Cu.

Mine Planning

The PEA mine plan was prepared by Hard Rock Consulting (HRC) using GemCom and AutoCad software. There were no constraints on land boundaries, allowing the pit shell and design pit to encompass and capture the majority of the MI&I resources in the November 7, 2017 Resource Report. The PEA-level phased pit design was based on slopes recommended by Call and Nicholas of 45-degrees in the oxide breccia rock type and 51-degrees in all other rock types. The 2.2 million tonne a year mine plan uses a cut-off grade of 0.24% copper.

The pit designs are based on PEA-level operating cost assumptions and appear to be consistent with current labour, fuel, reagent, and general processing costs.

Operating costs were calculated assuming CAT 777 trucks and CAT 992 loaders and DM45 production drills. The work schedule assumes two-12 hour shifts per day, 365 days per year at an assumed 92% availability for haul trucks and loaders, and 85% availability for all other equipment.

Production Schedule

The PEA mine plan was designed as a series of four phased push-backs to achieve a balanced production of ore and waste rock over the life of the mine.  The mine preproduction requirements at the project are minimal given the presence of mineable mineralization near the bedrock surface. The first pit phases are planned near the crusher area to minimize haulage distances at the beginning of the mine life. Waste material from the pit areas will be utilized for construction of the heap leach pad, crusher area and other infrastructure.

Crushing, Screening and Agglomeration

Run-of-mine ("ROM") ore will be delivered to a modular crushing-screening plant at a rate of 350 short tons per hour. This throughput is based on 75% plant availability on a 24-hour basis. ROM material is expected to have a P100 of 24". The leach pad is currently being designed for crushed material having a P80 of ¾".

The crushing-screening plant will consist of dump hopper, a vibrating grizzly feeder, a jaw crusher, a secondary screen and cone crusher, and a tertiary screen and cone crusher. These components are connected by 30-in wide conveyors.

Ore grade material from the open pit will be crushed to 6.35 mm and then agglomerated with cement prior to loading on the heap leach pad in 10m lifts. Agglomerated ore will be conveyed to the leach pad via a series of grasshopper conveyors feeding a radial stacker.

 Heap Leaching and Pregnant Leach Solution (PLS) Pond

Golder Associates have provided a PEA-level preliminary layout for a 20-million-tonne heap leach pad. The leach pad is located in an east-west valley located to the north of the Empire open pit in an area known as North Gulch. The layout includes perimeter roads and anchor trenches.

The PLS pond will receive the aggregate flow of PLS from the leach pad and has a pond capacity of 1,495,000 gallons. The contingency pond is designed to capture any overflow of the PLS pond in the event of a 24-hour 100-year storm event that saturates the leach pad. The design capacity is 8,380,000 gallons.

The leach pad is planned to be constructed in stages in order to minimize initial capital. Phase 1 will allow for 3 years of operation before phase 2 will need to be constructed.

Solvent Extraction, Tank Farm and Electrowinning (SX-EW)

Copper-bearing PLS will be pumped to the solvent extraction (SX) area for processing to extract the copper from solution. The SX stripping circuit consists of two stripping mixer-settlers in a series arrangement. Each SX stripper has two mix tanks and a settler which mix the copper-rich organic from the extraction settlers with strongly acidic lean electrolyte to transfer copper from the organic liquid to the electrolyte. Rich electrolyte loaded with copper leaving the stripping settlers will report to the loaded organic tanks in the tank farm.

The tank farm will be located below the solvent extraction facility and contains tanks, pumps, heat exchangers, and filters that service the SX-EW facilities. The tank farm will store and transfer organic, electrolyte, reagents, and crud, as well as provide storage for a 5-day supply of fresh reagents. The tank farm is designed with secondary containment capable of holding 110% of the contents of the largest tank.

The electrowinning facility removes copper from the rich electrolyte solution and plates the copper on cathodes using a direct current electrical process. The copper sheets are stripped, or "harvested", on a daily or weekly basis. The sheets are then sampled, bundled, weighed, and loaded onto flatbed trucks for transport to market.

A main electrical substation is located in the SX-EW plant area and receives power from a new 24.9kV power line coming from the Mackay substation 3 miles away belonging to Lost River Electric Cooperative in Mackay, Idaho. The Empire substation will transform power from 24.9 kV to 13.8 kV for the tankhouse, and lower voltages for distribution to the various areas of the plant. Medium and low voltage in the various plant areas will be 4160 V and 480 V. Motor control centres and electrical equipment rooms for the low voltage distribution are located at the crushing plant, the stockpile/agglomerator, the EW tankhouse, the SX circuit and tank farm, the leach pad/PLS pond and up at the truck shop near the Empire open pit.

Infrastructure and Services

Ancillary facilities at the mine site include a prefabricated modular guardhouse and truck scale, a pre-engineered metal warehouse/maintenance building, a truck shop and a fuel station.

In the town of Mackay, other ancillary facilities will include the administration building and an assay lab for production samples from the mine. A separate solution lab will be housed in a room at the EW building for control of process solutions.

The administration building is provided for the general administrative personnel, safety, environmental and office services. Currently, the building is specified to be a pre-engineered building. Space is also provided for an analytical laboratory. A warehouse/maintenance building is provided in the SX-EW plant area and a security gate house is provided at the main entrance to the plant.

Mine Access Road

The access to the Empire mine follows along the existing Smelter Avenue that leads from Mackay to the mine site. The mine access road has been designed for a maximum grade of 8% and will be widened to 40 ft to accommodate two-way traffic and oversize vehicles delivering mining equipment. Berms and drainage channels have been incorporated into the PEA design.

Power Supply and Distribution

Grid power for the Empire mine will be provided by Lost River Electric Cooperative, located in Mackay, and is assumed in the PEA at a bulk industrial rate of $0.07 per kW-hr. Power will be supplied through a new 24.9 kV power line from the Mackay substation.

Water Supply and Distribution

The Empire copper SX-EW operation will be a zero-discharge facility. All water that is used in the operation will be recycled into the raffinate leach solution.

The PEA estimates operational requirements of approximately 386 gpm for the processing circuit, truck shop, and dust control, with approximately 194 gpm lost to evaporation and irreducible moisture content in the heap. Fresh water and fire water will be stored in tanks at the site and will be filled with water from the Company's Cliff Creek water right and from a constructed catchment basin. Potable water will be sourced from Mackay.

 

Commodity Price Projections

In view of the medium-to long term copper supply shortfall a copper price of $3.75 per pound ($8,265 per tonne) has been used for the base case analysis. This price is based on the average forecast copper price as reported by Metal Bulletin Apex Copper.

Permitting and Environmental

As part of the PEA process, the Company determined that the most practical and economical mining and processing scenario would be to design the heap leach pad and SX-EW facility on unpatented claims north of the open-pit. This decision was made based on slope angles and safety factor calculations.

As a result, the Empire project will require the submission of a Plan of Operations and Record of Decision prior to operation. Project permitting will require a joint agency review and approval process for disturbance on patented land subject to regulation by the Idaho Department of Lands (IDL) and unpatented land in the Salmon-Challis National Forest (SCNF) managed by the Forest Service. It is anticipated that the Forest Service will be the lead agency for environmental reviews of the entire project, which will solicit input from state agencies and other federal agencies.

To initiate permitting, the Company will submit a Plan of Operation to the Forest Service. The plan must include general information including dates and duration of proposed operations, site location, access - including construction specifications for earthwork, layout of operation, description of operational details, engineering designs for structures, and environmental protection measures (EPMs). The EPMs must address air and water quality, fish and wildlife impacts, cultural resources, protection of scenic values, and solid and hazardous waste management. There are no water quality concerns that have been identified in the Project Area.

The Forest Service will conduct an environmental review, as required by the National Environmental Policy Act ("NEPA"). Formal scoping of the NEPA review will be initiated after submittal of the Plan of Operation. The project may be reviewed under an Environmental Assessment, since it does not fall into one of the categories of actions that normally require an Environmental Impact Statement, particularly since the claim block is not located within an inventoried roadless area, wilderness area, or proposed wilderness area.

A reclamation performance bond will be posted prior to the issuance of the Record of Decision. A single bond instrument could be issued to satisfy the requirements of the Forest Service and IDL on the unpatented and patented claims.

Economic Model and Analysis

The PEA for the Empire Project evaluates the project as a heap leach SX-EW copper cathode operation at a mining rate of 2 million tonnes of ore a year. The economic viability of the Project was evaluated using a constant-dollar, after-tax discounted cashflow.

Mineral resources were incorporated into the economic evaluation using Measured, Indicated and Inferred material. These are based on the November 2017 NI 43-101 resources.

After-Tax cash flows were calculated on a yearly basis for the life of the mine. Federal, state and local taxes were considered for this evaluation.

The Project is projected to have robust economics at the base case copper price of $3.75/lb. The projected sensitivities in the Net Present Value from variations in the discount rate have also been calculated on an After-Tax basis

The project economics are summarized below:

Imperial

Metric

Resources

Cut-off grade

0.24%

0.24%

Measure & indicated

short tons/tonnes

10,024,000

9,096,189

Cu Grade

%

0.56%

0.56%

Inferred

short tons/tonnes

8,098,000

7,348,457

Cu Grade

%

0.46%

0.46%

Waste

short tons/tonnes

48,565,000

44,069,873

Strip Ratio

2.68

2.68

Mine Production

Average ore per day

short tons/tonnes

6,200

5,626

Average ore per year

short tons/tonnes

2,200,000

1,996,370

Average waste per year

short tons/tonnes

5,896,000

5,350,272

Life of mine (LOM)

years

8

8

Copper Production

LOM Cu grade

%

0.52%

0.52%

Contained copper

short tons/tonnes

94,234

85,512

Average metallurgical recovery

%

76.0%

76.0%

LOM recovered copper

short tons/tonnes

71,618

64,989

Average annual copper production

short tons/tonnes

8,952

8,124

LOM Revenue

Base case copper price

US$ / short ton / per tonne

7,500

8,265

US$ / pound copper

3.75

3.75

LOM gross revenue

US$

537,136,080

537,136,080

LOM Net revenue after freight, insurance, royalties

US$

520,084,000

520,084,000

LOM Operating Costs

Mining

US$

115,480,000

Processing

US$

122,959,000

G&A

US$

22,511,000

Mining licences & property tax

US$

3,461,000

Total

US$

264,411,000

264,411,000

LOM EBITDA

US$

255,673,000

Average annual revenue

US$

65,010,500

Average annual operating cost

US$

33,051,375

Average annual EBITDA

US$

31,959,125

31,959,125

Pre Production Capital Costs

Lease purchase or contract mining

US$

185,000

Crushing & agglomerating

US$

11,122,000

Leach pads & ponds

US$

5,419,000

Process plant

US$

21,629,000

Infrastructure

US$

3,435,000

Site general

US$

13,879,000

Utilities

US$

3,538,000

Bonding

US$

2,000,000

Total

US$

61,207,000

61,207,000

Ongoing Capital Costs

Crushing & agglomerating

US$

2,145,000

Leach pads & ponds

US$

7,085,000

Mining equipment lease purchase

US$

18,310,000

Reclamation bonding

US$

4,000,000

Salvage

US$

- 643,000

Total

US$

30,897,000

30,897,000

Cash Flow

LOM cash flow pre tax

US$

134,580,000

LOM cash flow after tax

US$

117,940,000

NPV 5.0%

NPV pre tax

US$

82,800,000

NPV after tax

US$

70,580,000

NPV 7.5%

NPV pre tax

US$

64,210,000

NPV after tax

US$

53,660,000

IRR

IRR pre tax

%

26.3%

26.3%

IRR after tax

%

23.5%

23.5%

Operating Costs / Pound Copper

Mining

US$ / pound copper

0.81

Processing

US$ / pound copper

0.86

General & Administration

US$ / pound copper

0.16

Mine License & Property Tax

US$ / pound copper

0.02

Cash Cost / lb Cu

US$ / pound copper

1.85

 

Capital Cost Estimates

Capital costs for developing the Empire mine are estimated from other recent mine development capital costs as well as quotes for some of the larger components. The operating costs were determined based on HRC's industry knowledge and prior experience, Info Mine's Cost Mine Service, and actual costs data from operating mines of similar size. Golder Associates prepared the heap leach facility construction capital cost estimate, and M3 Engineering contributed PEA-level design information and takeoff data for the plant capital and operating cost estimates.

The open pit mining equipment is assumed to be leased rather than purchased. The type of lease is assumed to be a capital equipment lease. Total initial capital is estimated at $67.9 million, including a $6.8 million contingency

Sustaining capital costs are included for phase 2 and 3 of the leach pad. A portion of the leach pad conveying system is also delayed for purchase into year 1.

Operating Cost Estimates

Operating costs for the Project were developed from material and consumption data provided by M3 Engineering, HRC's industry knowledge and prior experience, and Info Mine's Cost Mine Service.

Taxes

State, local, and federal taxes, including income taxes and the Idaho Mining License tax, have been considered in this study, and are included in the economic analysis.

Royalties

A 2.5 percent royalty, calculated on the gross proceeds less transportation and refining costs, has been included for all the metal produced, as required by underlying agreements.

Consultants

The following consultants have contributed to the PEA and have been involved with the project since Q2 2017:

· Resources and Mine Planning Hard Rock Consulting LLC - Lakewood, Colorado

· Open Pit Slope Stability Call & Nicholas - Tucson, Arizona

· Heap Leach Pad and Ponds Designs Golder Associates Inc - Tucson, Arizona

· Metallurgical Testwork Minerals Technology LLC - Tucson, Arizona

· Process Plant and Infrastructure M3 Engineering & Technology Corp. - Tucson, Arizona

· Environmental Base Line and Permits CES - Pocatello, Idaho

 

Qualified Person

 

The information in this announcement has been reviewed by Roger Turner A.C.S.M., M.Sc., M.I.M.M.M., C.Eng., Chief Technical Officer and Director of the Company. Mr Turner is a graduate mining engineer from the Camborne School of Mines with an MSc in Economic Geology from Leicester University with more than 40 years' experience in mine development, construction and operation and is a qualified person under the AIM Rules. Mr Turner consents to the inclusion of the information in the form and context in which they appear.

 

Market Abuse Regulation (MAR) Disclosure

 

Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No 596/2014 until the release of this announcement.

**ENDS**

 

For further information please visit www.pgmining.com or contact:

Phoenix Global Mining Ltd

Dennis Thomas / Richard Wilkins

c/o St Brides Partners

+44 20 7236 1177

 

SP Angel

(Nominated Advisor)

 

Lindsay Mair / Caroline Rowe

Tel: +44 20 3470 0470

Brandon Hill Capital (Broker)

Jonathan Evans / Oliver Stansfield

Tel: +44 20 3463 5000

St Brides Partners

(Financial PR)

Charlotte Page / Susie Geliher

Tel: +44 20 7236 1177

 

 

Notes

 

Phoenix Global Mining Ltd (AIM: PGM) is a North American-focused, base and precious metal explorer and developer, which is fast-tracking the historically-producing Empire Mine in Idaho, USA, back into production and exploring for cobalt in Idaho and gold in Canada.

 

Having established an initial copper oxide JORC and NI 43-101 resource of 19.4 mt grading 0.47% copper ('Cu') for 90,547t contained Cu, plus zinc, gold and silver, Phoenix has defined a two-phase development strategy. Phase One is focused on commencing low cost, open pit production from the current oxide resource, targeting 7,000t copper cathode per annum. Stage Two will look to extend the life of mine by targeting the deeper (below c.120m), higher grade copper sulphides, where intercepts of up to 11.4% Cu have been recovered. Preliminary Economic Analysis work on the priority open pit oxide resource is already underway. It is estimated that only 5% of the potential ore system has been explored to date and accordingly there is significant opportunity to increase the resource through phased exploration; the current resource relates to the oxide resource only, which remains open along strike and does not include the deeper, higher grade sulphides. Phoenix owns 80% of Empire.

 

The Company also holds 100% of the Bighorn and Redcastle cobalt-copper properties in Idaho, USA, which are located north of the Empire Mine on the Idaho Cobalt Belt. These are situated close to the town of Cobalt and are close to projects being advanced by Canadian junior miners, including eCobalt Solutions and US Cobalt. Exploration will continue during 2018 to identify drilling targets.

 

The Company has also acquired an exclusive option to earn into 80% of the Gordon Lake Project, in the Northwest Territories, Canada, a high-grade shear hosted gold project comprising of 17 known mineralised zones of which only four have been tested with 59 diamond drill holes. The Company will proceed to examine the optimal way forward to develop the project as a low-cost underground gold producer.

 

With a management team that has successfully constructed, commissioned and operated mines and low risk, mining-friendly jurisdictions with excellent infrastructure, Phoenix is looking to fulfil its ambitions to become a mid-tier base and precious metals producing company, offering exposure to three high value and high demand metals with compelling demand/supply fundamentals.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLIPMRTMBIBBIP
Date   Source Headline
15th May 20244:51 pmRNSFinal results for the year ended 31 December 2023
15th May 20244:34 pmRNSConditional Subscription for $80m of Copper Bonds
7th May 20247:00 amRNSEmpire Open-Pit Mine Mineral Reserve Statement
8th Apr 202412:25 pmRNSBlock Listing Six Monthly Return
27th Mar 20247:00 amRNSExtension of Warrants
19th Mar 20247:00 amRNSPurchase of Empire Processing Equipment Finalised
4th Mar 20247:00 amRNSRefinancing of Short-Term Loan Facility
19th Feb 20247:00 amRNSUpdate: Purchase of Equipment and Debt Refinancing
31st Jan 20246:15 pmRNSResult of Retail Offer and Additional Subscription
26th Jan 202412:10 pmRNSResult of Placing and Subscription
26th Jan 20249:25 amRNSClose of Accelerated Bookbuild
26th Jan 20247:01 amRNSRetail Offer
26th Jan 20247:00 amRNSProposed Placing, Subscription and Retail Offer
18th Jan 20247:00 amRNSOperational Update
5th Jan 20247:00 amRNSCorporate copper bonds and loan facility update
11th Dec 20237:00 amRNSExtension of Loan Facility
20th Nov 20237:00 amRNSExtension of Loan Facility
24th Oct 20237:00 amRNSUpdate for Navarre Creek Exploratory Drilling
10th Oct 20235:02 pmRNSBlock Listing Six Monthly Return
28th Sep 20237:00 amRNSInterim Results
4th Sep 20237:00 amRNSResults of Metallurgical Testing at Empire Mine
17th Jul 20237:00 amRNSCommencement of Navarre Creek Drilling Programme
23rd Jun 20237:00 amRNSExtension of Loan Facility
8th Jun 202312:33 pmRNSResult of Annual General Meeting
6th Jun 20237:00 amRNSPreliminary Results of Metallurgical Testing
25th May 20237:00 amRNSFinal results for the year ended 31 December 2022
12th Apr 20237:00 amRNSExploration Drilling Results at the Empire Mine
6th Apr 20237:00 amRNSBlock Listing Six Monthly Return
29th Mar 20239:05 amRNSSecond Price Monitoring Extn
29th Mar 20239:00 amRNSPrice Monitoring Extension
24th Mar 20239:05 amRNSSecond Price Monitoring Extn
24th Mar 20239:00 amRNSPrice Monitoring Extension
24th Mar 20237:00 amRNSCorporate Update
16th Mar 20237:00 amRNSFurther Results of Metallurgical Core Drilling
12th Jan 20237:00 amRNSFurther Results of Metallurgical Core Drilling
5th Jan 20237:00 amRNSPhoenix Subsidiary Welcomes New General Manager
4th Jan 20237:00 amRNSAdditional Results of Metallurgical Core Drilling
9th Dec 202211:00 amRNSPrice Monitoring Extension
10th Nov 20227:00 amRNSInitial Results of Metallurgical Core Drilling
6th Oct 20227:00 amRNSBlock Listing Six Monthly Return
29th Sep 202211:05 amRNSSecond Price Monitoring Extn
29th Sep 202211:00 amRNSPrice Monitoring Extension
29th Sep 20227:00 amRNSInterim Results
23rd Sep 20229:06 amRNSSecond Price Monitoring Extn
23rd Sep 20229:00 amRNSPrice Monitoring Extension
20th Sep 20221:47 pmRNSTR-1: Notification of major holdings
15th Sep 20222:05 pmRNSSecond Price Monitoring Extn
15th Sep 20222:00 pmRNSPrice Monitoring Extension
13th Sep 20222:05 pmRNSSecond Price Monitoring Extn
13th Sep 20222:00 pmRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.