Operations Update

8 Jun 2010 07:00

RNS Number : 2100N
Petroneft Resources PLC
08 June 2010
 



 

PetroNeft Resources plc

("PetroNeft" or the "Company")

 

Operations Update

 

Positive result from first three production wells, pipeline complete and awaiting final testing

 

PetroNeft Resources plc (AIM: PTR) owner and operator of Licences 61 and 67, Tomsk Oblast, Russian Federation, is pleased to provide an update on its operations.

 

Highlights:

 

·; First three production wells successfully drilled

 

·; Pipeline construction complete, testing imminent

 

·; Construction of production facilities on schedule

 

·; Arbuzovskaya exploration well site preparations nearing completion

 

Development Drilling

Drilling of the first three of nine production wells at the Lineynoye oil field planned for 2010 have now been completed ahead of schedule. Preliminary log and survey data indicate that the results of these wells are in line with expectations:

 

Well No.

Top of reservoir vertical depth subsea metres

Gross hydrocarbon interval

metres

Net oil pay

metres

Comments

 

109

 

2,392

 

14.0

 

10.2

Interval is completely saturated with oil.

110

2,395

13.0

8.9

Interval is completely saturated with oil, bottom 2.7m appears to be tight reservoir.

 

112

 

2,401

 

16.2

 

12.0

Interval is completely saturated with oil.

 

 

The wells penetrated the top of the reservoir 5 to 8 metres higher than prognosis. The field wide oil-down-to in the reservoir is at 2,430 metres true vertical depth which is well below the oil-down-to in any of the production wells drilled thus far. This relationship will help the future production performance of the wells.

Production casing has been run in the wells and successfully cemented. The drilling rig has been moved along its rails and the fourth well, No. 113, has been spudded. A work-over rig has begun the process of perforating and installing electrical submersible pumps in wells 109, 110 and 112. Well No. 111 will be the final well drilled in the 2010 programme as an operational decision was made to re-order the drilling of wells.

 

Pipeline Construction

Construction of the 60km export pipeline from the Lineynoye field to the Kiev-Eganskoye field is complete. The pressure and hydro testing of the pipeline will commence later this month following which the pipeline will be ready to receive first oil production on schedule in the third quarter of 2010.

 

Production Facilities

Construction of production facilities continues and is on schedule to be completed for first oil production in the third quarter of 2010.

 

Arbuzovskaya Exploration Well

Rig-up operations for the Arbuzovskaya exploration well are over 80% complete and drilling is scheduled to commence in October after the nine well production drilling programme has been completed. This is the first of at least three exploration/delineation wells to be drilled in the northern part of Licence 61 in 2010 and 2011. This programme has the potential to materially increase both Group reserves and the long term production potential of Licence 61.

 

Dennis Francis, Chief Executive Officer of PetroNeft Resources plc, commented:

 

"The drilling of our production wells remains ahead of schedule and we are delighted with the well results to date. Pipeline testing is due to commence in the coming weeks and construction of production facilities continues at pace. We look forward to achieving first production in the third quarter and our year-end production target of 4,000 bopd"

 

 

For further information, contact:

 

Dennis Francis, CEO, PetroNeft Resources plc

+1 713 988 2500

Paul Dowling, CFO, PetroNeft Resources plc

+353 1 443 3720

John Frain/Brian Garrahy, Davy (NOMAD and Joint Broker)

+353 1 679 6363

Elijah Colby, Canaccord Adams Limited (Joint Broker)

+44 207 050 6500

Martin Jackson, Citigate Dewe Rogerson

+44 207 638 9571

Joe Murray/Ed Micheau, Murray Consultants

+353 1 498 0300

 

The information contained in this announcement has been reviewed and verified by Mr. Dennis Francis, Director and Chief Executive Officer of PetroNeft, for the purposes of the Guidance Note for Mining, Oil and Gas Companies issued by the London Stock Exchange in March 2006. Mr. Francis holds a B.S. Degree in Geophysical Engineering and a M.S. Degree in Geology from the Colorado School of Mines. He has also graduated from the Harvard University Program for Management Development. He is a member of the American Association of Petroleum Geologists and the Society of Exploration Geophysicists. He has over 35 years experience in oil and gas exploration and development.

 

Forward Looking Statements

This announcement contains forward-looking statements. These statements relate to the Company's future prospects, developments and business strategies. Forward-looking statements are identified by their use of terms and phrases such as 'believe', 'could', 'envisage', 'potential', 'estimate', 'expect', 'may', 'will' or the negative of those, variations or comparable expressions, including references to assumptions.

 

The forward-looking statements in this announcement are based on current expectations and are subject to risks and uncertainties that could cause actual results to differ materially from those expressed or implied by those statements. These forward-looking statements speak only as at the date of this announcement.

 

Notes to Editors

 

PetroNeft Resources plc was established in 2005 to develop oil and gas assets in Russia and the Former Soviet Union and was admitted to the London AIM and Dublin IEX Markets on 27th September 2006.

 

The main asset of the Company is a 100% interest in Licence 61, a 4,991 sq km oil and gas licence in the Tomsk Oblast in Russia, held through its wholly owned Russian subsidiary, Stimul-T. The Licence is located in the prolific Western Siberian Oil and Gas Basin and contains four known oil fields, Lineynoye, Tungolskoye, West Lineynoye and Kondrashevskoye, and over 25 exploration Prospects and Leads. In December 2009 the Company announced the acquisition of a second oil and gas licence in the Tomsk Oblast in Russia, Licence 67.

 

The Board and Management of PetroNeft is made up of highly experienced professionals, including former Marathon Oil Company executives, in the International and Russian Oil Exploration and Development business. The Russian Management team also has extensive local knowledge and experience in the exploration and development of oil and gas fields in the Tomsk Oblast.

 

Since acquiring Licence 61 in May 2005, the Company has carried out extensive reprocessing and reinterpretation, using modern technology, of over 2,500 line kms of vintage seismic acquired in Soviet times. It has also digitised and reinterpreted the logs of 14 wells drilled on the Licence since 1972. PetroNeft also has acquired over 1,000 line kms of new CDP-2D infill seismic and drilled six new exploration/delineation wells. This new seismic and six well drilling programme fully satisfied the exploration work obligation for the full 25 year licence term.

 

Reserve estimates on Licence 61 prepared by Ryder Scott as of 1 January 2010 were:

 

Proved reserves

(1P)

10.4 million bbls

Proved and probable reserves

(2P)

70.8 million bbls (P1+P2)

Proved, probable and possible reserves

(3P)

531.3 million bbls (P1+P2+P3)

 

 

PetroNeft has also recently announced a crude oil transportation agreement with Nord Imperial, effective for 25 years, which significantly reduces the various permits and associated approvals required for pipeline construction as well as the costs. The new route, from Lineynoye to Kiev-Eganskoye runs adjacent to the Tungolskoye and Kondrashevskoye oil fields and will create useful synergies for future development phases.

 

On 21 September 2009 PetroNeft announced a US$27 million fund raising from international institutional investors which fully funds the Phase 1 Development Plan for the Lineynoye and West Lineynoye Fields. PetroNeft expects to have year-round production from the Licence in the third quarter of 2010 with production of 4,000 bopd by the end of 2010. Production from the Phase 1 project is expected to peak at around 12,000 bopd in 2012.

 

On 28 May 2010, PetroNeft announced a US$30 million debt facility with Macquarie Bank.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCDBGDLXGGBGGR
Date   Source Headline
9th Jul 20087:00 amRNSDebt Facility
7th Jul 20087:00 amRNSRussian Reserves Update
30th Jun 20082:55 pmRNSDocument Availability
30th Jun 20087:00 amRNSPreliminary Results
26th Jun 20087:00 amRNSOperations Update
18th Jun 20089:38 amRNSAppointment of Joint Broker
17th Jun 20087:00 amRNSIEX Notice
12th Jun 200811:03 amRNSIssue of Equity
6th May 20087:02 amRNSBoard Appointment
16th Apr 20087:01 amRNSOperational Update
5th Mar 20087:00 amRNSOperational Update
25th Feb 20084:22 pmRNSPDMR Dealing
21st Feb 20085:22 pmRNSIssue of Options
19th Feb 20087:00 amRNSReserve Update
14th Jan 20087:01 amRNSAcquisition of Refinery Site
20th Dec 20077:01 amRNSOperational Update
10th Dec 20077:00 amRNSIEX Notice
5th Dec 20077:01 amRNSExercise of Options
23rd Nov 20077:00 amRNSOperational Update
20th Sep 20077:01 amRNSOperational Update
12th Sep 20077:01 amRNSInterim Results
5th Sep 20077:01 amRNSCFO Appointment
21st Aug 200712:38 pmRNSAIM Rule 26
14th Aug 20077:01 amRNSOperational Update
30th Jul 20077:00 amRNSIssue of Equity
17th Jul 200710:06 amRNSHolding in Company
11th Jul 20077:00 amRNSUS$15.26 million Placing
29th Jun 20075:33 pmRNSResult of AGM
19th Jun 20077:01 amRNSOperational Update
29th May 20077:02 amRNSOperational Update
21st May 20077:01 amRNSAppointment of Joint Broker
17th May 20077:01 amRNSOperational Update
24th Apr 20078:29 amRNSDrilling Update
5th Apr 20074:14 pmRNSDirector Shareholding
4th Apr 20077:00 amRNSDirector Shareholding
3rd Apr 20074:03 pmRNSDirector Shareholding
3rd Apr 20077:01 amRNSPreliminary Results
5th Mar 20077:04 amRNSOperational update
30th Jan 200712:34 pmRNSDirector/PDMR Shareholding
1st Dec 20067:01 amRNSShare Price Movement
23rd Oct 20067:01 amRNSInterim Results
27th Sep 20062:29 pmRNSNew IEX Admission
27th Sep 20067:00 amRNSAdmission to AIM/IEX

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.