RHA Drilling Update

3 Oct 2018 07:05

RNS Number : 7666C
Premier African Minerals Limited
03 October 2018
 

Premier African Minerals Limited / Ticker: PREM / Index: AIM / Sector: Mining

For immediate release

 

3 October 2018

 

Premier African Minerals Limited

RHA Drilling Update

 

Premier African Minerals Limited ("Premier" or the "Company") is pleased to provide an update on its drilling programme at the RHA Tungsten Mine ("RHA") in Zimbabwe in which Premier has a 49% interest and is the operator. As announced on 14 September the Company is drilling up to 2,750 metres to expand as well as to increase the Resources at RHA with the view to resume mining activities.

 

Highlights

· 9 diamond drill holes completed for 941 metres.

· Hole RHADD34 intersected 1.86 metres of 2.39 kg/t WO and 44.8 kg/t over 0.29m

· Drilling programme designed to expand and as well increase the resource confidence and guide future mine planning

· Sample preparation and assay is completed on site using owned XRF and standard reference material. Validations to be conducted by SGS

· Core logging of completed diamond drill holes has identified numerous wolframite and chalcopyrite bearing intercepts.

 

The preliminary analytical results set out in this announcement from underground drilling at RHA have been returned from the Company's own on-site analysis and samples are being submitted to SGS South Africa and the results of this analysis will be released in due course.

 

George Roach, Premier's CEO, commented: "The preliminary internal assay results from RHADD34 indicate multiple mineralised load structures with wolframite at commercial grades and visible copper mineralisation in the form of chalcopyrite co-existent in the same ore bodies as the wolframite. Wolframite concentrates previously produced at RHA have always contained copper, but no attempt was made to separately recover any copper, and whilst the production of any potential by- product is speculative at this time, the visibly pervasive presence needs a fuller investigation, and independent assay.

 This is likely to include floatation tests to understand what recoveries could be expected from these copper co-existent intersections. Whilst it is still too early to take a decision on whether to extend the underground operations at RHA through a new decline shaft or deepening of the current vertical shaft, projected mineralisation at depth is confirmed. Whilst drilling in the open pit has not been completed, the results obtained so far from the western end of the pit do not support a continuation of mining with the current plant configuration.

The results did however indicate that mineralisation is increasing in an easterly direction and it is likely that the pit may be extended at a time in the future if a decline shaft is constructed. Any significant extension to the open pit in an easterly direction will interfere with the existing vertical shaft."

 

Drilling Programme

Premier commenced a diamond drilling programme at RHA in the beginning of September 2018. The drilling programme is designed to expand the underground declared resource base as well as assisting with a determination of the future mining of the open pit. To date 9 holes have been drilled totalling 941 metres. The Company expects to complete the drilling programme by the end of October and will announce further meaningful intersections. Significant preliminary drilling results (subject to confirmation by SGS South Africa) returned to date include:

 

Table 1 - Drilling intercepts

 

Hole ID

From (m)

To (m)

Length (cm)

WO₃ kg/t

RHADD34

58,96

59,24

28

1,47

RHADD34

60,1

61,17

107

0,99

RHADD34

95,85

96,14

29

44,88

RHADD34

118,64

119,02

38

4,13

RHADD34

126,02

127

98

1,12

RHADD34

145,32

145,62

30

9,08

RHADD34

155,26

155,34

8

1,67

RHADD34

167,1

167,39

75

1,54

RHADD34

167,39

167,85

46

0,67

RHADD34

169,21

169,86

65

6,87

RHADD34

173,86

174,2

34

7,24

RHADD34

180,3

181,2

90

0,91

RHADD34

205,58

205,93

35

4,99

RHADD34

211,22

213,08

186

2,39

RHADD34

215,14

215,54

40

4,07

RHADD34

218,09

218,37

28

1,31

RHADD34

223,64

224,19

55

2,02

RHADD34

226,68

226,82

14

0,88

RHADD34

238,84

239,04

20

3,80

 

Notes:

(i) Reported intervals are downhole widths, the true widths may be narrower.

(ii) RHA's on-site laboratory is not certified for analysis and these results should be considered preliminary in nature. Results from a certificated laboratory will be released as and when available

 

QA/QC

Sample preparation is done at site and sample assays and the analytical results set out in this announcement from underground drilling at RHA have been returned from the Company's own on-site analysis out using RHA's own XRF. Every eighth sample analysed is a Certified Standard Reference Material ("CRM", GW-02 by Geostats, Australia) for tungsten. At least 20 per cent. of all samples will be submitted to SGS, South Africa, for verification of mineralisation and grades. The Company would further expect that in the preparation of any future independent reserve / resource statement undertaken in compliance with a recognised standard, the independent authors of such a statement would not use preliminary assay results but would only use assay results reported by an appropriately certificated laboratory.

 

 Qualified Person

Wolfgang Hampel, Senior Geologist with Premier African Minerals Limited, has reviewed and approved this release to the extent that reference is made to RHA. Wolfgang Hampel has 27 years' experience in the African, American, European and Asian exploration and mining industry and holds a Diploma in Economic Geology (Dipl.-Geol.) from the Technical University of Munich. He is a registered European Geologist (EurGeol). n° 1261 with the European Federation of Geologists.

 

Market Abuse Regulation (MAR) Disclosure

Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No 596/2014 until the release of this announcement. The person who arranged for the release of this announcement on behalf of the Company was George Roach, Director.

Enquiries:

Fuad Sillem

Premier African Minerals Limited

Tel: +44 (0)7734 922074

Michael Cornish / Roland Cornish

Beaumont Cornish Limited

(Nominated Adviser)

Tel: +44 (0) 20 7628 3396

Jerry Keen/Edward Mansfield

Shore Capital Stockbrokers Limited

Tel: +44 (0) 20 7408 4090

 

Notes to Editors:

Premier African Minerals Limited (AIM: PREM) is a multi-commodity mining and natural resource development company focused on Southern Africa with its RHA project in Zimbabwe.

 

The Company has a diverse portfolio of projects, which include tungsten, rare earth elements, lithium and tantalum in Zimbabwe, encompassing brownfield projects with near-term production potential to grass-roots exploration. In addition, the Company holds 5,010,333 shares in Circum Minerals Limited ("Circum"), the owners of the Danakil Potash Project in Ethiopia, which has the potential to be a world class asset. Premier also has an interest in Arc Minerals that has a number of mineral assets in Europe and Africa.

 

Forward Looking Statements:

Certain statements in this announcement are or may be deemed to be forward looking statements. Forward looking statements are identified by their use of terms and phrases such as ''believe'' ''could'' "should" ''envisage'' ''estimate'' ''intend'' ''may'' ''plan'' ''will'' or the negative of those variations or comparable expressions including references to assumptions. These forward-looking statements are not based on historical facts but rather on the Directors' current expectations and assumptions regarding the Company's future growth results of operations performance future capital and other expenditures (including the amount. nature and sources of funding thereof) competitive advantages business prospects and opportunities. Such forward looking statements reflect the Directors' current beliefs and assumptions and are based on information currently available to the Directors. Many factors could cause actual results to differ materially from the results discussed in the forward-looking statements including risks associated with vulnerability to general economic and business conditions competition environmental and other regulatory changes actions by governmental authorities the availability of capital markets reliance on key personnel uninsured and underinsured losses and other factors many of which are beyond the control of the Company. Although any forward-looking statements contained in this announcement are based upon what the Directors believe to be reasonable assumptions. The Company cannot assure investors that actual results will be consistent with such forward looking statements.

 

 

 

ENDS

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDZMMGGGZVGRZZ
Date   Source Headline
29th Apr 20157:00 amRNSLoan Note Instrument
28th Apr 20157:00 amRNSConstruction on Schedule at RHA Tungsten Project
27th Apr 201510:17 amRNSAdditional US$250,000 Loan Facility
9th Apr 20157:00 amRNSCorporate Update
7th Apr 20157:00 amRNSAcceptance of Environmental Impact Assessment
2nd Apr 20159:52 amRNSConstruction on schedule at RHA Tungsten Project
1st Apr 201512:54 pmRNSTotal Voting Rights
23rd Mar 201512:22 pmRNSConstruction on schedule at RHA Tungsten Project
16th Mar 20154:22 pmRNSIssue of Shares and Options
9th Mar 20159:50 amRNSConversion of Loan Note and Issue of Equity
9th Mar 20159:47 amRNSTungsten Off-take Agreement Completed
26th Feb 20152:40 pmRNSAppointment of Director
10th Feb 20151:06 pmRNSExercise of Options and Directors' Dealings
10th Feb 201510:13 amRNSExploration Update on Zimbabwe Projects
3rd Feb 20157:00 amRNSSigning of unsecured convertible loan note
30th Jan 201512:25 pmRNSResult of AGM
28th Jan 20157:00 amRNSRHA Tungsten Project implementation study complete
23rd Jan 20157:00 amRNSCircum Minerals Update
12th Jan 201510:15 amRNSFifth tranche of USD1 million received from Circum
8th Jan 20153:56 pmRNSNotice of AGM
25th Nov 20147:00 amRNSRHA Tungsten Project Update
12th Nov 20147:00 amRNSFourth tranche of USD1million received from Circum
28th Oct 20147:00 amRNSRHA Tungsten Project Open Pit Low Capital Strategy
27th Oct 20142:57 pmRNSHolding(s) in Company
14th Oct 20141:13 pmRNSHolding(s) in Company
13th Oct 20147:00 amRNSRHA Tungsten Preliminary Economic Assessment
7th Oct 20145:22 pmRNSRHA Tungsten Project Update
2nd Oct 20147:00 amRNSCompletion of Equity Swap and Payment Acceleration
29th Sep 20145:15 pmRNSHolding(s) in Company
29th Sep 20147:00 amRNSInterim Results
16th Sep 20143:01 pmRNSCorporate & Environmental Impact Assessment Update
10th Sep 20147:00 amRNSRHA Test Work Results
5th Sep 20147:00 amRNSRHA Tungsten Project Update
1st Sep 20146:19 pmRNSHolding(s) in Company
29th Jul 20148:50 amRNSCorporate Update
16th Jul 20148:42 amRNSSecond Tranche of $1 Million Received from Circum
26th Jun 20147:00 amRNSFinal Results for the Year Ended 31 December 2013
19th Jun 20147:00 amRNSRHA Project Update
20th May 20147:00 amRNSIssue of Equity
15th May 20147:00 amRNSCircum Danakil Option Exercise
13th May 20147:00 amRNSAgriMinco Danakil Option Exercise
9th May 20147:00 amRNSAgriMinco Danakil Option Approved
2nd May 20147:00 amRNSUpdate on AgriMinco Danakil Option
1st May 201412:21 pmRNSIncrease in contained Tungsten Metal at RHA
11th Apr 20147:00 amRNSAgriMinco Danakil Option Update
28th Mar 20147:01 amRNSDrilling and Corporate Update
20th Mar 20147:00 amRNSAgriMinco Danakil Option
18th Mar 20141:10 pmRNSAgriMinco Update
13th Mar 20147:00 amRNSHigh Grade Assay Results and New Mineralisation
12th Feb 201411:09 amRNSAgriMinco Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.