Lomada Progress Report

8 Sep 2010 07:00

RNS Number : 3055S
Patagonia Gold PLC
08 September 2010
 



PATAGONIA GOLD PLC

 

8th September 2010

 

DEVELOPMENT COMMENCES

LOMADA GOLD-HEAP LEACH PROJECT

SANTA CRUZ PROVINCE, ARGENTINA

 

 

Patagonia Gold Plc is pleased to announce the commencement of earthworks for the first stage of the Lomada Gold-Heap leach project on 30 August 2010.

 

The Lomada de Leiva gold-heap leach project (Lomada project) is located on the La Paloma property block approximately 40km to the south of the town of Perito Moreno and currently contains a Canadian National Instrument 43-101 compliant resource of 237,000 ounces (ozs) of gold.

 

The first stage of the Lomada project consists of the construction of a 50,000 tonne trial heap leach, which based on 70% recovery, is estimated to yield approximately 2,200 oz. of gold for the first 6 metre loading.

 

Earthworks, pad construction, mining and loading are scheduled for completion in Q4 2010. Tenders for the associated infrastructure are being finalised for award in 4th week September with completion planned for early Q1, 2011. Irrigation of the heap leach pad will then commence with the production of the first gold soon thereafter.

 

Subject to successful leaching and additional permitting, further loading and production from the first stage heap leach will continue until the main 5 million tonne heap leach project is fully operational, scheduled for Q4 2011.

 

The features of the main heap leach project are:

 

·; Low pre-production capital of $8.5 million

·; Production of 21,000 oz. of gold/year, for a mine life of 7 years, at a cash cost of $299/oz

·; Project cash flow before tax, of $63.6 million, based on a cash price of $850/oz. gold

 

There is significant potential to increase the mine life at Lomada de Leiva with further drilling on the remaining inferred resource not included in the main heap leach project, together with additional extension and exploration drilling on Lomada de Leiva and the adjacent Breccia Sofia prospect.

 

Commenting, Managing Director Bill Humphries, said:

 

'It is very pleasing to announce the commencement of construction for Patagonia Gold's first gold mine, Lomada de Leiva, particularly with the knowledge that we have further exciting projects following in the development pipeline with the advanced Cap-Oeste, Cose and Manchuria projects.

 

Marc Sale, (BSC. Geology, Fellow AusIMM, member AIG) a Director and consultant to Patagonia Gold Plc and a qualified person as defined in National Instrument 43-101, has reviewed and verified all scientific or technical mining disclosure contained in this press release.

 

ENDS

 

For more information, please contact:

Bill Humphries/Richard Prickett

Patagonia Gold Plc

Tel: +44(0)20 7409 7444

 

Simon Raggett / Angela Peace

Strand Hanson Ltd

Tel: +44(0)20 7409 3494

David Bick / Mark Longson

Square 1 Consulting

Tel : +44(0)20 7929 5599

 

Alastair Stratton / Tim Graham

Matrix Corporate Capital LLP

Tel : +44(0)20 3206 7204 / +44(0)20 3206 7206

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCLRMATMBMMBJM
Date   Source Headline
26th Nov 20121:00 pmRNSGold Room commissioned and first gold production
22nd Nov 20127:00 amRNSLomada de Leiva Permit
25th Oct 20126:15 pmRNSPlacing and Subscription
17th Oct 201212:31 pmRNSUpdate: Lomada de Leiva
21st Sep 20124:40 pmRNSSecond Price Monitoring Extn
21st Sep 20124:35 pmRNSPrice Monitoring Extension
17th Sep 20127:00 amRNSHalf Yearly Report
10th Sep 20127:00 amRNSCap-Oeste Resource Update
4th Sep 20124:35 pmRNSPrice Monitoring Extension
20th Aug 20124:35 pmRNSPrice Monitoring Extension
31st Jul 20124:35 pmRNSPrice Monitoring Extension
13th Jul 20124:40 pmRNSSecond Price Monitoring Extn
13th Jul 20124:35 pmRNSPrice Monitoring Extension
9th Jul 20124:35 pmRNSPrice Monitoring Extension
5th Jul 20127:00 amRNSDrilling Report
2nd Jul 20124:35 pmRNSPrice Monitoring Extension
28th Jun 20121:00 pmRNSDirector Shareholding
6th Jun 20125:45 pmRNSResult of AGM
6th Jun 20127:00 amRNSPlacing and Subscription
1st Jun 20127:00 amRNSExercise of Options
30th May 201211:44 amRNSReplacement - Operations Update: Lomada de Leiva
30th May 20127:00 amRNSOperations Update - Lomada de Leiva Gold Project
29th May 20127:00 amRNSExercise of Options
25th May 20127:00 amRNSExercise of Options
14th May 20129:38 amRNSPosting of Annual Report and Notice of AGM
25th Apr 20127:00 amRNS2011 Year End Financial Results
28th Mar 20127:00 amRNSDrilling Update - Cap-Oeste
16th Mar 20124:35 pmRNSPrice Monitoring Extension
14th Mar 20127:00 amRNSExercise of Options
7th Mar 20127:00 amRNSDirector Shareholding
6th Mar 20121:30 pmRNSExercise of Options
21st Feb 20127:00 amRNSCap-Oeste Metallurgical Test Update
20th Feb 20127:00 amRNSGrant of Options
18th Jan 201212:30 pmRNSDirector/PDMR Shareholding
12th Jan 20127:00 amRNSCap-Oeste Drilling Update
5th Jan 20127:00 amRNSACQUISITION OF ESTANCIA 'EL TRANQUILO'
20th Dec 20117:00 amRNSExercise of Options
14th Dec 20117:00 amRNSAppointment of Broker
7th Dec 201112:00 pmRNSCommencement of trading on TSX
6th Dec 20117:00 amRNSDual Listing on TSX
2nd Dec 20117:00 amRNSDirectorate Change
30th Nov 20117:00 amRNSCAP-OESTE UPDATED RESOURCE ESTIMATE
14th Nov 20117:00 amRNSChange of Registrar
3rd Nov 201111:38 amRNSDirector Declaration
2nd Nov 20117:00 amRNSDirectorate Change
31st Oct 20117:00 amRNSProgress Update - COSE
26th Oct 20117:00 amRNSFOMICRUZ SHAREHOLDERS AGREEMENT
24th Oct 20117:00 amRNSDrilling Report
3rd Oct 20113:01 pmRNSIssue of Equity
28th Sep 20117:00 amRNSInterim Statement

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.