Roundtable Discussion; The Future of Mineral Sands. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksPan African Regulatory News (PAF)

Share Price Information for Pan African (PAF)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 24.00
Bid: 23.80
Ask: 24.05
Change: -0.30 (-1.23%)
Spread: 0.25 (1.05%)
Open: 23.60
High: 24.00
Low: 23.40
Prev. Close: 24.30
PAF Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Operational Update for 9 Months ended March 2019

17 May 2019 07:00

Pan African Resources Plc - Operational Update for 9 Months ended March 2019

Pan African Resources Plc - Operational Update for 9 Months ended March 2019

PR Newswire

London, May 17

Pan African Resources PLC

("Pan African" or “the Company" or “the Group”)

(Incorporated and registered in England and Wales under Companies Act 1985 with registered number 3937466 on 25 February 2000)

Share code on AIM: PAF

Share code on JSE: PAN

ISIN: GB0004300496

OPERATIONAL UPDATE FOR THE NINE MONTHS ENDED 31 MARCH 2019

Pan African is pleased to provide an operational update for the nine months ended 31 March 2019 (“Current Reporting Period”) as well as detail on progress with internal growth projects and initial production guidance for the 2020 financial year.

Pan African CEO Cobus Loots commented:

“The Group’s performance over the past nine months reflects our efforts to maintain Pan African’s position as a safe, low-cost and long-life gold producer. Safe, highly profitable and sustainable ounces at Elikhulu have replaced those of Evander’s loss-making underground operations. We continue to optimise Elikhulu, which delivered a throughput of 1.3-million tonnes in March 2019, 100,000 tonnes above the name plate capacity. The focus is now on maximising sustainable margins from this world-class operation.

We have commenced the development and equipping of Evander Mines’ 8 Shaft Pillar (“Evander Pillar operation”), with first gold expected in August 2019. The Evander 8 Shaft Pillar is expected to contribute an additional 20,000oz to 30,000oz per annum for three years, at an all-in sustaining costs (“AISC”) of approximately US$900 per ounce, therefore making a meaningful contribution to the Group’s near-term production and profitability. The operation will be mined by a specialised and experienced independent contractor given the nature of pillar mining. 

We have completed extensive feasibility work on Barberton Mines’ Royal Sheba project (“Royal Sheba Project”). Due to the Group’s disciplined capital allocation criteria and the capital cost estimates to develop this mine, the Company will not pursue the Royal Sheba Project on a stand-alone basis. The existing Barberton Mines’ processing plant infrastructure can be upgraded to process ore from this orebody. The benefits of this approach is the ability to expedite the environmental licencing process, shorten the timeline to production, enhance returns from mining this orebody and negate the requirement for external capital funding. We look forward to updating the market on this project in the months ahead.

We are confident the Group remains on track to meet its gold production guidance of 170,000oz for the full financial year to end 30 June 2019. With Elikhulu producing at a steady state for a full year and the incremental contribution from Evander’s Pillar operation, we expect to produce approximately 185,000oz of gold for the 2020 financial year, which is a sizeable increase in our gold production profile.”

Key highlights for the current reporting period

Operational results:

Gold production from the Group’s continuing mining operations (note 1) increased by 51.4% to 123,771oz (2018: 81,729oz), with robust performances from Barberton Mines’ underground operations and the Group’s tailings retreatment plants. Gold production from the Barberton complex increased by 11.7% to 72,944oz (2018: 65,297oz) Underground and surface mining increased by 3.4% to 54,857oz (2018: 53,034oz); and Barberton tailings retreatment plant (“BTRP”) increased by 47.5% to 18,087oz (2018: 12,263oz) due to an improved tonnage throughput and recoveries following the successful commissioning of the BTRP regrind mill in May 2018. The Elikhulu tailings retreatment plant (“Elikhulu”) processed 6,915,113 tonnes from September 2018 to March 2019 at a recovered grade of 0.135g/t with 29,881oz (929.4kg) of gold sold. This excludes the pre-production gold of 736oz (22.9kg) capitalised as pre-production income and gold inventory locked-up in the Elikhulu circuit; As previously communicated, the incorporation of the historical Evander tailings retreatment plant’s (“ETRP”) throughput of 200,000 tonnes per month into Elikhulu was completed in December 2018, which increased Elikhulu’s processing capacity to 1.2-million tonnes per month; Elikhulu’s all-in sustaining cost of production continues to be lower than previously anticipated, at less than US$600/oz; and Evander Mines’ remnant mining and surface sources contributed a further 20,946oz (2018: 16,432oz).

Note 1: The continuing mining operations include: Barberton Mines, Evander Mines, Elikhulu and Evander’s tailings retreatment plant (“ETRP”) as well as the mining and vamping of the remnant high-grade stopes as part of the phased closure of the underground mining operation. The continuing mining operations exclude the discontinued Evander Mines’ large-scale underground mining operation, which produced 42,118oz in the corresponding nine months ended 31 March 2018 (“corresponding reporting period”). The Group’s corresponding reporting period gold production, including discontinued operations, was 123,845oz.

Safety:

The Group’s focus on safety and related ongoing improvements continues to bear fruit, with material improvements in all categories of safety statistics during the current reporting period: The Group had no fatalities in this quarter (2018: no fatalities); The Group’s lost-time injury frequency rate improved substantially to 1.75 (2018: 3.79); and The reportable injury frequency rate improved substantially to 0.58 (2018: 1.17).

Evander 8 Shaft Pillar:

The feasibility study into the merits of mining the Evander 8 Shaft Pillar and high-grade areas in proximity to the pillar has been completed and the Pan African board of directors has approved the development of the project. Development and equipping of this area has already commenced, with first gold expected during August 2019. The Evander 8 Shaft Pillar will replace the current remnant underground mining and vamping production and is expected to contribute, on average, 30,000oz per annum over the next three financial years, with approximately 20,000oz of production forecast for FY2020. The Evander 8 Shaft Pillar mining feasibility highlights are: An average all-in sustaining cost of approximately R415,000/kg or US$900/oz over the life of the project (assuming US$/ZAR1:14.30); The existing Kinross processing plant and Evander’s 7 Shaft infrastructure will be used to treat and hoist the mined ore from the Evander 8 Shaft Pillar; Capital expenditure of approximately R70 million is to be incurred over the life of the project, of which R40 million is to be incurred upfront. All capital for the Evander 8 Shaft Pillar’s development will be funded from existing Group facilities; and A forecast payback period on the initial capital investment of less than one year, from commencement of mining, and a net present value of R369 million (US$25.8 million) at a 10% real discount rate and an assumed gold price of R600,000/kg or US$1,305/oz.

Royal Sheba Project:

The Group has completed the Royal Sheba project feasibility study and concluded that the merits of mining the near-surface resource, using an opencast mining method, did not meet the Group’s disciplined capital allocation criteria. This was as a result of higher than anticipated capital expenditure, largely due to the challenging topography of the Sheba valley. The emphasis is now to assess the merits of using an underground sub-level open stoping mining method by developing haulages from surface into the orebody. The existing Barberton Mines’ processing plant infrastructure can be upgraded to process ore from this orebody, which will substantially reduce the originally contemplated capital expenditure, and shorten the environmental licensing approval process. Shareholders will be updated on progress with Royal Sheba development plans in the coming months.

Restructure of Revolving Credit Facility (“RCF”):

The Group has received final credit approvals from its consortium of bankers and is finalising the legal agreements with the intent of having the restructured facility effective by 30 June 2019. The proposed restructured RCF will amortise according to the following repayment profile:
Amortisation profileRCF available balance (R million)Repayments (R million)
Up to 15 June 20201,000250
15 June 202075025
15 December 202072525
15 June 202170050
15 September 202165050
15 December 202160050
15 March 202255050
15 June 2022500500
The repayment profile of the Elikhulu project’s term debt facility, comprising 10 semi-annual, equal principal instalments of R100 million, commencing in December 2019, is unaffected by the restructuring of the RCF.

The financial and other information contained in this announcement has neither been reviewed nor audited by the Company’s external auditors.

For further information on Pan African, please visit the Company’s website at www.panafricanresources.com.

Rosebank

17 May 2019

Contact information
Corporate Office The Firs Office Building 2nd Floor, Office 204 Cnr. Cradock and Biermann Avenues Rosebank, Johannesburg South Africa Office: + 27 (0)11 243 2900Registered Office Suite 31 Second Floor 107 Cheapside London EC2V 6DN United Kingdom Office: + 44 (0)20 7796 8644
Cobus Loots Pan African Resources PLC Chief Executive Officer Office: + 27 (0)11 243 2900 Deon Louw Pan African Resources PLC Financial Director Office: + 27 (0)11 243 2900
Phil Dexter St James's Corporate Services Limited Company Secretary Office: + 44 (0)20 7796 8644John Prior Numis Securities Limited Nominated Adviser and Joint Broker Office: +44 (0)20 7260 1000
Ciska Kloppers Questco Corporate Advisory Proprietary Limited JSE Sponsor Office: + 27 (0)11 011 9200Ross Allister/David McKeown Peel Hunt LLP Joint Broker Office: +44 (0)20 7418 8900
Julian Gwillim Aprio Strategic Communications Public & Investor Relations SA Office: +27 (0)11 880 0037 Jeffrey Couch/Thomas Rider/Neil Elliot BMO Capital Markets Limited Joint Broker Office: +44 (0)20 7236 1010
Bobby Morse/Chris Judd Buchanan Public & Investor Relations UK Office: +44 (0)20 7466 5000 paf@buchanan.uk.comWebsite: www.panafricanresources.com
Date   Source Headline
12th Mar 20127:07 amPRNFurther Cautionary Announcement
22nd Feb 20128:00 amPRNStatement re Results Presentation by Pan African
22nd Feb 20127:00 amPRNInterim Results for the 6 months ended 31 December 2011
1st Feb 201211:12 amPRNApproval for Barberton Tailings Project
31st Jan 20127:48 amPRNPresentation re acqusition of Evander on website
30th Jan 20122:04 pmPRNStatement re acquisition of Evander Gold Mine
30th Jan 20122:01 pmPRNAcquisition of Evander Gold Mine
30th Jan 20128:06 amPRNJoint briefing by Pan African and Wits Gold
25th Jan 20127:00 amPRNTrading Statement
30th Dec 201112:40 pmRNSSecond Price Monitoring Extn
30th Dec 201112:35 pmRNSPrice Monitoring Extension
29th Dec 20117:00 amPRNRenewal of Cautionary Announcement
14th Dec 201112:30 pmPRNChanges to the Board of Directors
13th Dec 20111:00 pmPRNHolding(s) in Company
1st Dec 20119:00 amPRNTotal Voting Rights
29th Nov 20117:11 amPRNFirst production at Phoenix
24th Nov 20119:00 amPRNIssue of Equity
17th Nov 201112:00 pmPRNCautionary Announcement
2nd Nov 20113:56 pmPRNDealings by an Associate of an Non-Executive Director
1st Nov 20113:52 pmPRNResult of AGM
1st Nov 20112:46 pmPRNDealings by an Associate of a Non-executive Director
28th Oct 20117:00 amPRNIssue of Equity
17th Oct 20117:00 amPRNCold commissioning commences at Phoenix Platinum
28th Sep 20111:50 pmPRNCorrection to Annual Report and Dividend dates
28th Sep 20118:30 amRNSAnnual Report, AGM & Dividend notification
22nd Sep 20112:09 pmPRNHolding(s) in Company
22nd Sep 20111:48 pmPRNNominated Adviser Change of Registered Name
12th Sep 20117:00 amPRNFinal Results
19th Aug 20117:00 amPRNListing of Manica as a Separate Entity
15th Aug 20117:00 amPRNNotice of Results
27th Jul 20118:51 amPRNWage Negotiations Concluded
20th Jul 20111:00 pmPRNDirectorate Change
1st Jul 201112:32 pmPRNCorrection : Statement re Phoenix Platinum Project
1st Jul 201112:01 pmPRNStatement re Phoenix Platinum Project
22nd Jun 20117:00 amPRNResource Upgrade at Manica and Group Resource Upgrade
9th Jun 20118:00 amPRNResults of Drilling Programme at Bramber Tailings Dam
31st May 20119:20 amPRNStatement re Conference Presentation
31st May 20119:15 amPRNStatement re Barberton Mines Resource Upgrade
3rd May 20118:58 amPRNStatement re Revolving Credit Facility
4th Apr 20117:00 amPRNMozambique Govt Awards Mining Licence on Manica Project
23rd Mar 20117:00 amPRNPan African Commences Bulk Earthworks at Phoenix Plat
22nd Feb 20117:00 amPRNInterim results for the six months ended 31 Dec 2010
10th Feb 20117:00 amPRNStatement re Site Visit to Barberton Mines
3rd Feb 20112:00 pmPRNTrading Update
4th Jan 201112:00 pmPRNTotal Voting Rights
31st Dec 20108:00 amPRNHolding(s) in Company
16th Dec 20104:35 pmRNSPrice Monitoring Extension
15th Dec 20102:00 pmPRNHolding(s) in Company
14th Dec 20102:00 pmPRNHolding(s) in Company
8th Dec 20102:01 pmPRNHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.