Less Ads, More Data, More Tools Register for FREE

Pin to quick picksOracle Power Regulatory News (ORCP)

Share Price Information for Oracle Power (ORCP)

Share Price is delayed by 15 minutes
Get Live Data
0.0575    -0.0025 (-4.17%)
Bid:
0.055
Ask:
0.06
Spread: 0.005 (9.091%)
Market Cap: £9.04m
ORCP Live PriceLast checked at - London Stock Exchange

Intraday Oracle Power Share Chart

Grid Study for Renewable Power Plant

7 May 2024 07:00

RNS Number : 3505N
Oracle Power PLC
07 May 2024
 

7 May 2024

Oracle Power PLC

("Oracle" or the "Company")

 

Commencement of Transmission and Grid Interconnection Study for Renewable Power Plant

 

Oracle Power PLC (AIM: ORCP), an international project developer, together with its joint venture company, Oracle Energy Limited ("Oracle Energy"), a developer of green energy projects, is pleased to announce the commencement of the Grid Interconnection Study (the "Study") for its proposed 1.3GW renewable power plant in Jhimpir, Sindh Province, Pakistan (the "Power Plant"). Oracle Energy, in collaboration with its joint development partner, China Electric Power Equipment and Technology Co., Ltd. ("CET"), a subsidiary of State Grid Corporation of China ("State Grid China"), has engaged Power Planners International (Pvt.) Ltd ("PPI"), a distinguished company renowned for its expertise in power system analysis and planning, particularly in the domain of grid interconnection studies for renewable energy projects, to undertake the Study.

 

The Study, paid for by State Grid China, encompasses a comprehensive evaluation for 1.3GW of renewable power, including an 800MW solar project, a 500MW wind project, and a suitable battery energy storage system. The Power Plant aims to export the generated renewable power to the National Grid, with connection facilitated through the Network of National Transmission & Dispatch Company (NTDC). Power evacuation would be facilitated through the existing 220kV Jhimpir-II Grid station or any other grid interconnection scheme identified in collaboration with NTDC, factoring in the latest load forecast and NTDC's future transmission plans.

 

The Study is expected to culminate in the finalisation of the grid interconnection scheme, determining voltage levels, step-up transformer specifications, interconnecting distribution lines, and necessary extensions or reinforcements to the nearby system network. This comprehensive analysis reinforces Oracle's commitment to ensuring reliable power dispersal and maximizing the project's impact on the national energy grid.

 

 CEO of Oracle, Naheed Memon, commented"We are delighted to announce the initiation of the Interconnection Study for our renewable power plant in Jhimpir. This Study will complete our feasibility study package for the Power Plant and will be instrumental in propelling us into the FEED stage. Additionally, it will help to lay the groundwork for future confirmation of potential off-take and financing arrangements. Through strategic partnerships and meticulous planning, we aim to optimize the integration of renewable energy sources into the national grid, contributing to the country's energy security and environmental sustainability."

 

*ENDS*

 

For further information on Oracle Power PLC, visit the Company's website at http://www.oraclepower.co.uk or contact:

 

Oracle Power PLC

Naheed Memon - CEO +44 (0) 203 580 4314

 

Strand Hanson Limited (Nominated Adviser & Joint Broker)

Rory Murphy, Matthew Chandler, Rob Patrick +44 (0) 20 7409 3494

Global Investment Strategy UK Limited (Joint Broker)

Samantha Esqulant +44 (0) 20 7048 9432

 

St Brides Partners Limited (Financial PR)

Susie Geliher, Isabel de Salis +44 (0) 20 7236 1177

 

 

About PPI

Power Planners International (Pvt.) Ltd is a reputable entity, registered with the Pakistan Engineering Council and accredited with registrations in England and Wales, Saudi Electricity Company (SEC), and the Alternative Energy Development Board. PPI is a group of professionals who possess highly specialized skills, vast and profound experience, and expertise of the advanced and latest state of the art software prevailing in the contemporary power system industry. Having long background of power system analysis and planning in WAPDA and other electric utilities, they fully understand the scope of the required study and are capable of delivering it efficiently and promptly.

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
MSCQKABBDBKBQPK
Date   Source Headline
8th Jun 20177:00 amRNSMarket Update
24th May 20171:35 pmRNSNotice of Annual General Meeting
10th May 201711:21 amRNSResults for the Year Ended 31 December 2016
9th Jan 20177:00 amRNSChina Pakistan Economic Corridor
5th Jan 20171:00 pmRNSHolding(s) in Company
21st Dec 20169:38 amRNSChange in registered office address
4th Oct 20167:00 amRNSBoard Changes
15th Sep 20169:39 amRNSHoldings in Company
14th Sep 20167:00 amRNSUNAUDITED INTERIM RESULTS FOR 6 MONTHS TO 30 JUNE
17th Jun 20167:00 amRNSDetermination of Feasibility Stage Coal Price
7th Jun 20166:08 pmRNSHolding(s) in Company
3rd Jun 20163:34 pmRNSStatement regarding Share Price Movement
22nd Apr 20162:58 pmRNSAppointment of Interim Chairman
20th Apr 20166:08 pmRNSResult of AGM
24th Mar 20169:26 amRNSHoldings in Company
21st Mar 20167:00 amRNSExtension of IRR arrangement
18th Mar 20167:00 amRNSResults for the Year Ended 31 December 2015
5th Nov 20157:00 amRNSLetter of No Objection on 600 MW Power Plant
16th Oct 20154:40 pmRNSSecond Price Monitoring Extn
16th Oct 20154:35 pmRNSPrice Monitoring Extension
12th Oct 20157:00 amRNSSigning of Consortium Agreement
24th Sep 20157:00 amRNSUnaudited Interim Results
11th Aug 20151:11 pmRNSAdmission of Coal Price Petition
4th Jun 20157:00 amRNSHolding(s) in Company
4th Jun 20157:00 amRNSHolding(s) in Company
20th May 20152:49 pmRNSResult of AGM
14th Apr 20157:00 amRNSFinal Results
17th Mar 20157:00 amRNSEXTENSION TO SEPCO EPC FRAMEWORK AGREEMENT
11th Mar 20157:00 amRNSChina-Pakistan Economic Corridor
25th Feb 20156:27 pmRNSCorrection: Result of General Meeting
25th Feb 201511:27 amRNSResult of General Meeting
23rd Feb 20157:00 amRNSMINING LEASE RESTORATION
9th Feb 20157:00 amRNSEquity Placing and Operational Update
6th Jan 20157:00 amRNSProgress Towards Reinstatement of Mining Lease
23rd Dec 20149:03 amRNSDiscussions with SEPCO continue
22nd Dec 20147:00 amRNSAppointment of Joint Broker
11th Dec 20147:00 amRNSMining Lease
25th Sep 20147:00 amRNSEPC Framework Agreement with SEPCO
23rd Sep 20147:00 amRNSInterim Results
16th Sep 20147:00 amRNSEquity Placing
21st May 20144:29 pmRNSResult of AGM
16th Apr 20147:00 amRNSResults for the Year ended 31 December 2013
17th Jan 201412:43 pmRNSMilestone development of Block VI, Thar Project
21st Nov 20137:00 amRNSOracle signs MOU with Chinese power group SEPCO
25th Oct 20137:00 amRNSCash Box Placing
30th Sep 20131:36 pmRNSUnaudited Interim Results
24th Sep 20137:00 amRNSJoint Development Agreement Signed
19th Aug 20133:47 pmRNSAdjournment of General Meeting
30th Jul 20137:00 amRNSNotice of General Meeting
23rd May 20137:00 amRNSResult of AGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.