Grid Interconnection Study Completed

5 Nov 2024 07:00

RNS Number : 8797K
Oracle Power PLC
05 November 2024
Β 

5 November 2024

Oracle Power PLC

("Oracle" or the "Company")

Β 

Completion of Transmission & Grid Interconnection Study for Proposed Renewable Power Plant

Β 

Oracle Power PLC (AIM:ORCP), an international project developer, together with its joint venture company, Oracle Energy Limited ("Oracle Energy"), a developer of green energy projects, is pleased to announce completion of the Transmission & Grid Interconnection Study (the "Study") in respect of its proposed 1.3GW hybrid renewable energy power plant in Jhimpir, Sindh Province, Pakistan. Oracle Energy, in collaboration with its joint development partner, China Electric Power Equipment and Technology Co., Ltd. ("CET"), a subsidiary of State Grid Corporation of China ("State Grid China"), engaged Power Planners International (Pvt.) Ltd ("PPI"), to undertake the Study. PPI is a distinguished company renowned for its expertise in power system analysis and planning, particularly in the domain of grid interconnection studies for renewable energy projects.

Β 

The Study, entirely funded by State Grid China, assessed the technical feasibility of interconnecting the proposed 1.3GW Hybrid Renewable Energy Power Plant (the "Hybrid RE PP"), which consists of 800MW solar power, 500MW wind power generation and a suitable battery energy storage system, to provide renewable power to the National Grid. Based on the updated transmission plan and load forecast provided by the National Transmission and Dispatch Company ("NTDC"), the Study proposes interconnecting the plant to the 220kV Jhimpir-II Grid Station via a direct 220kV double circuit transmission line of 35km in length, using a quad bundle rail conductor. The Study outlines the generation voltage for the Hybrid RE PP, which will be increased to 33kV using transformers at each inverter and collector group. The net maximum output of the plant is expected to be 1,155MW. Additionally, a 260MW battery energy storage system (BESS) is proposed to enhance system reliability, and a static var compensator (SVC) will be installed to maintain the required power factor, thereby fulfilling NTDC Grid Code requirements.

Β 

Comprehensive load flow studies were performed for peak and off-peak conditions during both summer and winter periods, demonstrating the reliability of the proposed transmission scheme under normal and contingency (N-1) conditions. Short circuit and dynamic stability analyses confirmed that fault currents are within rated capacities, and the system successfully passed dynamic stability checks, ensuring resilience under fault conditions.

Β 

The completed Study has now been submitted to NTDC for review and approval by the Pakistan Government. This approval process will be critical in advancing the project towards implementation and the Company looks forward to providing further updates in due course.

Β 

Oracle's CEO, Naheed Memon, commented:Β "We are pleased to confirm the completion of this key Study for our proposed hybrid renewable energy power plant in Jhimpir. This milestone marks the culmination of extensive investigative studies and sets the stage for the next phase of detailed engineering design (FEED). The findings of the Study provide a solid foundation for securing potential off-take agreements for power. Our strategic focus remains on ultimately seamlessly integrating renewable energy into the National Grid, thereby enhancing energy security and promoting sustainable development in Pakistan."Β 

Β 

-ENDS-

Β 

For further information contact:

Β 

Oracle Power PLC

Naheed Memon - CEO

Β 

+44 (0) 20 7236 1177

Strand Hanson Limited (Nominated Adviser & Broker)

Rory Murphy, Matthew Chandler, Rob Patrick

Β 

+44 (0) 20 7409 3494

St Brides Partners Limited (Financial PR)

Isabel de Salis, Susie Geliher

oracle@stbridespartners.co.uk

Β 

Β 

About PPI

Power Planners International (Pvt.) Ltd is registered with the Pakistan Engineering Council and accredited with registrations in England and Wales, the Saudi Electricity Company (SEC), and the Alternative Energy Development Board. PPI comprises a group of professionals who possess highly specialised skills, vast and profound experience, and expertise in the advanced and latest state-of-the-art software prevailing in the contemporary power system industry. Having a long background in power system analysis and planning with WAPDA and other electric utilities, they were ideally placed to efficiently and promptly undertake the requisite Study.

Β 

Β 

Β 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
Β 
END
Β 
Β 
MSCFSMFWLELSESF
Date   Source Headline
8th Jun 20177:00 amRNSMarket Update
24th May 20171:35 pmRNSNotice of Annual General Meeting
10th May 201711:21 amRNSResults for the Year Ended 31 December 2016
9th Jan 20177:00 amRNSChina Pakistan Economic Corridor
5th Jan 20171:00 pmRNSHolding(s) in Company
21st Dec 20169:38 amRNSChange in registered office address
4th Oct 20167:00 amRNSBoard Changes
15th Sep 20169:39 amRNSHoldings in Company
14th Sep 20167:00 amRNSUNAUDITED INTERIM RESULTS FOR 6 MONTHS TO 30 JUNE
17th Jun 20167:00 amRNSDetermination of Feasibility Stage Coal Price
7th Jun 20166:08 pmRNSHolding(s) in Company
3rd Jun 20163:34 pmRNSStatement regarding Share Price Movement
22nd Apr 20162:58 pmRNSAppointment of Interim Chairman
20th Apr 20166:08 pmRNSResult of AGM
24th Mar 20169:26 amRNSHoldings in Company
21st Mar 20167:00 amRNSExtension of IRR arrangement
18th Mar 20167:00 amRNSResults for the Year Ended 31 December 2015
5th Nov 20157:00 amRNSLetter of No Objection on 600 MW Power Plant
16th Oct 20154:40 pmRNSSecond Price Monitoring Extn
16th Oct 20154:35 pmRNSPrice Monitoring Extension
12th Oct 20157:00 amRNSSigning of Consortium Agreement
24th Sep 20157:00 amRNSUnaudited Interim Results
11th Aug 20151:11 pmRNSAdmission of Coal Price Petition
4th Jun 20157:00 amRNSHolding(s) in Company
4th Jun 20157:00 amRNSHolding(s) in Company
20th May 20152:49 pmRNSResult of AGM
14th Apr 20157:00 amRNSFinal Results
17th Mar 20157:00 amRNSEXTENSION TO SEPCO EPC FRAMEWORK AGREEMENT
11th Mar 20157:00 amRNSChina-Pakistan Economic Corridor
25th Feb 20156:27 pmRNSCorrection: Result of General Meeting
25th Feb 201511:27 amRNSResult of General Meeting
23rd Feb 20157:00 amRNSMINING LEASE RESTORATION
9th Feb 20157:00 amRNSEquity Placing and Operational Update
6th Jan 20157:00 amRNSProgress Towards Reinstatement of Mining Lease
23rd Dec 20149:03 amRNSDiscussions with SEPCO continue
22nd Dec 20147:00 amRNSAppointment of Joint Broker
11th Dec 20147:00 amRNSMining Lease
25th Sep 20147:00 amRNSEPC Framework Agreement with SEPCO
23rd Sep 20147:00 amRNSInterim Results
16th Sep 20147:00 amRNSEquity Placing
21st May 20144:29 pmRNSResult of AGM
16th Apr 20147:00 amRNSResults for the Year ended 31 December 2013
17th Jan 201412:43 pmRNSMilestone development of Block VI, Thar Project
21st Nov 20137:00 amRNSOracle signs MOU with Chinese power group SEPCO
25th Oct 20137:00 amRNSCash Box Placing
30th Sep 20131:36 pmRNSUnaudited Interim Results
24th Sep 20137:00 amRNSJoint Development Agreement Signed
19th Aug 20133:47 pmRNSAdjournment of General Meeting
30th Jul 20137:00 amRNSNotice of General Meeting
23rd May 20137:00 amRNSResult of AGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.