Grid Interconnection Study Completed

5 Nov 2024 07:00

RNS Number : 8797K
Oracle Power PLC
05 November 2024
 

5 November 2024

Oracle Power PLC

("Oracle" or the "Company")

 

Completion of Transmission & Grid Interconnection Study for Proposed Renewable Power Plant

 

Oracle Power PLC (AIM:ORCP), an international project developer, together with its joint venture company, Oracle Energy Limited ("Oracle Energy"), a developer of green energy projects, is pleased to announce completion of the Transmission & Grid Interconnection Study (the "Study") in respect of its proposed 1.3GW hybrid renewable energy power plant in Jhimpir, Sindh Province, Pakistan. Oracle Energy, in collaboration with its joint development partner, China Electric Power Equipment and Technology Co., Ltd. ("CET"), a subsidiary of State Grid Corporation of China ("State Grid China"), engaged Power Planners International (Pvt.) Ltd ("PPI"), to undertake the Study. PPI is a distinguished company renowned for its expertise in power system analysis and planning, particularly in the domain of grid interconnection studies for renewable energy projects.

 

The Study, entirely funded by State Grid China, assessed the technical feasibility of interconnecting the proposed 1.3GW Hybrid Renewable Energy Power Plant (the "Hybrid RE PP"), which consists of 800MW solar power, 500MW wind power generation and a suitable battery energy storage system, to provide renewable power to the National Grid. Based on the updated transmission plan and load forecast provided by the National Transmission and Dispatch Company ("NTDC"), the Study proposes interconnecting the plant to the 220kV Jhimpir-II Grid Station via a direct 220kV double circuit transmission line of 35km in length, using a quad bundle rail conductor. The Study outlines the generation voltage for the Hybrid RE PP, which will be increased to 33kV using transformers at each inverter and collector group. The net maximum output of the plant is expected to be 1,155MW. Additionally, a 260MW battery energy storage system (BESS) is proposed to enhance system reliability, and a static var compensator (SVC) will be installed to maintain the required power factor, thereby fulfilling NTDC Grid Code requirements.

 

Comprehensive load flow studies were performed for peak and off-peak conditions during both summer and winter periods, demonstrating the reliability of the proposed transmission scheme under normal and contingency (N-1) conditions. Short circuit and dynamic stability analyses confirmed that fault currents are within rated capacities, and the system successfully passed dynamic stability checks, ensuring resilience under fault conditions.

 

The completed Study has now been submitted to NTDC for review and approval by the Pakistan Government. This approval process will be critical in advancing the project towards implementation and the Company looks forward to providing further updates in due course.

 

Oracle's CEO, Naheed Memon, commented"We are pleased to confirm the completion of this key Study for our proposed hybrid renewable energy power plant in Jhimpir. This milestone marks the culmination of extensive investigative studies and sets the stage for the next phase of detailed engineering design (FEED). The findings of the Study provide a solid foundation for securing potential off-take agreements for power. Our strategic focus remains on ultimately seamlessly integrating renewable energy into the National Grid, thereby enhancing energy security and promoting sustainable development in Pakistan." 

 

-ENDS-

 

For further information contact:

 

Oracle Power PLC

Naheed Memon - CEO

 

+44 (0) 20 7236 1177

Strand Hanson Limited (Nominated Adviser & Broker)

Rory Murphy, Matthew Chandler, Rob Patrick

 

+44 (0) 20 7409 3494

St Brides Partners Limited (Financial PR)

Isabel de Salis, Susie Geliher

oracle@stbridespartners.co.uk

 

 

About PPI

Power Planners International (Pvt.) Ltd is registered with the Pakistan Engineering Council and accredited with registrations in England and Wales, the Saudi Electricity Company (SEC), and the Alternative Energy Development Board. PPI comprises a group of professionals who possess highly specialised skills, vast and profound experience, and expertise in the advanced and latest state-of-the-art software prevailing in the contemporary power system industry. Having a long background in power system analysis and planning with WAPDA and other electric utilities, they were ideally placed to efficiently and promptly undertake the requisite Study.

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
MSCFSMFWLELSESF
Date   Source Headline
28th Apr 20267:00 amRNSNorthern Zone: Geotechnical Drilling for MDCP
22nd Apr 20267:00 amRNSPreliminary Heritage Report: Northern Zone
15th Apr 20267:00 amRNSAssay results of up to 71 g/t Au at Northern Zone
25th Feb 20267:00 amRNSNorthern Zone Update
17th Feb 20267:00 amRNSMining Lease Application Update
2nd Feb 20267:00 amRNSKalgoorlie Gold Project - Drilling Results
19th Jan 20267:00 amRNSPositive Results: Kalgoorlie Drilling Programme
23rd Dec 20257:00 amRNSKalgoorlie Gold - Native Title Agreements Signed
23rd Dec 20257:00 amRNSKalgoorlie Gold - Native Title Agreements Signed
10th Dec 20257:00 amRNSNew Shallow Gold Zone: Northern Zone Gold Project
26th Nov 20257:00 amRNSGold Results Expand the Footprint at Northern Zone
18th Nov 20257:00 amRNSNext Drill Programme at Northern Zone Gold Project
21st Oct 20257:00 amRNSDrilling Underway at Northern Zone Gold Project
6th Oct 20257:00 amRNSGrade Control Drill Rig Booked for Northern Zone
2nd Oct 20257:00 amRNSExercise of Warrants
30th Sep 20257:00 amRNSNorthern Zone Gold Project Co-Operation Agreement
26th Sep 20251:39 pmRNSCompany Update
12th Sep 20257:00 amRNSInterim Results for the 6 months to 30 June 2025
21st Aug 20257:00 amRNSPlans Confirmed at Blue Rocks Copper Project
14th Aug 20257:00 amRNSPlacing to Raise £500,000
28th Jul 20257:00 amRNS-RNaheed Memon Joins National Hydrogen Working Group
18th Jul 20251:30 pmRNSResult of AGM
11th Jul 20257:00 amRNSQ2 2025 Overview and Shareholder Q&A
4th Jul 20257:00 amRNSCu Target Identified over 2km - Blue Rocks Project
23rd Jun 20257:00 amRNSFinal Results
20th May 20257:00 amRNSMetallurgical Results Confirm +90% Gold Recovery
15th May 202512:55 pmRNSNorthern Zone Gold Project Update
23rd Apr 20257:00 amRNSFurther Assay Results from Northern Zone Project
22nd Apr 20257:00 amRNSPlacing to Raise £318,600
16th Apr 20257:00 amRNSMoU for Green Hydrogen Project Renewed
15th Apr 20257:00 amRNSBlue Rock Geochemical Sampling Programme Completed
11th Apr 20257:00 amRNSNorthern Zone Gold Project Update
3rd Apr 20257:00 amRNSAssay Results from the Northern Zone Gold Project
31st Mar 20257:00 amRNSBlue Rocks Copper Project Update
20th Mar 20257:00 amRNSExtension Granted for LOI Validity Period
19th Mar 20257:00 amRNSAssay Results from Northern Zone Gold Project
27th Feb 202511:23 amRNS-RNorthern Zone Gold Project Update
18th Feb 20257:00 amRNSRiversgold Exercises 80% Option over Northern Zone
13th Feb 20257:00 amRNS2025 Drilling Campaign to Commence - Northern Zone
11th Feb 20257:00 amRNSNorthern Zone Gold Project Mining Lease Update
14th Jan 20257:00 amRNSQ4 2024 Overview and Shareholder Q&A
20th Dec 20247:00 amRNSAPEX Geoscience to Explore Blue Rocks Project
12th Dec 20242:47 pmRNSRepricing & Exercise of Warrants to Raise £416,667
10th Dec 20247:00 amRNSNorthern Zone Mining Lease Application Submitted
4th Dec 20247:00 amRNSNorthern Zone Gold Modelling and Project Update
3rd Dec 20243:20 pmRNSHolding(s) in Company
29th Nov 202410:35 amRNSHolding(s) in Company
28th Nov 20247:00 amRNSHolding(s) in Company
26th Nov 20247:00 amRNSNorthern Zone Project Drill Results
22nd Nov 20242:00 pmRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.