This statement provides an update on the performance of the Company for the period ending 30th June 2008, together with an update on the Company's key near term objectives.

 

 

Operating Review:

19.4 MW Gas-fired Plant at Mayavaram, Tamil Nadu

The 19.4 MW facility in Mayavaram ("OPGE") (in which the Company has a 44% economic interest) is in its fifth year of successful operation. Its unaudited headline trading figures for the quarters January to March and April to June 2008 are: 

 

Apr-Jun 2008

Jan-Mar 2008

Year to March 2008

Sales

US $3.18 Million

US $3.25 Million

US $12.06 Million

Pre tax profits

US $1.75 Million

US $1.55 Million

US $ 6.75 Million

Plants in Development:

10 MW Waste Heat Recovery Plant near Chennai

The Board is pleased to announce that commissioning trials have finished and grid connectivity is in place. Sales at this 10 MW waste-heat recovery facility at Chennai are expected to commence in August 2008 with optimum load factor and capacity anticipated shortly thereafter. 

77 MW Coal-fired Plant near Chennai

The construction of the 77 MW coal fired facility in Chennai has been further progressed. The component parts are being received on schedule and civil works are ongoing. The Directors expect that the plant will commence production in the first quarter of 2009, as planned.

2 x 135 MW Coal-fired Plant in Kutch, Gujarat 

As announced on 12 August 2008 the entire debt financing required for the 2 x 135 MW coal fired facility at Kutch in Gujarat has received credit approval. Documentation is now being progressed and is expected to be completed in September. 

Market Developments:

As previously announced the Company has entered into a coal purchase agreement with Knowledge Infrastructure for the supply of coal from Indonesia but is aware of the need to retain flexibility in terms of fuel source. Accordingly the Company had ensured all the plants were designed so as to be able to burn any combination of Indonesian or Indian coal. The Directors previously applied to the Ministry of Coal, Government of India for an allocation of Indian coal to supply the OPGPG 77MW plant which they are pleased to announce has now been approved. This provides the Company with an alternate and stable supply of coal which is able to satisfy the entire fuel requirements of the plant.

The Directors are currently in negotiations regarding a similar linkage for the OPGG 2x135MW plant. 

Demand for power continues to increase in India and, in particular, in Tamil Nadu and Gujarat, where the Company is building power plants. The Company's power plants are required to sell a minimum of 51% of the power to captive customers and the balance can be sold to power trading companies. It is noteworthy that power trading companies have recently increased the prices at which they are willing to purchase power and are now paying significantly higher prices than the Utility tariffs of approximately 11 c per kWh. 

The Directors are pleased with progress made since flotation and believe that the Company is well positioned to deliver significant shareholder value. 

The Company's next financial release will be in respect of the interim results for the period ending 30 September 2008.

 

OPG Power Ventures plc
 
Arvind Gupta, Managing Director
+91 98400 96299
V. Narayan Swami, Finance Director
+91 99400 17927
Martin Gatto, Senior Non Executive Director
+44 77 78 74 92 23
 
 
Cenkos Securities
+44 20 7397 8900
Stephen Keys
 
Camilla Hume
 
 
 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
TSTEBLFLVVBBBBD
Date   Source Headline
2nd Jul 20127:00 amRNSFinal Results
7th Jun 20127:00 amRNSProjects Update
10th May 20129:36 amRNSHolding(s) in Company
3rd Apr 20127:00 amRNSTamil Nadu tariff order
24th Feb 201210:37 amRNSTrading Update
12th Jan 20129:52 amRNSDirector/PDMR Shareholding
21st Dec 20114:51 pmRNSDirector/PDMR Shareholding
14th Dec 20117:00 amRNSHalf Yearly Report
14th Oct 20117:00 amRNSTNEB power sales tariff
28th Sep 20118:50 amRNSResult of AGM
22nd Sep 20119:48 amRNSCommencement of Works at Gujarat
5th Sep 20119:52 amRNSAnnual Financial Report
15th Aug 20117:00 amRNSFinal Results
20th Jul 20117:00 amRNSTrading Statement & Results Date-Replacement
19th Jul 20113:24 pmRNSTrading Statement & Results Date
5th Apr 20119:25 amRNSHolding(s) in Company
28th Feb 20113:12 pmRNSEGM Statement
7th Feb 20117:00 amRNSPlacing of up to 64,515,000 new Ordinary Shares
4th Feb 20116:27 pmRNSPlacing of up to 64,515,000 new Ordinary Shares
25th Jan 20114:41 pmRNSAquisition of land and expansion of plant
17th Jan 201112:30 pmRNSMoU with Government of Gujarat 5,400 MW capacity
14th Dec 20107:00 amRNSHalf Yearly Report
9th Dec 20109:43 amRNSHolding(s) in Company
29th Oct 20107:00 amRNSTrading Statement
30th Sep 20104:50 pmRNSAGM Statement
13th Sep 20107:00 amRNSNotice of AGM
3rd Sep 20107:00 amRNSSale of Power from 77 MW Plant to TNEB
10th Aug 20104:40 pmRNSSecond Price Monitoring Extn
10th Aug 20104:35 pmRNSPrice Monitoring Extension
12th Jul 201011:14 amRNS300 MW Project at Kutch in Gujarat
12th Jul 201010:50 amRNSSecond 77 MW Unit at Chennai
5th Jul 20102:00 pmRNSFinal Results
30th Jun 20107:00 amRNSReceipt of Environmental Approvals
29th Jun 201012:00 pmRNSNotice of Results
4th May 20107:00 amRNSCommissioning of the 77 MW Power Station
3rd Mar 20107:00 amRNSCommissioning Update
9th Feb 20107:00 amRNSTrading Statement
7th Dec 20099:41 amRNSReplacement: Half Yearly Report
7th Dec 20097:00 amRNSHalf Yearly Report
6th Aug 20097:00 amRNSTrading Statement
16th Jul 200912:30 pmRNSGrant of Options
16th Jul 200912:30 pmRNSAGM Statement
10th Jul 20098:00 amRNSCommissioning trials
30th Jun 20092:23 pmRNSAnnual Financial Report
23rd Jun 20097:00 amRNSAppointed O&M Contractor
22nd Jun 20097:00 amRNSFinal Results
30th Apr 20097:00 amRNSTrading Update
19th Mar 200911:14 amRNSChange of Registered Office
5th Feb 20097:00 amRNSPower supply contracts at higher rates
10th Dec 20087:00 amRNSInterim Results

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.