Trading Statement

29 May 2013 07:00

RNS Number : 7390F
OPG Power Ventures plc
29 May 2013
 



29 May2013

 

OPG Power Ventures plc

("OPG" or the "Company")

 

Trading update for the three months and for the year ended 31 March 2013

 

OPG, the developer and operator of power stations in India, presents the following trading update for the three months and for the year ended 31 March 2013.

 

Operational Highlights

·; Q4 FY13 generation of 338 million units up 99% (Q4 FY12:170 million units);

·; FY13generation of 932 million units up 44% (FY12: 648 million units); and

·; Both plants performed ahead of management expectations with over 90% PLF for the year as a whole and exceeding 100% in Q4 FY13.

 

Project Highlights

·; 80 MW Chennai III construction complete and final trials underway ; commissioning expected in June 2013;

·; 160 MW Chennai IV c. 50% of civil works foundation completed;boiler and chimney construction c.10% complete; project on track for commissioning in H2calendar year 2014;and

·; 300 MW Gujarat c. 80% civil works and foundation completed and boiler and chimney construction significantly advanced; project on schedule for commissioning in H2 calendar year 2014.

 

Financial Highlights

·; Average tariff realized up 13% to Rs5.58/kWh (FY12: Rs4.93/kWh);

·; Q4 FY13 estimated revenue £20m up 90% (Q4 FY12: £10.76m);

·; FY13 estimated revenue £56m up 46% (FY12: £38.48m); and

·; Underlying estimated Indian rupee revenue Rs 4,823m up 63% (FY12: Rs2.951m) despite 25 day shutdown.

 

Particulars

Q4 FY13

Q4 FY12

% Change

FY13

FY12

% Change

Generation (million units)

Chennai I

169

170

-1%

617*

648

-5%

Chennai II

169

NA

315

NA

Total

338

170

+99%

932

648

+44%

PLF (%)

Chennai I

102

101

92

96

Chennai II

102

NA

99

NA

Average PLF

102

101

96

Tariff (Rs/kWh)

5.59

5.23

+7%

5.58

4.93

+13%

Estimated Revenue (£m)

20

10.76

+90%

56

38.48

46%

Estimated Revenue (Rsm)

1,754

825

+113%

4,823

2,951

+63%

* 25 day shutdown taken in June 2013 for planned maintenance and connection of Chennai II to common facilities.

 

Projects

In an effort to assist OPG's shareholders in distilling the most important stages of the life cycle of a project during its development, for the first time, the Company has provided below a, quantified assessment of the progress of its current and most significant projects. This is based purely on management's experience and not verified by any third party and is presented by reference to each of four key stages in a typical project in development and estimates the risk of a non-performing project at each stage.

 

Project stage

Financing

Civil Works and Foundations

Chimney and Boiler related construction

Testing and Commissioning

Chennai III

100%

100%

100%

80%

Chennai IV

100%

50%

10%

-

Gujarat

100%

80%

40%

-

 

Results announcement date

Results for the year ended 31 March 2013 will be announced during the third week of June 2013.

 

 

About OPG

OPG is operating and developing power projects in India under the group captive model with 190 MW in operations and a further 552 MW under development. In the six months ended 30 September 2012, the Group's revenues were £17.8m and profit before tax was £2.5m.

 

 

For further information, please visit www.opgpower.com or contact:

 

OPG Power Ventures PLC

+91 (0) 44 429 11 211

Arvind Gupta

 

V Narayan Swami

Ajay Paliwal

 

 

 

Cenkos Securities (Nominated Adviser & Broker)

 

Stephen Keys / Camilla Hume

+44 (0) 20 7397 8900

 

 

Tavistock Communications

 

Simon Hudson/Kelsey Traynor

+44 (0) 20 7920 3150

 

-ends-

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
TSTVVLFLXEFEBBV
Date   Source Headline
2nd Jul 20127:00 amRNSFinal Results
7th Jun 20127:00 amRNSProjects Update
10th May 20129:36 amRNSHolding(s) in Company
3rd Apr 20127:00 amRNSTamil Nadu tariff order
24th Feb 201210:37 amRNSTrading Update
12th Jan 20129:52 amRNSDirector/PDMR Shareholding
21st Dec 20114:51 pmRNSDirector/PDMR Shareholding
14th Dec 20117:00 amRNSHalf Yearly Report
14th Oct 20117:00 amRNSTNEB power sales tariff
28th Sep 20118:50 amRNSResult of AGM
22nd Sep 20119:48 amRNSCommencement of Works at Gujarat
5th Sep 20119:52 amRNSAnnual Financial Report
15th Aug 20117:00 amRNSFinal Results
20th Jul 20117:00 amRNSTrading Statement & Results Date-Replacement
19th Jul 20113:24 pmRNSTrading Statement & Results Date
5th Apr 20119:25 amRNSHolding(s) in Company
28th Feb 20113:12 pmRNSEGM Statement
7th Feb 20117:00 amRNSPlacing of up to 64,515,000 new Ordinary Shares
4th Feb 20116:27 pmRNSPlacing of up to 64,515,000 new Ordinary Shares
25th Jan 20114:41 pmRNSAquisition of land and expansion of plant
17th Jan 201112:30 pmRNSMoU with Government of Gujarat 5,400 MW capacity
14th Dec 20107:00 amRNSHalf Yearly Report
9th Dec 20109:43 amRNSHolding(s) in Company
29th Oct 20107:00 amRNSTrading Statement
30th Sep 20104:50 pmRNSAGM Statement
13th Sep 20107:00 amRNSNotice of AGM
3rd Sep 20107:00 amRNSSale of Power from 77 MW Plant to TNEB
10th Aug 20104:40 pmRNSSecond Price Monitoring Extn
10th Aug 20104:35 pmRNSPrice Monitoring Extension
12th Jul 201011:14 amRNS300 MW Project at Kutch in Gujarat
12th Jul 201010:50 amRNSSecond 77 MW Unit at Chennai
5th Jul 20102:00 pmRNSFinal Results
30th Jun 20107:00 amRNSReceipt of Environmental Approvals
29th Jun 201012:00 pmRNSNotice of Results
4th May 20107:00 amRNSCommissioning of the 77 MW Power Station
3rd Mar 20107:00 amRNSCommissioning Update
9th Feb 20107:00 amRNSTrading Statement
7th Dec 20099:41 amRNSReplacement: Half Yearly Report
7th Dec 20097:00 amRNSHalf Yearly Report
6th Aug 20097:00 amRNSTrading Statement
16th Jul 200912:30 pmRNSGrant of Options
16th Jul 200912:30 pmRNSAGM Statement
10th Jul 20098:00 amRNSCommissioning trials
30th Jun 20092:23 pmRNSAnnual Financial Report
23rd Jun 20097:00 amRNSAppointed O&M Contractor
22nd Jun 20097:00 amRNSFinal Results
30th Apr 20097:00 amRNSTrading Update
19th Mar 200911:14 amRNSChange of Registered Office
5th Feb 20097:00 amRNSPower supply contracts at higher rates
10th Dec 20087:00 amRNSInterim Results

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.