Cambay Drilling Update

28 Oct 2013 07:00

RNS Number : 4848R
Oilex Ltd
27 October 2013
 



 

28 October 2013

 

 

Cambay Drilling Update

 

· Critical casing ordered and delivery scheduled for early December

· Casing fulfils a recommendation of the Independent Engineering Report

· Bid evaluations for rig and fracture stimulation equipment nearing completion

 

Oilex Ltd (ASX: OEX, AIM: OEX, Oilex) is pleased to provide an update on the preparations for drilling Cambay-77H in its Cambay Tight Hydrocarbon Project. As indicated previously, the full suite of tender packages for all equipment, materials and services required for Cambay-77H have been issued and all the bid documents have been received from prospective bidders. Joint Venture representatives have completed technical evaluation of the following critical items:

 

· 4 ½ inch completion tubulars

· Drill Rig and Associated Services

Of these critical items, the commercial evaluation is now complete and approved by the Joint Venture for the 4 ½ inch completion tubulars. This critical item has been ordered with an expected delivery to the site during December 2013. Availability of these tubulars is crucial for compliance with the recommendations of the independent engineering review of Cambay-76H, announced during October 2012.

The quotations to supply the rig and associated services are currently being reviewed within the Joint Venture and the commercial evaluation will begin immediately follow endorsement by the technical team. Multiple bids have been received and based upon the technical submissions a number of rigs appear to be suitable for Cambay-77H. The evaluation of bids for the Fracture Services is progressing in parallel with the Drill Rig.

 

In relation to endorsement of the Gas Sales Agreement signed and announced in April 2013, the Government has recently informed the Joint Venture that a formal competitive tendering process is now required to demonstrate an arm's length price structure before endorsement of the GSA is granted. Competitive bids are due in late November 2013.

 

Managing Director of Oilex, Ron Miller, said

"We are confident that the tendering process is progressing and the selection of contractors, suppliers and vendors is being completed in a methodical fashion to mitigate risks as per the recommendation of the independent engineering report.

The focus is now on completion of the recommendation for the drilling rig and fracture stimulation equipment selection and we look forward to updating the market accordingly."

 

For further information, please contact:

Oilex Ltd

Ron Miller, Managing Director

Email: oilex@oilex.com.au

Tel: +61 8 9485 3200

Australia

RFC Ambrian Limited

Nominated Adviser and AIM Broker

Samantha Harrison

Email: samatha.harrison@rfcambrian.com

Tel: +44 203 440 6800

UK

 

Tavistock Communications

Conrad Harrington

Email: charrington@tavistock.co.uk

Tel: +44 207 920 3150

UK

 

Competent Person's Statement

Information in this report relating to hydrocarbon reserves or resources has been reviewed and checked by Mr Peter Bekkers B.Sc. (Hons), the Chief Geoscientist of Oilex Ltd who has over 15 years of experience in petroleum geology and is a member of the Society of Petroleum Engineers and AAPG. Mr Bekkers consents to the inclusion of the information in this report relating to hydrocarbon reserves and resources in the form and context in which it appears. Resource estimates contained in this report are in accordance with the standard definitions set out by the Society of Petroleum Engineers, Petroleum Resources Management System, 2007.

This document may include forward-looking statements. Forward-looking statements include, but are not necessarily limited to, statements concerning Oilex Ltd.'s planned exploration program and other statements that are not historic facts. When used in this document, the words such as "could", "plan", "estimate" "expect", "intend", "may", "potential", "should" and similar expressions are forward-looking statements. Although Oilex Ltd believes that its expectations reflected in these are reasonable, such statements involve risks and uncertainties, and no assurance can be given that actual results will be consistent with these forward-looking statements.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUBSUROVARUUA
Date   Source Headline
7th Aug 20209:32 amRNSTermination of JPDA Arbitration Proceedings
31st Jul 202011:07 amRNSJune 2020 Quarterly Report
31st Jul 202010:45 amRNSLoan Restructure and Equity Issue
30th Jul 20209:00 amRNSManaging Director Contract Extension
27th Jul 20207:00 amRNSWest Kampar Update
17th Jul 20207:07 amRNSIssue of Securities
30th Jun 202010:40 amRNSSuccessful Bid for Cooper Basin Permit
30th Jun 20208:17 amRNSResults of General Meeting
30th Jun 20208:11 amRNSExecutive Director Contract Extension
30th Jun 20208:05 amRNSChange of Registered Office
29th Jun 20207:00 amRNSIndia Update
15th Jun 202010:28 amRNSChange to Notice of Meeting
15th Jun 20207:56 amRNSArmour Share Purchase Agreement
5th Jun 202011:52 amRNSExtension to Armour Agreement
3rd Jun 20201:14 pmRNSNotice of Change of Interest of Substantial Holder
1st Jun 20207:15 amRNSExtension to Armour Agreement
29th May 20207:00 amRNSNotice of General Meeting
27th May 20209:28 amRNSSale of Cooper Eromanga Basin Assets
26th May 20207:00 amRNSNotice of Change of Interest of Substantial Holder
15th May 20207:00 amRNSIssue of Securities
6th May 20207:00 amRNSAppendix 3Z B Lingo
6th May 20207:00 amRNSReplacement Appendix 5B
5th May 20208:36 amRNSBoard Changes
30th Apr 20209:16 amRNSMarch 2020 Quarterly Report
28th Apr 20204:41 pmRNSSecond Price Monitoring Extn
28th Apr 20204:35 pmRNSPrice Monitoring Extension
28th Apr 202011:02 amRNSCooper Basin Update
27th Apr 20207:14 amRNSCorrection: Variation to Financing Terms
23rd Apr 20201:45 pmRNSVariation to Financing Terms
3rd Apr 20207:00 amRNSExtension for Acquisition of Cooper Licences
3rd Apr 20207:00 amRNSChairman Consulting Contract Extension
26th Mar 20207:32 amRNSAppendix 3X Mark Bolton
26th Mar 20207:00 amRNSBoard and Executive Changes
24th Mar 20207:30 amRNSDoriemus Transaction - Update
16th Mar 20207:15 amRNSInterim Report 31 December 2019
16th Mar 20207:00 amRNSBusiness and Financial Restructure
12th Mar 20207:00 amRNSDoriemus Shareholders Approve Transaction
6th Mar 20207:15 amRNSOpportunity to Participate in Doriemus Offer
3rd Mar 202012:24 pmRNSUpdate on Cambay Sale Process
28th Feb 20209:29 amRNSExtension for Acquisition of Cooper Basin Licences
21st Feb 20207:30 amRNSStrong Funding Support for Cooper-Eromanga
11th Feb 20207:00 amRNSChairman Consulting Contract Extension
4th Feb 20207:00 amRNSAppendix 3B: Issue of Securities
3rd Feb 20202:23 pmRNSNew Series C Loan Facility
31st Jan 20208:17 amRNSDecember 2019 Quarterly Report
30th Jan 20207:00 amRNSDOR - Prop Acqn of Major Cooper-Eromanga Portfolio
29th Jan 202010:39 amRNSSale of Cooper Eromanga Basin Assets
28th Jan 20207:00 amRNSSale of Participating Interest in Bhandut
17th Jan 20202:05 pmRNSUpdate on Cambay Sale Process
7th Jan 20207:34 amRNSNotice of Change of Interest of Substantial Holder

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.