Project Update

26 Nov 2018 07:00

RNS Number : 4103I
Ncondezi Energy Limited
26 November 2018
 

 

News Release 

 

 

Project Update

 

26 November 2018: Ncondezi Energy Limited ("Ncondezi" or the "Company") (AIM: NCCL) provides an update on its process to conclude a binding Joint Development Agreement ("JDA") for the Company's integrated 300MW power and coal mine project in Tete Mozambique (the "Project").

 

The Company has finalised the work program and timetable for the Project with its potential strategic partners and submitted it to the Liaison Committee which includes representatives from the Ministry of Mineral Resources and Energy ("MIREME") and Mozambican state power utility Electricity de Mozambique ("EDM"). The work program and timetable includes the following key milestones and target dates:

 

• JDA - Q1 2019

 

• Binding engineering, procurement, and construction ("EPC") and operations and maintenance ("O&M") contracts - Q1 2019

 

• Signing of key commercial agreements: Power Purchase Agreement and Power Concession Agreement - Q1 2020

 

• Financial Close - H1 2020

 

• Commercial Operations Date - H1 2023

 

The timetable has been designed to fit with EDM's generation plan which includes coal fired power to be produced in the Tete region by 2023. The generation plan is based on EDM's 10 year strategy, published earlier in 2018, and is in line with the Mozambican Government's Electricity Master Plan 2018-2043 which was approved on 16 October 2018. The Mozambican Government is targeting universal access to electricity by 2030 and this includes up to 1,350MW of potential coal fired power generation.

 

The proposed work program and timetable targets approval being received from all Liaison Committee members before year end, however the timing will be dependent on feedback from the Liaison Committee and the review and agreement process. The Company is treating this process as a main priority and expects to start the JDA, EPC and O&M processes once agreement is made.

 

Non-Executive Chairman, Michael Haworth, commented: "Today's announcement represents another important step in the Company's pathway to success, with alignment on key Project milestones and delivery between Ncondezi and its potential strategic partners being shared with the Liaison Committee for discussion and approval. The Liaison Committee is the Government sanctioned committee tasked with implementing the Project, and the updated work program and timetable is the final part of a process which targets having all relevant parties responsible for the Project's delivery in agreement on the way forward. Once agreed, the Company and its potential strategic partners can focus on the delivery of key milestones, such as the JDA. The Project is one of the most advanced power development projects in the region, and is located in an area where the effects of drought have reduced generation capacity from traditional hydroelectric power sources by up to 25%. The Company believes it is well positioned to bring meaningful benefits to Mozambique and meet its growing power needs, with a clear pathway to delivery in 2023, a competitive power tariff and world leading potential development partners. Further updates will be made to shareholders post the meetings with the Liaison Committee."

 

 

 

Enquiries

For further information please visit www.ncondezienergy.com or contact:

 

Ncondezi Energy:

Hanno Pengilly

+27 (0) 71 362 3566

 

Liberum Capital Limited:NOMAD & Joint Broker

 

Christopher Britton / Richard Crawley

+44 (0) 20 3100 2000

Novum Securities Limited:

Joint Broker

Colin Rowbury

+44 (0) 20 7399 9427

 

 

Note:

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulation ("MAR"). Upon the publication of this announcement via Regulatory Information Service ("RIS"), this inside information is now considered to be in the public domain. If you have any queries on this, then please contact Hanno Pengilly, Chief Development Officer of the Company (responsible for arranging release of this announcement) on +27 (0) 71 362 3566.

 

 

Ncondezi owns 100% of the Ncondezi Project which is strategically located in the power generating hub of the country, the Tete Province in northern Mozambique. The Company is developing an integrated thermal coal mine and power plant in phases of 300MW up to 1,800MW. The first 300MW phase is targeting domestic consumption in Mozambique using reinforced existing transmission capacity to meet current demand.

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDFELLLVFFLFBL
Date   Source Headline
13th Sep 20127:00 amRNSPositive DFS Results for Power Plant Project
12th Sep 20124:56 pmRNSHolding(s) in Company
6th Sep 201211:39 amRNSHolding(s) in Company
4th Sep 20127:00 amRNSInterim Results
20th Aug 20127:00 amRNSOperational Update
14th Aug 20124:23 pmRNSHolding(s) in Company
1st Aug 20127:00 amRNSAppointment of Joint Broker
27th Jul 20123:41 pmRNSResult of AGM
17th Jul 20122:54 pmRNSPress Speculation
29th Jun 20122:35 pmRNSHolding(s) in Company
21st Jun 201212:48 pmRNSCorrection: Directors Dealings
21st Jun 20127:00 amRNSDirectors Dealings
18th Jun 20127:00 amRNSProject Update
31st May 20124:37 pmRNSDirector/PDMR Shareholding
22nd May 20127:00 amRNSManagement Restructure
18th May 20127:00 amRNSFramework Agreement Signed
14th May 20127:00 amRNSChange of Adviser
26th Apr 20127:00 amRNSNcondezi Initiates Strategic Partner Search
23rd Apr 20127:00 amRNSFinal results for the year ended 31 December 2011
20th Mar 20127:53 amRNSNcondezi Project Coal Resource Upgrade
18th Jan 20127:00 amRNSNcondezi Infrastructure Agreement
21st Dec 20117:00 amRNSNcondezi Project South Block Resource Update
7th Dec 20117:00 amRNSAppointment of Joint Broker
6th Dec 20117:00 amRNSResult of Power Generation Studies
21st Nov 20117:00 amRNSCompany Update to Shareholders
30th Sep 20117:00 amRNSInterim Results
26th Jul 20112:45 pmRNSHolding(s) in Company
30th Jun 20112:15 pmRNSNotice of AGM
24th Jun 20117:00 amRNSFinal Results for the year ended 31 December 2010
10th Jun 20114:51 pmRNSReplacement Issue of Shares and Total Voting Right
10th Jun 20114:30 pmRNSIssue of Shares and Total Voting Rights
9th Jun 20117:00 amRNSIssue of shares and Total Voting Rights
27th May 20117:00 amRNSINITIAL COAL QUALITY RESULTS AND OPS UPDATE
3rd Mar 20117:00 amRNSDFS WORK PROGRAMME UPDATE
28th Jan 20117:00 amRNSSettlement of Placing Shares
20th Jan 201110:30 amRNSBuy-back of Shares
13th Jan 20113:15 pmRNSResult of Placing
13th Jan 20117:00 amRNSProposed cash placing
17th Dec 201010:48 amRNSAllotment of Shares
16th Dec 20102:50 pmRNSHolding(s) in Company
15th Dec 20107:00 amRNSNCONDEZI COMPLETES 2010 DRILL PROGRAMME
28th Sep 20103:45 pmRNSInterim Results
23rd Sep 20107:00 amRNSNcondezi commences core drilling
1st Sep 20107:00 amRNSCommencement of DFS Work Programme
15th Jul 201010:18 amRNSChange of Address, Agent and Company Secretary
11th Jun 201011:03 amRNSHolding(s) in Company
10th Jun 20107:00 amRNSAdmission to Trading on AIM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.