Project Update

26 Nov 2018 07:00

RNS Number : 4103I
Ncondezi Energy Limited
26 November 2018
Β 

Β 

News ReleaseΒ 

Β 

Β 

Project Update

Β 

26 November 2018: Ncondezi Energy Limited ("Ncondezi" or the "Company") (AIM: NCCL) provides an update on its process to conclude a binding Joint Development Agreement ("JDA") for the Company's integrated 300MW power and coal mine project in Tete Mozambique (the "Project").

Β 

The Company has finalised the work program and timetable for the Project with its potential strategic partners and submitted it to the Liaison Committee which includes representatives from the Ministry of Mineral Resources and Energy ("MIREME") and Mozambican state power utility Electricity de Mozambique ("EDM"). The work program and timetable includes the following key milestones and target dates:

Β 

β€’ JDA - Q1 2019

Β 

β€’ Binding engineering, procurement, and construction ("EPC") and operations and maintenance ("O&M") contracts - Q1 2019

Β 

β€’ Signing of key commercial agreements: Power Purchase Agreement and Power Concession Agreement - Q1 2020

Β 

β€’ Financial Close - H1 2020

Β 

β€’ Commercial Operations Date - H1 2023

Β 

The timetable has been designed to fit with EDM's generation plan which includes coal fired power to be produced in the Tete region by 2023. The generation plan is based on EDM's 10 year strategy, published earlier in 2018, and is in line with the Mozambican Government's Electricity Master Plan 2018-2043 which was approved on 16 October 2018. The Mozambican Government is targeting universal access to electricity by 2030 and this includes up to 1,350MW of potential coal fired power generation.

Β 

The proposed work program and timetable targets approval being received from all Liaison Committee members before year end, however the timing will be dependent on feedback from the Liaison Committee and the review and agreement process. The Company is treating this process as a main priority and expects to start the JDA, EPC and O&M processes once agreement is made.

Β 

Non-Executive Chairman, Michael Haworth, commented: "Today's announcement represents another important step in the Company's pathway to success, with alignment on key Project milestones and delivery between Ncondezi and its potential strategic partners being shared with the Liaison Committee for discussion and approval. The Liaison Committee is the Government sanctioned committee tasked with implementing the Project, and the updated work program and timetable is the final part of a process which targets having all relevant parties responsible for the Project's delivery in agreement on the way forward. Once agreed, the Company and its potential strategic partners can focus on the delivery of key milestones, such as the JDA. The Project is one of the most advanced power development projects in the region, and is located in an area where the effects of drought have reduced generation capacity from traditional hydroelectric power sources by up to 25%. The Company believes it is well positioned to bring meaningful benefits to Mozambique and meet its growing power needs, with a clear pathway to delivery in 2023, a competitive power tariff and world leading potential development partners. Further updates will be made to shareholders post the meetings with the Liaison Committee."

Β 

Β 

Β 

Enquiries

For further information please visit www.ncondezienergy.com or contact:

Β 

Ncondezi Energy:

Hanno Pengilly

+27 (0) 71 362 3566

Β 

Liberum Capital Limited:NOMAD & Joint Broker

Β 

Christopher Britton / Richard Crawley

+44 (0) 20 3100 2000

Novum Securities Limited:

Joint Broker

Colin Rowbury

+44 (0) 20 7399 9427

Β 

Β 

Note:

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulation ("MAR"). Upon the publication of this announcement via Regulatory Information Service ("RIS"), this inside information is now considered to be in the public domain. If you have any queries on this, then please contact Hanno Pengilly, Chief Development Officer of the Company (responsible for arranging release of this announcement) on +27 (0) 71 362 3566.

Β 

Β 

Ncondezi owns 100% of the Ncondezi Project which is strategically located in the power generating hub of the country, the Tete Province in northern Mozambique. The Company is developing an integrated thermal coal mine and power plant in phases of 300MW up to 1,800MW. The first 300MW phase is targeting domestic consumption in Mozambique using reinforced existing transmission capacity to meet current demand.

Β 

Β 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
Β 
END
Β 
Β 
UPDFELLLVFFLFBL
Date   Source Headline
19th Jan 20224:36 pmRNSPrice Monitoring Extension
18th Jan 20224:41 pmRNSSecond Price Monitoring Extn
18th Jan 20224:36 pmRNSPrice Monitoring Extension
17th Jan 20222:06 pmRNSSecond Price Monitoring Extn
17th Jan 20222:01 pmRNSPrice Monitoring Extension
17th Jan 20227:00 amRNSProject Update
29th Dec 20217:00 amRNSHolding(s) in Company
22nd Dec 202111:06 amRNSSecond Price Monitoring Extn
22nd Dec 202111:00 amRNSPrice Monitoring Extension
20th Dec 202111:45 amRNSHolding(s) in Company
13th Dec 20212:05 pmRNSSecond Price Monitoring Extn
13th Dec 20212:00 pmRNSPrice Monitoring Extension
10th Dec 202111:05 amRNSSecond Price Monitoring Extn
10th Dec 202111:00 amRNSPrice Monitoring Extension
10th Dec 20217:00 amRNSSubmission of Transmission Integration Study
7th Dec 20217:00 amRNSRepayment of Director’s Bridge Loan
3rd Dec 20217:00 amRNSUS$1.3 million Sale of C&I Subsidiary
17th Nov 202110:30 amRNSResult of AGM
28th Oct 20216:35 pmRNSHolding(s) in Company-Amendment
28th Oct 20212:30 pmRNSHolding(s) in Company
25th Oct 20217:00 amRNSNotice of AGM
15th Oct 20217:00 amRNSDirectors Bridge Loan Extension
13th Oct 20214:41 pmRNSSecond Price Monitoring Extn
13th Oct 20214:36 pmRNSPrice Monitoring Extension
13th Oct 20213:00 pmRNSMaiden C&I Project Fully Commissioned
29th Sep 20217:00 amRNSHalf-year Report
22nd Sep 20219:05 amRNSSecond Price Monitoring Extn
22nd Sep 20219:00 amRNSPrice Monitoring Extension
9th Sep 20217:00 amRNSPower Plant EPC Contract Signed
26th Aug 20214:40 pmRNSSecond Price Monitoring Extn
26th Aug 20214:35 pmRNSPrice Monitoring Extension
26th Aug 20212:05 pmRNSSecond Price Monitoring Extn
26th Aug 20212:00 pmRNSPrice Monitoring Extension
26th Aug 202112:45 pmRNSPlacing
23rd Aug 20217:00 amRNSEPC Contract Target Signature Date Agreed
12th Jul 20211:45 pmRNSTermination of EBTs
12th Jul 20217:00 amRNSCorporate Presentation
25th Jun 20217:00 amRNSAnnual Financial Report
14th Jun 20217:00 amRNSNESA Power Joint Venture Term Sheet Signed
9th Jun 20217:00 amRNSC&I Solar Battery Pipeline Update
4th Jun 20214:41 pmRNSSecond Price Monitoring Extn
4th Jun 20214:36 pmRNSPrice Monitoring Extension
1st Jun 20217:00 amRNSSolar Battery Project Update
19th May 20217:00 amRNSProject Update
4th May 20217:00 amRNSSolar Battery Project Fully Financed
8th Apr 20217:00 amRNSNon-Executive Director/ PDMR dealing
6th Apr 20217:00 amRNSC&I Project Update & Directors Bridge Loan
25th Mar 20217:05 amRNSCEO Share Subscription
25th Mar 20217:00 amRNSProject Update
9th Mar 20217:00 amRNSAppointment of Project Advisors

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.