Weekly Project Update

 

Mosman Oil & Gas (AIM: MSMN), the New Zealand and Australia focussed oil exploration and development company, advises on latest progress at its Petroleum Creek Project as follows.

 

The Cross Roads-1 well has been halted at 335m, for future re-entry and testing. The Oil Discovery in the Eight Mile formation means the exploration phase has been successful and signals the start of the appraisal phase. Meetings will be held next week to review the core and wireline log data obtained, and to consider the next steps. This includes laboratory analysis of core data, review of the geological model and detailed well test design. The team will also review the mapped extent of the accumulation and consider what additional information is required to determine contingent resources.

 

As previously reported the Cobden limestone had oil shows in the bottom of the 8.5 inch hole at 241m and in the first 6m of core (242m to 247m). Evidence of fracturing then increased, significant mud losses occurred, and oil shows ceased. Wireline logs were performed and reviewed by independent consultants and it has been determined that the logs for the Cobden limestone are inconclusive and further analyses and tests are required.

 

This has no effect on the Oil Discovery reported for the Eight Mile formation.

 

Cross Roads-1 was cored and drilled to near-basement at 335m, and 4.5 inch casing run and cemented to allow future cased hole testing of the Cobden and Eight Mile formations. Due to extended coring and logging operations created by the previously reported oil shows, and minor rig equipment delays, the well has taken a few days longer than anticipated. In accordance with operational Health Safety and Environment (HSE) requirements, the rig crew is now on break time. From an HSE perspective, we are pleased to report there been no HSE incidents. The rig, crew and service company performance has been excellent.

 

With the new geological information acquired and the encouraging results, Mosman (in consultation with its existing resource consultants, and now additional petroleum engineers), is reviewing the 2014 forward programme at Petroleum Creek. Of note is an increased focus on the seismic defined flank prospects near Cross Roads-1. These include the Blair, Pipers Creek, No Town Track and Bells Gully prospects, which were previously identified by SRK. At this stage it is anticipated that some of these locations could be ready to drill in the next few weeks. The prospects and logistics are being reviewed to determine the optimal well design and the sequence of drilling. The recent funding allows important foundation work to be undertaken, such as additional technical studies and seismic acquisition and re-processing, as well as operational improvements such as the purchase of the currently rented property to provide the local base camp and storage area.

 

Given the recent capital raising, and the success at Cross Roads-1, it is now anticipated that at least 4 and possibly 5 or 6 wells may be drilled in 2014. Planning has also commenced on seismic targets which may be acquired in the near term.

 

John W Barr, Executive Chairman of Mosman commented: "Cross Roads-1's success has brought early exploration success and as a result we are making every effort to increase and maximize the exploration efforts in 2014. Focus has now broadened to review and appraisal and resetting priorities for the next few months."

 

Investor presentations

John W Barr and Andy Carroll will be in London presenting at the Oil Barrel conference on 2 July, and at the Proactive Investors event on 10 July. Both events are recommended to investors.

 

Competent Person's Statement

The information contained in this announcement has been reviewed and approved by Andy Carroll, Technical Director for Mosman Oil and Gas, who has over 35 years of relevant experience in the oil industry. Mr Carroll is a member of the Society of Petroleum Engineers (SPE).

 

 

Enquiries

 

Mosman Oil & Gas Limited

John W Barr, Executive Chairman

Andy Carroll, Technical Director

jwbarr@mosmanoilandgas.com

acarroll@mosmanoilandgas.com

 

SI Capital Limited

Nick Emerson/Andy Thacker

+44 (0) 1483 413500

Gable Communications

Justine James/John Bick

+44 (0) 20 7193 7463

mosman@gablecommunications.com

 

ZAI Corporate Finance Limited

Tom Price/John Simpson

+44 (0) 20 7060 2220

 

Updates on the Company's activities are regularly posted on its website www.mosmanoilandgas.com

 

About Mosman

Mosman (AIM: MSMN) is a New Zealand and Australia focussed oil exploration and development company, with the Petroleum Creek Project, an onshore oil and gas projects in New Zealand and in the Officer Basin Project in Western Australia.

 

Petroleum Creek Project, New Zealand

Mosman's immediate focus is on the Petroleum Creek Project a 143.6 sq. km low cost onshore exploration project located near Greymouth on the South Island in the southern extension of the proven Taranaki oil system. The project has a Mean Unrisked Recoverable OIIP of 26.6 Mmstb and the Cross Roads-1 well was declared an Oil Discovery in June 2014.

 

Officer Basin Project, Australia

Mosman has a 25% investment in the Officer Basin Project, a 22,527 sq. km large land holding with significant exploration potential, which lies in one of the more explored parts of the Basin with road access. The project area is in the Western Australian part of the Officer Basin and offers both conventional and unconventional potential with hydrocarbon shows reported and all elements of a petroleum system are present.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCLLLLLZQFEBBD
Date   Source Headline
26th Feb 20259:32 amRNSOperational, Corporate, and Board Updates
20th Feb 202510:25 amRNSEPA-155 Update
3rd Feb 20258:19 amRNSUSA Helium Project Update and EP145 Sale Update
30th Jan 20258:21 amRNSUSA Helium Project Update
29th Jan 202510:30 amRNSExploration Permit EP-145 Update
22nd Jan 20259:05 amRNSReplacement: EP(A) 155 and Exploration Update
22nd Jan 20257:41 amRNSEP(A) 155 and Exploration Update
14th Jan 202510:43 amRNSPortfolio Review and Sale of EP-145
30th Dec 20248:47 amRNSAcquisition of Helium Exploration Lease in US
24th Dec 20249:35 amRNSUpdate on Vecta Helium Project and EP-145
19th Dec 20247:54 amRNSHelium Exploration Leases in Colorado, USA
13th Dec 20249:30 amRNSExploration Update - Australia
11th Dec 20247:54 amRNSEPA 155 Update
10th Dec 202411:43 amRNSIssue of Options and Capital Structure Update
29th Nov 20248:33 amRNSResult of AGM
28th Nov 202411:00 amRNSAGM Statement
5th Nov 202410:05 amRNSNotice of AGM and posting of Annual Report
31st Oct 20247:00 amRNSFinal Results to 30 June 2024
15th Oct 20249:37 amRNSEP-145 Update
2nd Oct 20247:00 amRNSCompletion of Sale of Oil Assets
16th Sep 20247:00 amRNS£1.5m Placing to Pursue Helium Opportunities
13th Sep 202411:29 amRNSResolution of Legal Action
10th Sep 20248:30 amRNSWarrant Exercise
9th Sep 20241:28 pmRNSSale of Oil Assets - Update
4th Sep 20247:00 amRNSSale of Oil Assets - Update
6th Aug 202410:52 amRNSEP 145 Update
5th Aug 20249:04 amRNSCapital Structure and Helium Update
26th Jul 20249:21 amRNSWarrant Exercise
23rd Jul 20247:38 amRNSWI Increased to 20% of Vecta Helium Project
22nd Jul 202411:18 amRNSWarrant Exercise
16th Jul 20249:41 amRNSWarrant Exercise
15th Jul 20249:08 amRNSJune 2024 Quarter Summary and Corporate Update
10th Jul 20248:28 amRNSWarrant Exercise and Total Voting Rights
4th Jul 20248:19 amRNSUpdate re. EP 155 Farmin Partner
1st Jul 20249:42 amRNSWarrant Exercise
26th Jun 20249:25 amRNSWarrant Exercise
25th Jun 202410:36 amRNSWarrant Exercise
18th Jun 20248:38 amRNSWarrant Exercise
17th Jun 20249:53 amRNSWarrant Exercise
12th Jun 20247:00 amRNSEP 145 - Helium Project Update
10th Jun 20247:00 amRNSSale of Oil Assets
4th Jun 20241:30 pmRNSWarrant Exercise
3rd Jun 20247:00 amRNSHelium Acquisition
31st May 20247:00 amRNSEP 145 - Helium Project Update
28th May 20247:00 amRNSUS Operations Update
7th May 20247:00 amRNSProduction Increases at Stanley & EP145 update
29th Apr 20248:55 amRNSEP 145 Farmin receives Government Approval
10th Apr 202412:53 pmRNSMarch 2024 Quarter Production Summary
28th Mar 20248:09 amRNSProgressing Helium & Hydrogen Exploration in E 145
27th Mar 20249:06 amRNSHalf Year Results

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.