Petroleum Creek Weekly Update

23 Jun 2014 07:00

RNS Number : 2176K
Mosman Oil and Gas Limited
23 June 2014
 



 

23 June 2014

 

Mosman Oil and Gas Limited

("Mosman" or the "Company")

 

Weekly Project Update

 

Mosman Oil & Gas (AIM: MSMN), the New Zealand and Australia focussed oil exploration and development company, advises on latest progress at its Petroleum Creek Project as follows.

 

The Cross Roads-1 well has been halted at 335m, for future re-entry and testing. The Oil Discovery in the Eight Mile formation means the exploration phase has been successful and signals the start of the appraisal phase. Meetings will be held next week to review the core and wireline log data obtained, and to consider the next steps. This includes laboratory analysis of core data, review of the geological model and detailed well test design. The team will also review the mapped extent of the accumulation and consider what additional information is required to determine contingent resources.

 

As previously reported the Cobden limestone had oil shows in the bottom of the 8.5 inch hole at 241m and in the first 6m of core (242m to 247m). Evidence of fracturing then increased, significant mud losses occurred, and oil shows ceased. Wireline logs were performed and reviewed by independent consultants and it has been determined that the logs for the Cobden limestone are inconclusive and further analyses and tests are required.

 

This has no effect on the Oil Discovery reported for the Eight Mile formation.

 

Cross Roads-1 was cored and drilled to near-basement at 335m, and 4.5 inch casing run and cemented to allow future cased hole testing of the Cobden and Eight Mile formations. Due to extended coring and logging operations created by the previously reported oil shows, and minor rig equipment delays, the well has taken a few days longer than anticipated. In accordance with operational Health Safety and Environment (HSE) requirements, the rig crew is now on break time. From an HSE perspective, we are pleased to report there been no HSE incidents. The rig, crew and service company performance has been excellent.

 

With the new geological information acquired and the encouraging results, Mosman (in consultation with its existing resource consultants, and now additional petroleum engineers), is reviewing the 2014 forward programme at Petroleum Creek. Of note is an increased focus on the seismic defined flank prospects near Cross Roads-1. These include the Blair, Pipers Creek, No Town Track and Bells Gully prospects, which were previously identified by SRK. At this stage it is anticipated that some of these locations could be ready to drill in the next few weeks. The prospects and logistics are being reviewed to determine the optimal well design and the sequence of drilling. The recent funding allows important foundation work to be undertaken, such as additional technical studies and seismic acquisition and re-processing, as well as operational improvements such as the purchase of the currently rented property to provide the local base camp and storage area.

 

Given the recent capital raising, and the success at Cross Roads-1, it is now anticipated that at least 4 and possibly 5 or 6 wells may be drilled in 2014. Planning has also commenced on seismic targets which may be acquired in the near term.

 

John W Barr, Executive Chairman of Mosman commented: "Cross Roads-1's success has brought early exploration success and as a result we are making every effort to increase and maximize the exploration efforts in 2014. Focus has now broadened to review and appraisal and resetting priorities for the next few months."

 

Investor presentations

John W Barr and Andy Carroll will be in London presenting at the Oil Barrel conference on 2 July, and at the Proactive Investors event on 10 July. Both events are recommended to investors.

 

Competent Person's Statement

The information contained in this announcement has been reviewed and approved by Andy Carroll, Technical Director for Mosman Oil and Gas, who has over 35 years of relevant experience in the oil industry. Mr Carroll is a member of the Society of Petroleum Engineers (SPE).

 

 

Enquiries

 

Mosman Oil & Gas Limited

John W Barr, Executive Chairman

Andy Carroll, Technical Director

jwbarr@mosmanoilandgas.com

acarroll@mosmanoilandgas.com

 

SI Capital Limited

Nick Emerson/Andy Thacker

+44 (0) 1483 413500

Gable Communications

Justine James/John Bick

+44 (0) 20 7193 7463

mosman@gablecommunications.com

 

ZAI Corporate Finance Limited

Tom Price/John Simpson

+44 (0) 20 7060 2220

 

Updates on the Company's activities are regularly posted on its website www.mosmanoilandgas.com

 

About Mosman

Mosman (AIM: MSMN) is a New Zealand and Australia focussed oil exploration and development company, with the Petroleum Creek Project, an onshore oil and gas projects in New Zealand and in the Officer Basin Project in Western Australia.

 

Petroleum Creek Project, New Zealand

Mosman's immediate focus is on the Petroleum Creek Project a 143.6 sq. km low cost onshore exploration project located near Greymouth on the South Island in the southern extension of the proven Taranaki oil system. The project has a Mean Unrisked Recoverable OIIP of 26.6 Mmstb and the Cross Roads-1 well was declared an Oil Discovery in June 2014.

 

Officer Basin Project, Australia

Mosman has a 25% investment in the Officer Basin Project, a 22,527 sq. km large land holding with significant exploration potential, which lies in one of the more explored parts of the Basin with road access. The project area is in the Western Australian part of the Officer Basin and offers both conventional and unconventional potential with hydrocarbon shows reported and all elements of a petroleum system are present.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCLLLLLZQFEBBD
Date   Source Headline
5th Aug 20197:00 amRNSSpudding of Stanley-3
31st Jul 20198:02 amRNSSix Month Production Update
24th Jul 201911:59 amRNSAustralian Exploration Update
15th Jul 20197:00 amRNSStanley-2 Initial Production
1st Jul 20197:00 amRNSSale of Strawn Production Facilities and Leases
27th Jun 201912:38 pmRNSStanley Project Update
25th Jun 20197:00 amRNSOperations Update
14th May 20197:00 amRNSChampion drilling, fundraising and Stanley update
8th May 20197:05 amRNSCorporate Presentation
8th May 20197:00 amRNSFarm-out of Champion Project
24th Apr 20199:00 amRNSProduction Update
18th Apr 20198:38 amRNSStanley Production Update
11th Apr 201910:03 amRNSStanley Project Update
1st Apr 20197:00 amRNSStanley-2 Drilling Update
28th Mar 201911:10 amRNSHalf-year Report
25th Mar 20199:16 amRNSStanley Project Update
19th Mar 20197:00 amRNSStanley-2 Drilling Update
14th Mar 201911:55 amRNSTechnical Presentation at AGES conference in NT
13th Mar 20198:43 amRNSRecompletion of Stanley-1
12th Mar 20194:40 pmRNSSecond Price Monitoring Extn
12th Mar 20194:35 pmRNSPrice Monitoring Extension
4th Mar 20199:53 amRNSStanley Update
12th Feb 201911:33 amRNSUpdate on Gem International Resources Inc
7th Feb 201910:51 amRNSIncreased Interest in Texas Production Lease
6th Feb 20197:00 amRNSProduction Update
7th Jan 20192:30 pmRNSStanley-2 well update
20th Dec 20189:49 amRNSResult of AGM
11th Dec 201812:41 pmRNSSpudding Stanley-2 and Increased Working Interest
5th Dec 20182:24 pmRNSDirectors' Subscription
30th Nov 20187:00 amRNSStanley-2 Drilling Update
28th Nov 201812:54 pmRNSNotice of AGM
28th Nov 201812:50 pmRNSFinal Results
13th Nov 20188:57 amRNSStanley-1 Well Test Results
9th Nov 20188:38 amRNSPlanned drilling, operational update & fundraising
29th Oct 201811:53 amRNSTexas Projects Update
18th Oct 20188:03 amRNSWeather causes delays in Texas
18th Oct 20187:58 amRNSStanley-1 Production and Stanley-2 Update
4th Oct 20187:52 amRNSStanley First Sales and Planning of Stanley-2
28th Sep 20181:16 pmRNSArkoma Project Update
24th Sep 20187:00 amRNSAcquisitions and Baja Strategic Alliance Update
18th Sep 201812:58 pmRNSArkoma Project Update
17th Sep 20188:09 amRNSHydrocarbon Production and Sales at Stanley-1
4th Sep 20187:00 amRNSIncreased Production & new Corporate Presentation
2nd Aug 20188:11 amRNSJoint Broker Appointment
1st Aug 20187:00 amRNSSuccessful drilling at Stanley completed
30th Jul 20187:07 amRNSProduction almost doubles at Welch Project
25th Jul 20187:00 amRNSArkoma: 27% WI with option to increase to 33.3%
20th Jul 20187:32 amRNSStanley Drilling Project Update
17th Jul 201810:01 amRNSJuly 2018 Operations Update
2nd Jul 20187:00 amRNSArkoma Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.