Interim Management Statement

24 Oct 2014 07:00

RNS Number : 1768V
Morgan Sindall Group PLC
24 October 2014
Β 

ο»Ώ

Β 

24 October 2014

Morgan Sindall Group plc

Β 

Interim Management Statement

Β 

Morgan Sindall Group plc ('the Group') today announces its Interim Management Statement for the Period from 1 July 2014 to date ('the Period').

Β 

Group Performance and Outlook

Β 

Whilst the Group's Affordable Housing, Urban Regeneration, Fit Out and Infrastructure activities have performed well during the Period, the Group has been adversely impacted by a small number of construction contracts in London and the South which have experienced timetable slippages and increased estimated costs to complete.

Β 

As a result, the Board now expects the full year result will be below previous expectations set at the time of the half year results announced on 5 August 2014.

Β 

Further details are as set out below.

Β 

Operating Performance

Β 

In Construction & Infrastructure, whilst the Infrastructure business continues to perform in line with expectations, delivery pressures in London and the South's construction activities have adversely impacted performance with programme slippage and increases in costs to complete projects both contributing factors.

Β 

The deterioration in performance over the Period relates mainly to a small number of fixed price construction contracts which are due to complete within the next six months and were procured over a year ago.

Β 

Additional resources have been required to complete these contracts which, when added to inflationary pressures since contract win, have increased forecast costs to complete. Also, where programme overruns are now anticipated, forecast contractual penalties have further increased the potential contract costs.

Β 

Additionally, during the Period the construction site for the Β£15.8m construction of the GlaxoSmithKline Carbon Neutral Laboratory of Sustainable Chemistry for The University of Nottingham was destroyed by fire. Work commenced on site in autumn 2013 and was due for completion in early 2015 and therefore the loss of expected contribution from the time of the fire up to completion has further impacted divisional performance. Β 

As a result, the division is now expected to deliver a full year performance below previous expectations, with full year operating profit margins reduced from 1% in 2013 to around 0.3%-0.5%.

Β 

The Construction & Infrastructure committed order book was Β£1,550m as at 30 September 2014, down 5% from the half year end, however up 3% from the start of the year.

Β 

Fit Out has traded strongly, with significant levels of bidding activity resulting in the order book of Β£260m as at the end of September, up 17% from the half year and up 83% from the start of the year.

Β 

It is currently anticipated that the positive revenue and profit growth momentum will continue through to the end of the year and beyond and therefore the full year result is now expected to be above previous expectations.

Β 

In Affordable Housing, progress has been as expected, with sales of open market houses for the year currently expected to be level with the prior year, although a significant proportion are scheduled for construction and completion in the fourth quarter of the year. Investment has continued in developing mixed-tenure sites which will benefit the division from late 2015 and, particularly, in 2016 and beyond. The Response Maintenance activities continue to perform broadly in line with the repositioning and turnaround as detailed at the time of the half year results.

Β 

The Affordable Housing committed order book was Β£734m as at 30 September 2014, level with the half year end and up 26% from the start of the year

Β 

The key market sectors for Urban Regeneration being residential, commercial and industrial all remain strong. Current and forecast progress on the portfolio of active development schemes indicates that the division is on track to deliver a strong performance for the year, with significant progress being made towards its targeted return of 15%. However, as is normal for its activities, the division's short-term profit performance is in part dependent upon third party construction programmes and completions, some of which are currently scheduled for completion in the final quarter of the year. As a consequence, some of these activities may now complete in 2015.

Β 

During the Period, Investments headed up the consortium appointed as Preferred Bidder for the North West batch of the Priority Schools Building Programme under the Government's PF2 initiative, for projects with a capital value of between Β£80-120m.

Β 

Order Book

Β 

The Group's committed order book1 as at 30 September 2014 was Β£2.7bn, down 2% from the half year position but up 12% from the start of the year. The Regeneration & development pipeline2 as at 30 September 2014 was Β£3.2bn, level with the half year position and up 5% from the start of the year

Β 

Financial Position

Net debt as at 22 October was Β£32.0m. Average daily net debt from the start of the year to 22 October was Β£7.7m.

Β 

Directorate Change

Β 

Geraldine Gallacher will be retiring from the Board as a non-executive director and member of the audit, remuneration and nomination committees with effect from 31 December 2014. The Board would like to thank Geraldine for her commitment and significant contribution to the Group over the last seven years.

Β 

Outlook

Β 

Whilst the Group's Affordable Housing, Urban Regeneration, Fit Out and Infrastructure activities have performed well during the Period, the Group has been adversely impacted by a small number of construction contracts in London and the South which have experienced timetable slippages and increased estimated costs to complete.

Β 

As a result, the Board now expects the full year result will be below its previous expectations set at the time of the half year results announced on 5 August 2014.

Β 

Looking further ahead, the Board remains confident that with the market positions held and the development opportunities being pursued, together with the strong order book and the more positive general market conditions, the Group is well-positioned to benefit from the significant growth opportunities available.

Β 

John Morgan, Chief Executive, said;

Β 

"We are obviously disappointed that a small number of construction contracts in London and the South have been impacted by timetable slippage and increased estimated costs to complete. This is a short-term and localised issue which is receiving the highest level of management attention and which should be worked through over the next six months.

Β 

The rest of the business is performing well, particularly Fit Out, and we expect an improved performance from Urban Regeneration in the year, supporting our long-term strategy of investment in regeneration. We firmly believe that the medium and long term opportunities and prospects for the Group remain very attractive, as demonstrated by the higher quality order book and pipeline."

Β 

Β 

Β 1 'Committed order book' comprises the secured order book and framework order book. The secured order book represents the Group's share of future revenue that will be derived from signed contracts or letters of intent. The framework order book represents the Group's expected share of revenue from the frameworks on which the Group has been appointed. This excludes prospects where confirmation has been received as preferred bidder only, with no formal contract or letter of intent in place.

Β 

2Β 'Regeneration & development pipeline' represents the Group's share of the gross development value of secured schemes including the estimated development value of open market housing schemes.

Β 

ENDS

Morgan Sindall Group

Morgan Sindall Group plc is a leading UK construction and regeneration group with revenue of cΒ£2 billion, employing around 5,700 employees and operating in the public and commercial sectors. It operates through five divisions of construction and infrastructure, fit out, affordable housing, urban regeneration and investments.

Β 

ENQUIRIES:

Β 

Morgan Sindall Group Tel: 020 7307 9200

John Morgan, Chief Executive

Steve Crummett, Finance Director

Β 

Brunswick Tel: 020 7404 5959

Jonathan Glass

Alison Kay

This information is provided by RNS
The company news service from the London Stock Exchange
Β 
END
Β 
Β 
IMSBCBDGGBDBGSX
Date   Source Headline
11th Jul 20227:00 amRNSNotice of Results
1st Jul 202210:50 amRNSTotal Voting Rights
14th Jun 202212:51 pmRNSAdditional Listing
6th Jun 202212:00 pmRNSTotal Voting Rights
1st Jun 20223:49 pmRNSDirector Declaration
17th May 20221:47 pmRNSHolding(s) in Company
10th May 202211:23 amRNSAdditional Listing
5th May 20224:45 pmRNSResult of AGM
5th May 20227:00 amRNSAGM Trading Update
3rd May 20223:48 pmRNSTotal Voting Rights
20th Apr 202210:25 amRNSBlock listing Interim Review
5th Apr 202210:40 amRNSAdditional Listing
5th Apr 20227:00 amRNSMeet the Management Forum
1st Apr 202210:36 amRNSTotal Voting Rights
24th Mar 202212:46 pmRNSAnnual Financial Report
18th Mar 202211:57 amRNSDirector/PDMR Shareholding
16th Mar 20223:03 pmRNSDirector/PDMR Shareholding
16th Mar 20229:23 amRNSDirector/PDMR Shareholding
16th Mar 20229:21 amRNSDirector/PDMR Shareholding
8th Mar 20224:00 pmRNSAdditional Listing
8th Mar 20228:27 amRNSHolding(s) in Company
7th Mar 20221:55 pmRNSDirector/PDMR Shareholding
7th Mar 20221:51 pmRNSDirector/PDMR Shareholding
4th Mar 20224:04 pmRNSDirector/PDMR Shareholding
4th Mar 20224:00 pmRNSDirector/PDMR Shareholding
1st Mar 20222:39 pmRNSTotal Voting Rights
24th Feb 20227:00 amRNSFinal Results
7th Feb 20227:00 amRNSNotice of Results
1st Feb 202211:41 amRNSTotal Voting Rights
4th Jan 20223:15 pmRNSTotal Voting Rights
21st Dec 202111:42 amRNSDirector Declaration
7th Dec 20212:26 pmRNSAdditional Listing
30th Nov 20214:53 pmRNSTotal Voting Rights
9th Nov 202112:51 pmRNSAdditional Listing
3rd Nov 20217:00 amRNSTrading Update
1st Nov 20219:24 amRNSTotal Voting Rights
20th Oct 202110:57 amRNSBlock listing Interim Review
20th Oct 20218:43 amRNSChange in Directors' Details
7th Oct 20218:44 amRNSAdditional Listing
4th Oct 20213:27 pmRNSHolding(s) in Company
1st Oct 20219:50 amRNSTotal Voting Rights
24th Sep 20218:00 amRNSHolding(s) in Company
22nd Sep 20218:19 amRNSHolding(s) in Company
7th Sep 20211:19 pmRNSAdditional Listing
2nd Sep 20217:26 amRNSHolding(s) in Company
1st Sep 202111:44 amRNSTotal Voting Rights
10th Aug 20213:13 pmRNSAdditional Listing
9th Aug 20214:26 pmRNSDirector/PDMR Shareholding
4th Aug 20217:00 amRNSHalf-year Report
2nd Aug 20219:37 amRNSTotal Voting Rights

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.