MCPP: Final Approval for ESIA Scoping Reports

16 Jan 2017 07:00

RNS Number : 2188U
Kibo Mining Plc
16 January 2017
 

Kibo Mining Plc (Incorporated in Ireland)

(Registration Number: 451931)

(External registration number: 2011/007371/10)

Share code on the JSE Limited: KBO 

Share code on the AIM:KIBO

ISIN:  IE00B97C031

("Kibo" or "the Company")

 

 

16 January 2017

 

Mbeya Coal to Power Project Receives Final Approval for ESIA Scoping Reports

 

Kibo Mining plc ("Kibo" or the "Company") (AIM: KIBO; AltX: KBO), the Tanzania focused mineral exploration and development Company, is pleased to announce that the Tanzania National Environmental Management Council ("NEMC") approved and accepted both the Mbeya Coal Mine and Mbeya Power Plant Environmental and Social Impact Assessment ("ESIA") scoping reports.

 

Approval and acceptance of the scoping reports concludes Stage 2 of the required three stage statutory ESIA approval process. Completion of Stage 2 now paves the way for final ESIA certification of both the Mbeya Coal Mine and the Mbeya Power Plant.

 

Louis Coetzee, CEO of Kibo Mining, said: "Approval and acceptance of the MCPP ESIA scoping reports represents a critical point in the overall ESIA approval process. At this stage the majority of the ESIA work, i.e. specific ESIA terms of reference, required specialist studies as well as consultation, have been completed, submitted and accepted by the NEMC as compliant for certification. We expect Stage 3, (i.e. certification process), to be completed in a shorter time frame than usual, given the fact that the preparation work for an accelerated conclusion of Stage 3 was done whilst awaiting approval of the scoping reports.

 

Receipt of the scoping report approvals from the NEMC, follows a week of broad and productive consultation with various Tanzanian Government departments regarding the further development of the MCPP. These discussions once again confirmed continued support for the MCPP as a strategic energy / development project and also that the recent and still ongoing policy changes and restructuring, will have significant long term benefits for projects like the MCPP.

 

Further updates in this regard as well as an update on the completion of the MCPP Integrated Bankable Feasibility Study will follow shortly"

 

 

Contacts

 

Louis Coetzee

 

 

+27 (0) 83 2606126

 

 

Kibo Mining plc

 

 

Chief Executive Officer

 

Andreas Lianos

+27 (0) 83 4408365

River Group

Corporate Adviser and

Designated Adviser on JSE

Jon Belliss

+44 (0) 207 382 8300

Beaufort Securities Limited

Broker

Oliver Morse

+61 8 9480 2500

RFC Ambrian Limited

Nominated Adviser

on AIM

Liz Morley /

Anna Legge

+44 (0) 203 772 2500

Bell Pottinger

Investor and Media Relations

 

 

Kibo Mining - Notes to editors

Kibo Mining is listed on the AIM market in London and the AltX in Johannesburg. The Company is focused on exploration and development of mineral projects in Tanzania, and controls one of Tanzania's largest mineral right portfolios. Tanzania provides a secure and stable operating environment for the mineral resource industry and Kibo Mining therein.

 

Kibo Mining holds a thermal coal deposit at Mbeya, which has a significant NI 43-101 compliant defined resource, and is developing a 250-350 MW mouth-of-mine thermal power station, the Mbeya Coal to Power Project ("MCPP"), previously called Rukwa Coal to Power Project ("RCPP"), with an established management team that includes ABSA / Barclays as Financial Advisor. Kibo is undertaking a Coal Mining Definitive Feasibility Study and a Power Pre- Feasibility Study for the Mbeya project with an Integrated Bankable Feasibility Study report for the MCPP to be released in the near term. On 25 August 2016, Kibo signed an Agreement with China based EPC contractor SEPCO III granting it the right to become the sole bidder for the EPC contract to build the power plant component of the MCPP in exchange for SEPCO III refunding 50% of the development costs incurred by Kibo to date on the project. Kibo has already received the first tranche of this funding in the amount of US$1.8 million on the 5th September 2016

 

The Company also has extensive gold focused interests including Lake Victoria Goldfields and Morogoro projects. At Lake Victoria, the Company has 100% owned projects with a 550,000 oz. JORC compliant gold Mineral Resource at the Imweru Project and a 168,000 oz. NI 43-101 compliant gold Mineral Resource at the Lubando Project. The Company is currently undertaking a Definitive Feasibility Study on its Imweru Project.

 

Kibo also holds the Haneti Project on which the latest technical report confirms prospectivity for nickel, PGMs, gold and strategic metals including lithium.

 

Kibo Mining further holds the Pinewood (coal & uranium) project where the company has entered into a 50/50 Exploration Joint Venture with Metal Tiger plc.

 

Finally, the Company also holds the Morogoro (gold) project where the company has also entered into a 50/50 Exploration Joint Venture with Metal Tiger plc.

 

The Company's projects are located in the established and gold prolific Lake Victoria Goldfields, the emerging goldfields of eastern Tanzania and the Mtwara Corridor in southern Tanzania where the Government has prioritized infrastructural development attracting significant recent investment in coal and uranium. The Company has a positive working relationship with the Tanzanian government at local, regional and national levels and works hard to maintain positive relationships with all communities where company interests are held. The Company recognizes the potential to enhance the quality of life and opportunity for Tanzanian citizens through careful development of its projects.

 

Updates on the Company's activities are regularly posted on its website www.kibomining.com

 

 

Johannesburg

16 January 2017

Corporate and Designated Adviser

River Group

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCBFMFTMBJBMAR
Date   Source Headline
22nd Dec 20208:00 amRNSBenga Power Plant Project Update
21st Dec 20207:00 amRNSSloan (MED) to Trigger 2nd Production-Ready Site
17th Dec 20208:00 amRNSUpdate on PPA with Baobab Resources Ltd
14th Dec 202012:40 pmRNSResults of AGM
11th Dec 20202:05 pmRNSSecond Price Monitoring Extn
11th Dec 20202:00 pmRNSPrice Monitoring Extension
20th Nov 202010:00 amRNSNotice of AGM
20th Nov 20208:00 amRNSTR-1: Notification of major holdings
19th Nov 20204:41 pmRNSSecond Price Monitoring Extn
19th Nov 20204:36 pmRNSPrice Monitoring Extension
12th Nov 202011:06 amRNSSecond Price Monitoring Extn
12th Nov 202011:00 amRNSPrice Monitoring Extension
10th Nov 202011:06 amRNSSecond Price Monitoring Extn
10th Nov 202011:00 amRNSPrice Monitoring Extension
6th Nov 20203:45 pmRNSIssue of Shares in lieu of payment to Contractors
3rd Nov 20204:41 pmRNSSecond Price Monitoring Extn
3rd Nov 20204:35 pmRNSPrice Monitoring Extension
3rd Nov 20202:06 pmRNSSecond Price Monitoring Extn
3rd Nov 20202:00 pmRNSPrice Monitoring Extension
28th Oct 20208:00 amRNSUK Subsidiary Secures Third Reserve Power Site
23rd Oct 20204:41 pmRNSSecond Price Monitoring Extn
23rd Oct 20204:35 pmRNSPrice Monitoring Extension
22nd Oct 20208:00 amRNSUnaudited Interim results 30 June 2020
22nd Oct 20207:55 amRNSTR-1: Notification of major holdings
15th Oct 202011:05 amRNSSecond Price Monitoring Extn
15th Oct 202011:00 amRNSPrice Monitoring Extension
14th Oct 20207:00 amRNSAppointment of Executive Director
13th Oct 202011:00 amRNSNew Corporate Presentation
13th Oct 20207:00 amRNSTR-1: notification of major holdings
9th Oct 20209:20 amRNSTR-1: Standard notification of major holdings
6th Oct 20204:40 pmRNSSecond Price Monitoring Extn
6th Oct 20204:35 pmRNSPrice Monitoring Extension
6th Oct 20209:40 amRNSInvestor Webinar
1st Oct 20209:55 amRNSUpdate on PPA with Baobab Resources Ltd
30th Sep 20207:00 amRNSTR-1: Standard form notification of major holdings
23rd Sep 20208:00 amRNSResults for the Year Ended 31 December 2019
18th Sep 20208:00 amRNSClarification to Company RNS of 17 September 2020
17th Sep 20207:00 amRNSSettlement and Termination of CLN's and Placing
7th Sep 20208:25 amRNSSloane Acquires 9 MW flexible power project
4th Sep 20209:35 amRNSTR-1: Notification of major holdings
2nd Sep 20201:35 pmRNSIssue of Conversion Shares
26th Aug 202010:10 amRNSUpdate on the Mozambique Power Project Portfolio
25th Aug 202012:00 pmRNSPublication of Full Year and Half-Yearly Accounts
24th Aug 20203:00 pmRNSFacility Arrangement Fee & Conversion Shares Issue
24th Aug 202010:35 amRNSResults of EGM
19th Aug 20204:41 pmRNSSecond Price Monitoring Extn
19th Aug 20204:36 pmRNSPrice Monitoring Extension
18th Aug 202010:30 amRNSTR-1: Standard form for notification
11th Aug 202011:05 amRNSSecond Price Monitoring Extn
11th Aug 202011:00 amRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.