Mbeya Coal to Power Project ("MCPP") - Update

26 Jul 2017 07:00

RNS Number : 1130M
Kibo Mining Plc
26 July 2017
 

Kibo Mining Plc (Incorporated in Ireland)

(Registration Number: 451931)

(External registration number: 2011/007371/10)

Share code on the JSE Limited: KBO 

Share code on the AIM:KIBO

ISIN:  IE00B97C031

("Kibo" or "the Company")

 

 

26 July 2017

 

 

Mbeya Coal to Power Project ("MCPP") - Update

Kibo Mining plc ("Kibo" or the "Company") (AIM: KIBO; AltX: KBO), the Tanzania focused mineral exploration and development Company, is pleased to announce that, following recent announcements (See RNS' of 01 June 2017, 14 June 2017 and 14 July 2017), the Company has during the past week concluded a very successful second round of follow-up meetings with Government departments and other Tanzanian stakeholders regarding the further development of the MCPP.

Whilst completion of the Mbeya Coal special mining right application remains on course, as does the environmental certification of the Mbeya Coal Mine and Mbeya Power Plant, the following significant milestones were also achieved during the past week:

· Official instruction by the Tanzanian Ministry of Energy and Minerals ("MEM"), to the Company and TANESCO, to prepare a final Memorandum of Understanding that will govern the further development of the MCPP in general and the Power Purchase Agreement ("PPA") in particular. The latter is to be submitted to the Attorney General for review within the next ten days, with the Company anticipating receipt of approval sometime thereafter in the absence of any feedback to the contrary;

· On the back of the latest progress made in the further development of the MCPP, several formal expressions of interest were received from internationally recognized infrastructure investors, expressing interest in making equity investments in the MCPP.

Further high level workshops and meetings will take place over the course of next month as part of the ongoing priority development schedule for the MCPP and the Company looks forward to updating shareholders in due course.

 Louis Coetzee, CEO of Kibo Mining, said: "We are very pleased with progress on the MCPP over the past six weeks and particularly pleased with the significant increase in momentum over the past three weeks. Development of the MCPP is currently advancing on all levels and we are optimistic that this trend will persist going forward.

 

We will continue to keep the market updated".

 

 

 

Contacts

 

Louis Coetzee

 

 

+27 (0) 83 2606126

 

 

Kibo Mining plc

 

 

Chief Executive Officer

 

Andreas Lianos

+27 (0) 83 4408365

River Group

Corporate Adviser and

Designated Adviser on JSE

Jon Belliss

+44 (0) 207 382 8300

Beaufort Securities Limited

Broker

Andrew Thomson

+61 8 9480 2500

RFC Ambrian Limited

Nominated Adviser

on AIM

Liz Morley /

Molly Stewart

+44 (0) 203 772 2500

Bell Pottinger

Investor and Media Relations

 

 

Kibo Mining - Notes to editors

 

Kibo Mining is listed on the AIM market in London and the AltX in Johannesburg. Kibo Mining is focused on exploration and development of mineral projects in Tanzania, and controls a large mineral rights portfolio in Tanzania. Tanzania provides a secure and stable operating environment for the mineral resource industry and Kibo Mining therein.

 

Kibo Mining holds a thermal coal deposit at Mbeya, which has a significant NI 43-101compliant defined resource, and is developing a 250-350 MW mouth-of-mine thermal power station, the Mbeya Coal to Power Project ("MCPP"), previously called the Rukwa Coal to Power Project ("RCPP"), with an established management team that includes ABSA / Barclays as Financial Advisor. Kibo has completed a Coal Mining Definitive Feasibility Study and a Power Pre- Feasibility Study for the Mbeya project and has recently announced the completion of an Integrated Bankable Feasibility Study report for the project. On 25 August 2016, Kibo signed an Agreement with China based EPC contractor SEPCO III granting it the right to become the sole bidder for the EPC contract to build the power plant component of the MCPP in exchange for SEPCO III refunding 50% of the development costs incurred by Kibo to date on the project. Kibo has already received the first tranche of this funding in the amount of US$1.8 million on the 5th September 2016 and signed an EPC contract with SEPCO III on the 19th December 2016.

 

Kibo also holds the Haneti Project on which the latest technical report confirms prospectivity for nickel, PGMs, gold and strategic metals including lithium.

 

Kibo Mining's projects are located in central Tanzania and in the Mtwara Corridor in southern Tanzania where the Government has prioritized infrastructural development attracting significant recent investment in coal and uranium. Kibo Mining has a positive working relationship with the Tanzanian government at local, regional and national levels and works hard to maintain positive relationships with all communities where company interests are held. Kibo Mining recognizes the potential to enhance the quality of life and opportunity for Tanzanian citizens through careful development of its projects.

 

Updates on the Kibo Mining's activities are regularly posted on its website www.kibomining.com.

 

This announcement contains inside information as stipulated under the Market Abuse Regulations (EU) no. 596/2014 ("MAR").

 

 

Johannesburg

26 July 2017

Corporate and Designated Adviser

River Group

 

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCRFMATMBMTMLR
Date   Source Headline
15th Jun 20177:00 amRNSImweru Drill Programme Update
14th Jun 20177:00 amRNSMCPP Gains Momentum after Talks with Stakeholders
8th Jun 201711:00 amRNSAnnual Report and Notice of AGM
8th Jun 20178:09 amRNSKibo Monthly Q&A for Investors
2nd Jun 20179:00 amRNSNotice of AGM
2nd Jun 20178:00 amRNSLake Victoria Early Stage Licence Portfolio Update
1st Jun 20177:00 amRNSMCPP Receives Formal Reconfirmation
31st May 20177:00 amRNSUpdate on Katoro Gold PLC: Imweru Gold Project
31st May 20177:00 amRNSWork on Imweru Gold Project Commences
26th May 201711:00 amRNSFull Year Results 2016
5th May 20178:14 amRNSUpdate on Opera Reverse Take Over Transaction
20th Apr 20177:00 amRNSMCPP: MOU Mbeya Cement
12th Apr 20179:00 amRNSKibo commences monthly Q&A for investors
30th Mar 20177:00 amRNSDiversified Production Strategy for Mbeya Mine
23rd Mar 20178:00 amRNSQ1 2017 Strategic Objectives successfully met
6th Mar 20172:15 pmRNSMCPP Delivers First Classrooms
2nd Mar 201710:30 amRNSUpdate on Proposed Acquisition by Opera
1st Mar 201712:50 pmRNSNotifiable Holding Change
24th Feb 201710:00 amRNSCessation of Metal Tiger Joint Ventures
15th Feb 20179:31 amRNSMbeya Coal to Power Project Update
15th Feb 20178:45 amRNSMbeya Coal to Power Project Update
27th Jan 20177:00 amRNSChange of Share Registrar
23rd Jan 20177:00 amRNSMCPP Update: Integrated Bankable Feasibility Study
16th Jan 20177:00 amRNSMCPP: Final Approval for ESIA Scoping Reports
3rd Jan 201711:45 amRNSAnnouncement regarding TANESCO press reports
21st Dec 20162:50 pmRNSShare Issue
21st Dec 20168:47 amRNSTerm Sheet with Sanderson Capital Partners Agreed
21st Dec 20167:16 amRNSMCPP Update
19th Dec 20169:18 amRNSMCPP Update: EPC Contract Awarded to SEPCO III
9th Dec 20167:30 amRNSShare Issue
2nd Dec 20167:00 amRNSUpdate on Acquisition by Opera
30th Nov 20167:00 amRNSMCPP Update: Integrated Financial Model Completed
21st Nov 20167:00 amRNSMCPP Update: Collaboration Agreement with GE
1st Nov 20167:00 amRNSMCPP Update: Kibo Receives Final Commercial Bids
13th Oct 20167:00 amRNSAgreement of Development Costs for MCPP
27th Sep 20169:00 amRNSHalf-year Report
23rd Sep 20168:00 amRNSMCPP Update: Date Extended to Finalize Agreement
23rd Sep 20167:45 amRNSSigned Heads of Agreement with Opera Investments
22nd Sep 20167:00 amRNSMCPP Update: Financial Advisory Mandate Letter
16th Sep 20167:00 amRNSMCPP Update: MOU with GE International Inc.
8th Sep 201610:00 amRNSTransfer of Kibo Shares to Sanderson
5th Sep 20167:30 amRNSMCPP SEPCO III Agreement Update
1st Sep 20167:00 amRNSSanderson Loan Facility Repayment
25th Aug 20167:00 amRNSMCPP Update: New Agreement with SEPCO III
17th Aug 20168:00 amRNSLetter of Engagement with Norton Rose Fulbright
10th Aug 20161:00 pmRNSShare Issue
10th Aug 20167:02 amRNSDefinitive Agreement with Lake Victoria Gold Ltd
3rd Aug 20168:00 amRNSMCPP and Imweru Gold Project Interim Update
22nd Jul 20167:00 amRNSNet Smelter Royalty Agreement with Acacia
21st Jul 201612:00 pmRNSResult of AGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.