Production Update

12 Jul 2010 15:54

RNS Number : 2171P
GMA Resources PLC
12 July 2010
 



AIM: GMA

12 July 2010

 

GMA Resources plc

("GMA" or the "Company")

 

Production Update for Q2 2010

 

GMA announces that from 1 April to 30 June 2010, the Amesmessa gold mine in Algeria increased production to 6095.97 oz of gold (Q1 2010: 5,731.5 oz) and 1,205.43 oz of silver (Q1 2010: 1,197.3 oz). Detailed production data is set out below.

 

The unused carbon in leach (CIL) plant at Tirek has been transferred to Amesmessa, where compliance testing commenced in May. However, a failure of the gearbox that drives the ball mill and subsequent back up unit has delayed the start up until August. The replacement gear box has arrived in Algiers and is currently awaiting customs clearance. This plant is expected to contribute approximately a further 1,000 oz of gold to monthly output from August.

 

Systematic selection of higher grade, low strip ratio ore locations across the concession has commenced. This process is being made more productive by collecting new geochemical soil sampling data. As announced on 15 June 2010, initial work carried out resulted in the identification of 76 alteration zones within the concession which were considered to be potential loci of gold mineralisation. To date 26 of the 76 anomalies identified have been soil sampled. Results to date of the first anomalies tested have indicated elevated gold in soil results that will require follow up through trenching and drilling as previously reported. More recent results also indicate elevated gold in soil results. The purpose built drill rig has arrived at the mine site and preliminary drilling has commenced with the first 17 holes drilled and samples forwarded to the assay laboratory. Early drilling results will be announced later this year.

 

More detailed production data for second quarter of 2010 is set out in the table below:

 

Unit

Apr '10

May '10

June '10

2nd Quarter

Total Gold Production ENOR

oz

2,077.97

2,079.83

1,938.18

6,095.97

Total Silver Production ENOR

oz

412.43

411.51

381.49

1,205.43

High Grade Ore Tonnes ex-Mine

mt

7,590

1,200

2,460

11,250

High Grade Ore Grade ex-Mine

g/t Au

12.47

11.55

14.98

12.92

Heap Leach Ore Tonnes ex-Mine

mt

48,495

40,305

33,200

122,000

Heap Leach Ore Tonnes ex-Mine

g/t Au

2.59

2.62

3.66

2.89

Waste Tonnes Mined

mt

347,220

356,610

314,385

1,018,215

Strip Ratio

6.19

8.59

8.82

7.64

Ore Stacked to Heap Leach Pad

mt

40,071

46,520

43,357

129,948

Crushed Ore Grade

g/t Au

3.45

3.09

3.69

3.40

Recovery

%

46.74

44.97

37.70

42.90

 

 

 

 

 

Ken Crichton, Chief Executive of GMA, commented:

 

"Whilst management has been focused on securing financing for GMA's near term working capital requirements, steps have also been taken to establish more reliable and cost effective production at Amesmessa with incremental improvements in Q2 and more expected next quarter. In particular, we expect to see an improvement in output with the assistance of the Tirek CIL and continued exploration progress following up the early success in June."

 

Enquiries:

 

GMA Resources Plc

 

Ken Crichton

+20 (0)10766 6118

Merchant Securities Limited (Nomad)

Bidhi Bhoma

+44 (0) 20 7628 2200

 

Notes to Editors:

 

GMA owns a controlling 52% stake in ENOR spa ("ENOR"), the Algerian based operating company for the Tirek-Amesmessa project, with the remainder owned by Sonatrach, the Algerian state-owned oil and gas company.

 

ENOR holds the exploitation authorisation to the Tirek-Amesmessa property, an area of some 1,417 km2, located approximately 450km south west of the city, Tamanrasset, in southern Algeria. Amesmessa is an open pit heap leach gold mine located in the extreme south of the permit area. The now closed Tirek mine site is located centrally in the northern third of the exploration permit area, some 60 km north of Amesmessa. Research to date suggests that the Zita Zone, which lies between Tirek and Amesmessa, offers considerable potential for the development of additional prospects amenable to open-pit mining. GMA plans to quickly expand upon resources outside of the major 80km Tirek-Amesmessa fault north/south of the concession.

 

GMA's shares are traded on the AIM market of the London Stock Exchange (AIM: GMA).

 

For further information on the Company, please visit: www.gmaresources.co.uk

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCLLFESDVIFLII
Date   Source Headline
17th Apr 20132:27 pmRNSAcquisition
19th Mar 20137:00 amRNSAdviser Change of Name
28th Feb 20131:06 pmRNSResult of General Meeting
15th Feb 201310:23 amRNSIssue of Equity
7th Feb 201310:11 amRNSSchedule 1 - GMA Resources Plc
6th Feb 20132:03 pmRNSStmnt re Share Price Movement
5th Feb 20137:30 amRNSRestoration - GMA Resources Plc
4th Feb 20135:29 pmRNSAdmission document posted
4th Feb 20132:48 pmRNSProposed Acquisition
10th Dec 201210:08 amRNSResult of Class Meetings
13th Nov 201211:46 amRNSProposed amendments to Loan Stock Instruments
26th Sep 20127:00 amRNSHalf Yearly Report
10th Sep 20128:19 amRNSResult of AGM
23rd Aug 20128:56 amRNSPosting of Accounts
6th Aug 20127:00 amRNSFinal Results
29th May 20127:30 amRNSSuspension - GMA Resources Plc
29th May 20127:00 amRNSStatement re. Suspension
4th May 20123:53 pmRNSStmnt re Share Price Movement
17th Apr 201212:56 pmRNSFurther re Proposed Disposal of ENOR Spa
25th Jan 20127:00 amRNSStatement re Share Price Movement
9th Jan 201210:06 amRNSDirectorate Change
6th Jan 201210:48 amRNSResult of General Meeting
21st Dec 20117:00 amRNSProposed disposal of ENOR Spa
7th Dec 20113:27 pmRNSFurther re: Decision to withdraw from ENOR Spa
23rd Nov 20117:00 amRNSChange of Broker
19th Oct 20117:01 amRNSDecision to withdraw from ENOR Spa
19th Oct 20117:00 amRNSProduction Update Q3 2011
30th Sep 20117:00 amRNSHalf Yearly Report
29th Jul 20113:15 pmRNSTotal Voting Rights
15th Jul 20117:00 amRNSProduction Update for Q2 2011
1st Jul 20112:17 pmRNSLoan Stock 2012 Conversion
29th Jun 20114:37 pmRNSResult of AGM
22nd Jun 20119:34 amRNSExploration and Production Update
6th Jun 201110:31 amRNSFinal Results
31st May 201110:18 amRNSTotal Voting Rights
24th May 201111:12 amRNSLoan Stock 2012 Conversion
28th Apr 201110:20 amRNSTotal Voting Rights
20th Apr 20112:28 pmRNSHolding(s) in Company
20th Apr 201110:19 amRNSIssue of Equity
12th Apr 20114:29 pmRNSCorrection: Production and Exploration Update
12th Apr 20113:47 pmRNSProduction& Exploration Update
11th Mar 20117:00 amRNSExploration and Production Update
31st Jan 20119:04 amRNSTotal Voting Rights
25th Jan 20115:07 pmRNSHolding(s) in Company
20th Jan 20117:00 amRNSIssue of Equity
12th Jan 20117:00 amRNSProduction Update
21st Dec 20107:00 amRNSAppointment of Director & Grant of Options
17th Dec 20107:31 amRNSExploration Update and Assay Results
9th Nov 20107:00 amRNSExploration Update
29th Oct 20107:00 amRNSTotal Voting Rights

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.