George Frangeskides, Chairman at ALBA, explains why the Pilbara Lithium option ‘was too good to miss’. Watch the video here

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksKefi Gold Regulatory News (KEFI)

Share Price Information for Kefi Gold (KEFI)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 0.526
Bid: 0.528
Ask: 0.548
Change: -0.01 (-1.87%)
Spread: 0.02 (3.788%)
Open: 0.534
High: 0.534
Low: 0.512
Prev. Close: 0.536
KEFI Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Tulu Kapi Resource Update

8 Mar 2016 07:00

RNS Number : 3262R
KEFI Minerals plc
08 March 2016
 

8 March 2016

 

KEFI Minerals plc

("KEFI" or the "Company")

 

PRELIMINARY ECONOMIC ASSESSMENT OF TULU KAPI UNDERGROUND MINE

Potential to increase annual Tulu Kapi gold production to 150,000oz from open pit and underground

 

KEFI Minerals (AIM: KEFI), the gold exploration and development company with projects in the Kingdom of Saudi Arabia and the Federal Democratic Republic of Ethiopia, is pleased to report the positive results of the preliminary economic assessment (PEA) by KEFI of the underground mining potential at the Tulu Kapi Gold Project ("Tulu Kapi"), underneath the planned open pit.

 

As stated previously, the Board of KEFI continues to pursue its growth strategy of maintaining exploration activities in the Arabian-Nubian Shield focused on identifying the Company's next value-adding stages beyond the construction and start-up of the Tulu Kapi open pit. This PEA, which is a study of the resource potential at Tulu Kapi beneath the open pit mine, is the first stage in the implementation of that strategy. KEFI anticipates commencing development of the underground mine after Tulu Kapi has begun generating positive cash flows from the open pit mine and repaying its development finance, with a view to introducing underground production around the third year of the open pit operation.

 

Economic benefits to KEFI

This assessment indicates that the total production of Tulu Kapi (combining the open pit mine and underground mine) could approximate 150,000oz pa. This production capacity would result in aggregate net operating cash flow of c. US$100 million pa and KEFI's share of the estimated project NPV being US$150 million (£100 million) assuming a gold price of US$1,250/oz, an 8% discount rate applied against after tax cash flows and KEFI's beneficial ownership being 75%.

 

The estimated Tulu Kapi open pit cash flows (based on a gold price of US$1,250/oz), as confirmed by the independent technical experts for the Company's finance lenders for Tulu Kapi, project a cash build-up during the first three production years of US$135 million, which would be sufficient for the full repayment of project loans as well as the provision of returns to shareholders and the funding of the underground development (assuming it is triggered during that period).

 

Jeff Rayner, Exploration Director of KEFI Minerals, commented: "As we continue to make excellent progress on financing and preparing for the development of the Tulu Kapi open pit mine, we are pleased with the positive results of our preliminary economic assessment for the underground mine potential. When combined, the estimated total annual gold production increases to approximately 150,000oz. We expect the development of the underground mine to commence after the open pit has begun generating cash flow and repayment of development finance, and so it will increase the net operating cash flow of the project, thereby strengthening the economic potential of Tulu Kapi. We look forward to reporting progress on this, and other exploration targets that stand to leverage the Tulu Kapi infrastructure, in due course."

 

 

Highlights of Preliminary Economic Assessment for the Tulu Kapi Underground Mine:

· The Mineral Resources that are the subject of the PEA are, primarily, the deeper extensions of the high-grade core of the same orebody that will be developed for the Tulu Kapi open pit gold mine.

· The PEA of the underground mining potential indicates an estimated NPV of US$44 million at a gold price of US$1,250/oz, based on a preliminary underground mining study of the Indicated and Inferred Resources reported in August 2014 and utilising updated capital costs and operating costs estimated in February 2016.

· Combined with the NPV (at a gold price of US$1,250/oz) of the planned open pit, the total Tulu Kapi operation would have an estimated project NPV of US$200 million, all based on projected after tax cash flows at a discount rate of 8%. Assuming 75% project ownership after completion of project financing, KEFI's share of the NPV would be US$150 million.

· The PEA for the underground project is based on June 2014 (JORC-compliant) reported Indicated and Inferred Mineral Resource of 1.65 million tonnes at 6.26g/t Au for 330,000oz Au in-situ at a cut-off grade of 3.5g/t Au. The subsequent 2015 reported Mineral Resource focused only on the zones of mineralisation directly below the open pit and did not consider other drilled zones of mineralisation accessible from underground which were included in the 2014 reported Resource.

· Based on the latest interpretation, it is considered that there is exploration potential for tripling the current 330,000oz underground Mineral Resource to c. 1Moz.

· Modelling of mineable stopes resulted in a conversion rate of 76% of the resource to give potential reserves of 1.3Mt at 5.17g/t Au. A production rate of 325,000 tonnes pa for an initial four-year life of mine results in total recovered 206,000oz Au at a rate of c. 50,000oz Au pa, after accounting for dilution, ore losses and metallurgical recovery.

· Access would be via decline from the open pit. Mining would be mechanised on stopes designed for vertical thickness of 4m to 25m and larger widths. The lodes have been mapped up to 180 metres wide.

· Capital expenditure is estimated at US$37 million, cash operating cost at c. US$664/oz, AISC (All-in Sustaining Costs) at c. US$845/oz. Net operating cash flow is estimated at c. US$30 million pa.

· The IRR for the underground mine is estimated at 58% according to a base case scenario.

· As the final mine plan for the open pit indicates a core of eight years annual production averaging 115,000oz pa commencing in 2018, adding the contemplated underground mine would potentially increase annual production to over 165,000oz Au and aggregate net operating cash flow to US$96 million pa (US$66 million from the open pit and US$30 million from the underground mine, both processed in the Tulu Kapi processing plant, which would also require a relatively minor expansion programme).

· Mineralisation increases in grade and thickness with depth, and remains open at depth and +600-800m along strike to the north.

· The work sequence for this project would include an infill drilling programme on Inferred Resource and a limited confirmatory drilling programme on resource extensions, combined with the normal series of scoping, preliminary and definitive feasibility studies by KEFI's project planning team with independent expert confirmations as appropriate. Subject to the results of these studies, the potential underground development would be justified by the economics of the current reported resources, that the provision of underground access would enable the cost-effective expansion of resources and, in due course, the potential reserves from underground drilling and development.

· At present, the Company anticipates development commencing after Tulu Kapi has begun generating positive cash flows from the open pit and repaying its development finance, with a view to introducing underground production between year 2 and 4 of the open pit operation.

· An explanatory presentation has been made available on the Company's website entitled "Exploration and Development Upside: The Tulu Kapi Underground Project".

 

 

Enquiries

 

KEFI Minerals plc

Harry Anagnostaras-Adams (Executive Chairman)

Jeff Rayner (Exploration Director)

+357 99457843

+905 339281913

SP Angel Corporate Finance LLP (Nominated Adviser)

Ewan Leggat, Jeff Keating

+44 20 3470 0470

Brandon Hill Capital Ltd (Joint Broker)

Oliver Stansfield, Jonathan Evans

+44 20 3463 5000

 

Beaufort Securities Ltd (Joint Broker)

Elliot Hance

+44 20 7382 8300

Luther Pendragon Ltd (Financial PR)

Harry Chathli, Claire Norbury, Oli Hibberd

+44 207 618 9100

 

NOTES TO EDITOR

 

KEFI Minerals plc

 

KEFI is the operator of two advanced gold development projects within the highly prospective Arabian-Nubian Shield, with an attributable 1.93Moz (100% of Tulu Kapi's 1.72Moz and 40% of Jibal Qutman's 0.73Moz) gold Mineral Resources (JORC 2012) plus significant resource growth potential. KEFI targets that production at these projects generate cash flows for further exploration and expansion as warranted, recoupment of development costs and, when appropriate, dividends to shareholders.

 

KEFI Minerals in Ethiopia

 

Since the acquisition by KEFI in December 2013 of 75% (subsequently increased to 100%) of the Tulu Kapi Gold Project ("Tulu Kapi"), the Company has overhauled the project plans for the initial open pit:

· Expanded the Indicated Resource by 50%; completely and successfully overhauled the development and operating plan; completed several independent cycles of due diligence on the optimised plans; received full permitting for development and operation; signed a bilateral agreement with the Government of Ethiopia setting out the fiscal regime for life of mine; and installed the project construction management team, project contractors and the lead bank.

· In August 2015, KEFI published the 2015 Definitive Feasibility Study on the Tulu Kapi open pit project setting out capital requirements at US$176 million on an owner-operated basis, reduced from the US$289 million estimate of the previous owner.

· Subsequent refinements and the terms of appointment of the project contractors in October 2015 reduced this to a funding requirement of c. US$130 million, which has since been the focus of the financing syndicate with a view to striking an appropriate balance between risk-mitigation and equity dilution.

· Tulu Kapi's open pit annual gold production and All-in Sustaining Costs are estimated at c. 115,000oz pa and c. US$729/oz to US$757/oz at a gold price range of US$1,000/oz to US$1,400/oz, placing it in the most competitive quartile when measured against existing gold producers globally. 

· The project now has soundly-based robust economics and significant growth potential beyond the existing Ore Reserves estimate of 15.4Mt at 2.12g/t gold, containing 1.05Moz.

· KEFI is in the midst of assembling the development financing for Tulu Kapi and has published the findings of a Preliminary Economic Assessment on potentially developing an underground mine underneath the Tulu Kapi open pit, which would increase total production (an aggregate of the open pit and underground mine) to over 150,000oz pa.

 

KEFI Minerals in the Kingdom of Saudi Arabia

 

In 2009, KEFI formed Gold & Minerals Ltd ("G&M") in Saudi Arabia with local Saudi partner Abdul Rahman Saad Al-Rashid & Sons Company Ltd ("ARTAR"), to explore for gold and associated metals in the Arabian-Nubian Shield. KEFI has a 40% interest in G&M and is the operating partner. To date, G&M has conducted preliminary regional reconnaissance and has had five exploration licences ("ELs") granted, including Jibal Qutman and the more recently granted Hawiah EL that contains over 6km strike length of outcropping gossans developed on altered and mineralised rocks with all the hallmarks of a copper-gold-zinc VHMS deposit.

 

At Jibal Qutman, G&M's flagship project, Mineral Resources are estimated to total 28.4Mt at 0.80g/t gold for 733,045 contained ounces. The shallow oxide portion of this resource is being evaluated as a low capital expenditure heap-leach mine development.

 

ARTAR, on behalf of G&M, holds 24 EL applications that cover an area of approximately 1,484km2. ELs are renewable for up to three years and bestow the exclusive right to explore and to obtain a 30-year exploitation (mining) lease within the area.

 

Saudi Arabia has policies to encourage minerals exploration and development, and KEFI supports this priority by serving as the technical partner within G&M. ARTAR also serves this government policy as the major partner in G&M, which is one of the early movers in the modern resurgence of the Kingdom's minerals sector.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCAKODQBBKBNNK
Date   Source Headline
8th Apr 201612:14 pmRNSHolding(s) in Company 08.04.2016
7th Apr 20168:38 amRNSHolding(s) in Company
31st Mar 20168:27 amRNSTotal Voting Rights
22nd Mar 20167:00 amRNSConditional Placing to Raise £1.75 million
8th Mar 20167:00 amRNSTulu Kapi Resource Update
29th Feb 20167:00 amRNSTulu Kapi progress update
8th Feb 20167:00 amRNSKEFI Minerals presenting at Mining Indaba
3rd Feb 20167:00 amRNSSelection of Tulu Kapi preferred bankers
19th Jan 201610:36 amRNSGrant of Share Options
13th Jan 20167:00 amRNSTulu Kapi Development & Finance Plan Update
30th Dec 20157:00 amRNSFOURTH QUARTER 2015 OPERATIONAL UPDATE
14th Dec 201511:59 amRNSHolding(s) in Company
10th Dec 20157:05 amRNSResult of General Meeting & Completion of Placing
10th Dec 20157:02 amRNSChairman's General Meeting Statement
1st Dec 20158:58 amRNSHolding(s) in Company
24th Nov 201511:12 amRNSCONDITIONAL PLACING TO RAISE US$4 MILLION
13th Nov 20157:00 amRNSHolding(s) in Company
12th Nov 201510:33 amRNSUPDATED PRESENTATION ON WEBSITE
11th Nov 201512:03 pmRNSGovernment of Ethiopia to invest in Tulu Kapi
19th Oct 201511:28 amRNSHolding in Company
19th Oct 20157:00 amRNSTHIRD QUARTER 2015 OPERATIONAL UPDATE
14th Oct 20152:55 pmRNSHolding(s) in Company
14th Oct 20157:00 amRNSAPPOINTMENT OF PREFERRED MINING CONTRACTORS
13th Oct 20157:00 amRNSAPPOINTMENT OF PREFERRED PLANT CONTRACTOR
5th Oct 20157:00 amRNSPROGRESS AT JIBAL QUTMAN, SAUDI ARABIA
28th Sep 20157:00 amRNSTULU KAPI FUNDING UPDATE AND INTERIM RESULTS
9th Sep 20157:00 amRNSUPDATE ON TULU KAPI GOLD PROJECT FINANCING
7th Sep 20157:00 amRNSPLANNED PRODUCTION AT TULU KAPI EXPANDED BY 33%
28th Aug 20159:12 amRNSKEFI PRESENTING AT AFRICA DOWN UNDER CONFERENCE
21st Aug 20158:37 amRNSEdison initiates coverage on KEFI Minerals
17th Aug 20157:00 amRNSCONTRACTING AND FINANCING ON SCHEDULE
27th Jul 20157:27 amRNSDirector/PDMR Shareholding
17th Jul 20157:00 amRNSFINAL BIDDING TRIGGERED FOR PROJECT CONTRACTORS
2nd Jul 201511:12 amRNSDirector Share Purchase
1st Jul 20157:00 amRNSTotal Voting Rights
1st Jul 20157:00 amRNSSECOND QUARTER 2015 OPERATIONAL UPDATE
29th Jun 20158:57 amRNSKEFI PRESENTING AT MINING CAPITAL CONFERENCE
26th Jun 20157:00 amRNSMining Capital Conference & Quarterly Webinar
24th Jun 20157:00 amRNSCOMPLETION OF 2015 DFS & DEVELOPMENT FUNDING PLAN
22nd Jun 201511:08 amRNSHolding(s) in Company
16th Jun 20157:00 amRNSCONDITIONAL PLACING TO RAISE £2.9 MILLION
15th Jun 20154:30 pmRNSResult of AGM
15th Jun 20157:00 amRNSChairman's AGM Statement
4th Jun 20157:00 amRNSEXPLORATION UPDATE-LICENCES ADJACENT TO TULU KAPI
2nd Jun 20157:00 amRNS2015 DFS and Financing Update
29th May 201510:02 amRNSTotal Voting Rights
22nd May 20157:10 amRNSNotice of AGM, Annual Report & Adviser Appointment
20th May 20157:00 amRNSFINAL RESULTS FOR THE YEAR ENDED 31 DECEMBER 2014
11th May 20157:00 amRNSFINANCING UPDATE
6th May 20157:01 amRNSEXPLORATION UPDATE AT JIBAL QUTMAN, SAUDI ARABIA

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.