Update PFS Economic Study Delivers Increased NPV

9 Jul 2024 07:00

RNS Number : 5850V
Cadence Minerals PLC
09 July 2024
 

Cadence Minerals Plc

 

("Cadence Minerals", "Cadence", or "the Company")

 

Update PFS Level Economic Study Delivers an Increased Net Present Value of US$1.145 Billion

 

Cadence Minerals (AIM: KDNC) is pleased to announce the results from the updated economic study, the progress on the environmental applications and the ongoing development of the 67% 'Green Iron' processing flow sheet at the Amapá Ore Project ("Amapá", "Project" or "Amapá Project"). Since the end of March 2024, Cadence's total investment in the Amapá Project had increased by approximately US$0.7 million to approximately US$13.9 million, and consequently, the equity stake in the project now stands at 34.2%.

 

Highlights:

· 20% increase of Post-tax Net Present Value ("NPV") to US$1.14 billion at a discount rate of 10%, with profit after tax of US$3.14 billion over the Life of Mine ("LOM").

· 10% increase in average production after ramp-up to 5.82 million dry metric tonnes ("DMT") per annum ("Mtpa") of Fe concentrate, consisting of 4.81 Mtpa at 65.4% Fe and 1.01 Mtpa at 62% Fe concentrate.

· A 6% decrease in Free on Board ("FOB") C1 Cash Costs to US$33.5/dmt at the port of Santana. Cost and Freight ("CFR") C1 Cash Costs US$62.2/dmt in China.

· Improved Post-tax Internal Rate of Return from 34% to 42%.

· The port's environmental licensing is on schedule with the studies complete and the required reports being drafted, it is due to be submitted on schedule in the current quarter of this year.

· Testing of the 67% Fe "Green Iron" flow sheet has commenced, and results are expected by the end of September 2024.

· If successful, the 67% flow could increase the net operating profit of the Project, at full production, from approximately US$227 million to US$324 million per year.

 

Cadence CEO, Kiran Morzaria, commented: "On belhaf of our Board, I am thrilled with the positive outcomes from the updated economic study at the Amapá Ore Project, along with further he significant progress made at Amapá. The increased net present value of US$1.145 billion and the enhanced post-tax internal rate of return demonstrate substantial improvements to the Project's already robust economics.

 

The ongoing development of the 67% 'Green Iron' processing flow sheet and the Project's 100% renewable power source exemplify our commitment to propelling Amapa forward to meet the growing demand for low-carbon iron ore and steel, while at the same time demonstrating a potential 43% uplift in projected annual net operating profit.

 

We are optimistic about the potential of the Amapá Iron Ore Project and look forward to providing further updates on our progress in the future."

 

Updated PFS-level economic study

In March this year, the Amapa Project announced the results of the optimisation study, which delivered material capital savings to the Project. Based on these results, the Amapa Project carried out an updated PFS-level economic study.

 

Updated Mining Schedule

As part of the optimisation study completed in March 2024, the engineering consultants identified higher availability at the processing plant, which increased the annual run-of-mine feed rate to the processing plant. As a result of this, it was necessary to re-examine the mining and other related engineering disciplines, and in particular, the mine schedule had to be recalculated to optimise the project's NPV.

 

A life of mine production plan was scheduled using the Deswik.Blend® Scheduler Optimizer. The solids used in the mine scheduling were based on the final pit design, with an SMU (Selective Mining Unit) of 100 m x 200 m x 4 m. The life of mine schedule allows for 15 years of production with the current economic values and cut-off of 25% Fe. The resultant life of mine strip ratio is approximately 0.4:1 (tonnes waste: tonnes ore) and an average ore mine delivered to the plant of 13 million metric tonnes per annum.

 

Project Financial Analysis

An updated PFS financial model, which included the updated mining schedule, lower capex, and lower operational costs, was developed to evaluate the project's economics. All other aspects of the financial analysis remained the same as per the PFS published in January 2023, including the iron ore concentrate price. Which was a long-term average price for 62% iron ore concentrate of US$95/dmt and US$118.8/dmt for 65.4% iron ore concentrate, both quoted on a Cost and Freight ("CFR") basis. As of 8 July 2024 the 62% iron ore concentrate price was US$108.75/dmt and 65% iron ore fines was US$129/dmt. Summary results from the financial model outputs are presented in the tables below, including financial analysis. The financial model considers 100% equity funding for the Project, although, in reality, the financing of the Project will be a mix of debt and equity. However, the existing obligations in terms of principal repayment and current interest liabilities payable have been included in the financial model. A summary of the key financial information is presented below, alongside the 2022 PFS data.

 

Table 1.1 Key Project Metrics (100% project basis)

Metric

Unit

2022 PFS Data

2024 PFS Data

Total ore feed to the plant

Mt (dry)

176.88

176.93

Life of Mine

Years

16

15

Fe grade of ore feed to the plant

%

39.34

39.34

Recovery

%

76.27

76.27

62.0% iron ore concentrate production

Mtpa

0.89

0.95

65.4% iron ore concentrate production

Mtpa

4.23

4.51

C1 Cash Costs FOB *

US$/dmt

35.53

33.50

C1 Cash Costs CFR **

US$/dmt

64.23

52.20

Pre-Production capital investment***

US$M

399

343

Sustaining capital investment over LOM****

US$M

245

245

Post-tax NPV (10%)

US$M

949

1,145

Post-tax IRR

%

34

42

Project payback

Years

4

4

Total profit after tax (net operating profit)

US$B

2.96

3.14

 

Means operating cash costs, including mining, processing, geology, OHSE, rail, port and site G&A, divided by the tonnes of iron ore concentrate produced. It excludes royalties and is quoted on a FOB basis (excluding shipping to the customer).

**

Means the same as C1 Cash Costs FOB; however, it includes shipping to the customer in China (CFR).

***

Includes direct tax credit rebate over 48 months

****

Includes both sustaining CAPEX and deferred capital expenditure, specifically, improvements to the railway and the installation of conveyor belt and mine site to rail load out

 

Table 1.2 FOB and CFR average cash cost per tonne of dry product over the LOM

Cash Cost Per Discipline

PFS 2022

PFS 2024

 

US$/dmt

US$/dmt

Mine

17.05

16.73

TSF

0.08

0.08

Beneficiation Plant, Road / Conveyor Transfer & Rail Loading

12.43

10.94

Rail Freight

2.43

2.43

Port

1.55

1.55

G & A (5% total cost)

1.99

1.77

FOB Cash Costs

35.53

33.50

Marine Logistics

28.70

28.70

CFR Cash Costs

64.23

62.20

 

Table 1.3 Summary of key financial information for the Project.

Item Over Life of Mine

Unit

2022 PFS Data

2024 PFS Data

Gross revenue

US$M

9,387

9,389

Freight (Maine Logistics)

US$M

(2,350)

(2,351)

Net Revenue

US$M

7,037

7,038

Operating costs

US$M

(2,910)

(2,744)

Royalties and taxes (excluding income tax)

US$M

(373)

(373)

EBITDA

US$M

3,754

3,922

EBIT

US$M

3,315

3,547

Net Taxes and Interest

US$M

(355)

(390)

Net Operating Profit

US$M

2,960

3,144

Initial, Sustaining capital costs & repayments

US$M

(727)

(645)

Free Cash Flow

US$M

2,672

2,874

 

Item

Unit

2022 PFS Data

2024 PFS Data

LOM

Years

16

15

Discount rate

%

10

10

NPV

US$M

949

1,145

IRR

%

34

42

Project Payback

Years

4

4

 

Licensing

As announced in September 2023, Amapá Project Management had agreed with the Amapá State Environmental Agency ("SEMA") to an expedited environmental process, given the Project had previously been granted all its Operational Licenses ("LO").

 

SEMA is reviewing the application for the Installation License ("LI") for the mine and railway, which were submitted in March 2024. The the LI application for the wholly-owned port are nearing completion, with the final reports due for submission in the current quarter. Our understanding from SEMA is that based on the current timeline, the LI will be granted by the end of 2024. The LI allows the rehabilitation and construction of the Amapá Project, and once this is completed, the LO is granted, and mining operations can commence.

 

67% 'Green Iron' Flowsheet

The Amapá Project Management team continues to develop the 'green iron' flowsheet. Part of the work entails carrying out a mineralogical and multi-elemental analysis of run-of-mine ore, concentrate, and tailings and testing the full circuit at a pilot-scale level.

 

To this end, the Project has completed a life-of-mine sampling programme, collecting approximately two tonnes of material, which was shipped to our independent consultant engineers in March. The samples were shipped and cleared Chinese customs in late June. The samples have been checked and reconciled, and flow sheet testing results are expected by the end of the current quarter.

 

Assuming the testing confirms the flow sheet, we will update the project economics to reflect the increased revenue and any capital expenditure changes and update the market with these figures.

 

Project Financing

In October 2023, Cadence announced a memorandum of understanding ("MOU") to obtain debt financing for the Project. More information can be found in the announcement here. The MOU remains in place and our primary focus has been on securing the equity needed for the Project's construction.

 

We have signed several non-disclosure agreements in this regard, and interested parties have been and will be conducting technical site visits as part of their due diligence. The Project will need to have the necessary equity and debt in place to start construction. We will inform the markets if any definite agreements are made. In the meantime, Cadence plans to fund ongoing work, including the advancement of the 67% flow sheet, licensing, maintenance of the tailings storage facility, and general working capital for the Project.

 

About the Amapá Project and Cadence Ownership

The Amapá Project is a brownfield integrated iron ore project in the Amapá State of Brazil. It has Mineral Resources of 276 million tonnes (Mt) at 38.33% Iron (Fe) and Ore Reserves of 196 Mt at 39.34%. The Project comprises the mine, processing plant, wholly owned port and a 194km railway.

 

Since the end of March 2024, Cadence's total investment in the Amapá Project had increased by approximately US$0.7 million to approximately US$13.9 million, and consequently, the equity stake in the project now stands at 34.2%.

 

For further information contact:

 

Cadence Minerals plc

+44 (0) 20 3582 6636

Andrew Suckling

Kiran Morzaria

WH Ireland Limited (NOMAD & Broker)

+44 (0) 20 7220 1666

James Joyce

Darshan Patel

Isaac Hooper

Fortified Securities - Joint Broker

+44 (0) 20 3411 7773

Guy Wheatley

Brand Communications

+44 (0) 7976 431608

Public & Investor Relations

Alan Green

 

Qualified Person

Kiran Morzaria B.Eng. (ACSM), MBA, has reviewed and approved the information contained in this announcement. Kiran holds a Bachelor of Engineering (Industrial Geology) from the Camborne School of Mines and an MBA (Finance) from CASS Business School.

 

Cautionary and Forward-Looking Statements

Certain statements in this announcement are or may be considered forward-looking. Forward-looking statements are identified by their use of terms and phrases such as "believe", "could", "should", "envisage", "estimate", "intend", "may", "plan", "will", or the negative of those variations or comparable expressions including references to assumptions. These forward-looking statements are not based on historical facts but rather on the Directors' current expectations and assumptions regarding the company's future growth results of operations performance, future capital, and other expenditures (including the amount, nature, and sources of funding thereof) competitive advantages business prospects and opportunities. Such forward-looking statements reflect the Directors' current beliefs and assumptions and are based on information currently available to the Directors. Many factors could cause actual results to differ materially from the results discussed in the forward-looking statements, including risks associated with vulnerability to general economic and business conditions, competition, environmental and other regulatory changes actions by governmental authorities, the availability of capital markets reliance on crucial personnel uninsured and underinsured losses and other factors many of which are beyond the control of the company. Although any forward-looking statements contained in this announcement are based upon what the Directors believe to be reasonable assumptions. The company cannot assure investors that results will be consistent with such forward-looking statements.

 

The information contained within this announcement is deemed by the company to constitute Inside Information as stipulated under the Market Abuse Regulation (E.U.) No. 596/2014, as it forms part of U.K. domestic law under the European Union (Withdrawal) Act 2018, as amended. Upon the publication of this announcement via a regulatory information service, this information is considered to be in the public domain.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDEANXPEFKLEFA
Date   Source Headline
28th May 202611:15 amRNSAzteca Restart Update
19th May 20268:44 amRNSHolding(s) in Company
7th May 202610:36 amRNS-RCEO Interview on grant of Installation License
6th May 20265:32 pmRNSIssue of Options
5th May 20267:00 amRNSAmapá – Installation Licence Granted
2nd Apr 20268:00 amRNS-RInvestor Presentation via Investor Meet Company
2nd Apr 20267:05 amRNSIssue of shares to EBT and Total Voting Rights
2nd Apr 20267:00 amRNSAmapá Project Update - Licensing and Azteca
25th Mar 20267:00 amRNSSonora Lithium Project Arbitration Funding
13th Mar 20267:06 amRNSAmapá Project Update
13th Mar 20267:06 amRNSAmapá Project Update
9th Jan 202610:35 amRNS-RInvestor Presentation via Investor Meet Company
7th Jan 202610:32 amRNS-RCEO Interview on Amapá & Azteca Plant
6th Jan 20267:00 amRNSGrant of Preliminary Environmental Licence - Amapá
15th Dec 20257:00 amRNSAmapá Project Update
12th Dec 20257:00 amRNSAmapá Project Update
1st Dec 20257:00 amRNSExecution of Binding Prepayment Offtake Agreement
17th Nov 202511:09 amRNSUpdate on Offtake Financing for the Azteca Plant
6th Oct 20257:00 amRNSResult of Oversubscribed WRAP Retail Offer
3rd Oct 20251:41 pmRNSEarly Close of WRAP Retail Offer
2nd Oct 20257:00 amRNSWRAP Retail Offer for up to £200,000
30th Sep 20257:00 amRNSFunding Secured for Azteca Offtake Agreement
29th Sep 202511:38 amRNSInterim Results for six months ended 30 June 2025
29th Sep 202510:51 amRNSResult of General Meeting
12th Sep 202511:49 amRNSNotice of GM
10th Sep 20258:08 amRNS-RCEO interview on Funding & Azteca/Amapá Production
9th Sep 20257:00 amRNSCadence Signs Terms to Restart Azteca Plant
18th Aug 20257:00 amRNSSignificant Mining Cost Reduction at Amapá Project
6th Aug 20253:19 pmRNSResult of AGM
10th Jul 20252:42 pmRNSNotice of AGM
9th Jul 20252:45 pmRNSCorp Update - EG1 commences exploration at Leonora
8th Jul 202510:31 amRNSAdmission of Shares
1st Jul 20258:29 amRNS-RCEO Interview Regarding Amapa Developments
27th Jun 20251:36 pmRNSDirector Share Purchases
27th Jun 20257:00 amRNSAmapa Production Plan & Equity Subscription
18th Jun 20253:13 pmRNSAnnual Results for the year ended 31 December 2024
10th Jun 202511:59 amRNSAmapa Iron Ore Project Update
7th May 20254:33 pmRNSCorporate Update–retraction to EG1 acquire Leonora
6th May 20257:00 amRNSCorporate Update - EG1 acquires Leonora Goldfields
17th Jan 20258:47 amRNSIssue of Options
15th Jan 202510:24 amRNSEverGreen: LCT Pegmatite & Gold at Bynoe Project
17th Dec 20247:00 amRNSLOI to acquire Projects, £1m Fundraise & Updates
3rd Dec 20247:00 amRNSUpdated PFS Economic Study Delivers Increased NPV
26th Nov 20247:00 amRNSAmapa Iron Ore Project Update
18th Nov 20247:00 amRNSEverGreen – RC Drilling Commenced at Bynoe Project
29th Oct 20249:07 amRNSEverGreen – Spodumene Discovery at Bynoe Project
18th Oct 20242:55 pmRNSResults of AGM
17th Oct 20248:07 amRNSCorporate Update
27th Sep 20247:00 amRNSInterim Results
17th Sep 20247:00 amRNSAmapá Project Licensing on Schedule

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.