Pin to quick picksCadence Mineral Regulatory News (KDNC)

Share Price Information for Cadence Mineral (KDNC)

Share Price is delayed by 15 minutes
Get Live Data
6.50    0.00 (0.00%)
Bid:
0.00
Ask:
0.00
Spread: 1.00 (16.667%)
Market Cap: £26.60m
KDNC Live PriceLast checked at - London Stock Exchange

Intraday Cadence Mineral Share Chart

Significant Mining Cost Reduction at Amapá Project

18 Aug 2025 07:00

RNS Number : 6898V
Cadence Minerals PLC
18 August 2025
 

 

 

The company deems the information contained within this announcement to constitute Inside Information as stipulated under the Market Abuse Regulation (E.U.) No. 596/2014, as it forms part of U.K. domestic law under the European Union (Withdrawal) Act 2018, as amended. Upon the publication of this announcement via a regulatory information service, this information is considered to be in the public domain.

 

Cadence Minerals Plc

 

("Cadence Minerals", "Cadence", or "the Company")

 

Significant Mining Cost Reduction at the Amapá Iron Ore Project

 

Cadence Minerals (AIM: KDNC) is pleased to announce the results of a review into the mining costs of the Amapá Iron Ore Project ("Amapá", "Project" or "Amapá Project") in northern Brazil. The updated mining costs have materially reduced the overall Free on Board ("FOB") and Cost and Freight ("CFR") costs compared to those announced previously. Cadence holds a 35.1% equity interest in the Project.

 

Highlights:

· 36.7% Mining Cost Reduction: Mining costs reduced from US$17.65/DMT to US$11.17/DMT following re-quotation from one of Brazil's largest mining contractors.

· FOB Costs Down 19.2%: Overall FOB costs reduced from US$33.75/DMT to US$27.28/DMT.

· Major Annual Savings: Estimated cost savings of approximately US$33.3 million per annum.

· Life-of-Mine Benefit: Total savings of around US$500 million over the life of mine.

· CFR Cash Cost at US$55.46/DMT - Positions Amapá among some of the lowest cost producers.

 

Kiran Morzaria, CEO of Cadence Minerals, commented:

"These revised mining costs represent a major improvement in the economics of the Amapá Project. With a CFR cost base of just over US$55 per tonne, we believe Amapá is positioned among the lowest-cost iron ore operations globally."

 

"Importantly, these savings are based on the production plan for a premium DR-grade iron ore product, which is expected to capture higher market pricing than standard 62% Fe products. This combination of low costs and premium pricing potential delivers significant annual and life-of-mine savings, strengthens our competitiveness, and further de-risks the project as we progress towards development."

 

Mining Cost Reassessment

As part of our ongoing cost assessment, the Project identified that the mining costs quoted by a third-party provider were disproportionately high for this type of operation, given its low strip ratio and minimal blasting requirement (approximately 25% of total production). Earlier this year, we invited one of Brazil's largest mining contractors (the "Contractor") to re-quote based on the mining schedule and volumes used in the updated PFS published in December 2024.

 

Under the proposed arrangement, the Contractor will provide all necessary personnel, equipment, transport, accommodation, supplies, supervision, documentation, road works, fleet details, and organisational information. Amapá will provide the prepared worksite, utilities, meals, plans, schedules, licences, water, fuel, power, security, medical support, access to facilities, and all other necessary infrastructure to enable the Contractor to perform the works.

 

The revised costs are based on the planned production of a premium Direct Reduction ("DR") grade iron ore product, as outlined in previous Cadence announcements. DR-grade products typically attract a price premium in the seaborne iron ore market.

 

The quote specified the following main production equipment (Table 1). Total employees (direct and indirect) are estimated to be 283 personnel

 

Equipment

Number

Hydraulic Excavator HITACHI EX2500 (or similar)

3

Haul Truck Komatsu HD 785 (or similar)

18

Buldozer CATERPILLAR D9 (or similar)

5

Drill Rig Sandvik Pantera DP 1500i (or similar)

1

Wheel Loader CATERPILLAR 980 (or similar)

3

Hydraulic Excavator CAT 320 (or similar)

1

Hydraulic Excavator with Breaker (or similar)

1

Motor Grader CAT 16H (or similar)

3

Water Truck 30.000 l - Mercedes-Benz AXOR (or similar)

4

Ancillary Equipment

30

Table 1: Summary of Mining Equipment

 

Their quote has reduced the mining costs from US$17.65/ dry metric tonne ("DMT") to US$11.17 / DMT, with the overall FOB costs reducing from US$33.75 / DMT to US$27.28 / DMT (Table 2). This decreased cost base reduces the annual costs by US$33.3 million per annum, resulting in a total saving of US$500 million over the life of mine.

 

Cash Cost Per Discipline

Updated DR Grade PFS Dec 2024

Updated Costs (Mining) August 2025

 

US$/DMT

US$/DMT

Mine

17.65

11.17

TSF

0.09

0.09

Beneficiation Plant, Pipeline, Transfer & Rail Loading

10.50

10.50

Rail Freight

2.26

2.26

Port

1.52

1.52

G & A

1.74

1.74

FOB Cash Costs

33.75

27.28

Marine Logistics

28.18

28.18

CFR Cash Costs

61.93

55.46

Table 2 - Updated FOB and CRF Costs

 

Competitive Positioning

For context, major iron ore producers report CFR-equivalent costs broadly in the range of US$58-65/DMT. For example, Rio Tinto's Pilbara operations recorded 2024 unit cash costs of US$23-24.5/DMT FOB.[1], which, when adjusted for freight[2], equates to around US$58-60/DMT CFR. BHP's cost support range for iron ore is estimated at US$80-100/DMT CFR[3], while Vale's Northern System CFR costs are around US$60/DMT[4].

 

Against this backdrop, Amapá's updated CFR cash cost of US$55.46/DMT is well positioned in the global cost curve, offering a clear margin advantage over most major producers.

 

Mining Schedule

The mining schedule used in the cost reassessment is the same as that applied in the revised PFS published in December 2024. The annual feed rate ("ROM") is 13.99 Mtpa (wet base). Mine engineering and design were undertaken by Wardell Armstrong International at PFS level, incorporating an Ore Reserve Estimate prepared in accordance with the JORC Code (2012).

 

The Ore Reserve for Amapá is 195.8 million tonnes at an average grade of 39.34% Fe and a cut-off grade of 25% Fe. A Life of Mine ("LOM") production plan was scheduled using Deswik.Blend® Scheduler Optimiser based on the final pit design with a Selective Mining Unit of 100m x 200m x 4m. The LOM schedule supports 15 years of production, with a strip ratio of approximately 0.4:1 (waste:ore) and an average ore delivery to the plant of 13.99 Mtpa. A site plan of the pits and phases is outlined in Figure 1.

 

Figure 1 Open Pit Design Phases

 

Cadence Ownership

As of the end of June 2025, Cadence's total investment in the Amapá Project is approximately US$14.8 million, and its equity stake in the project stands at 35.1%.

 

About the Amapa Project

The Amapá Iron Ore Project is a fully integrated operation in Brazil, comprising established mine, rail, port, and beneficiation infrastructure. It hosts a JORC-compliant Mineral Resource of 276 million tonnes at 38% Fe and a Proven and Probable Ore Reserve of 195.8 million tonnes at 39.34% Fe. In December 2024, an updated Pre-Feasibility Study confirmed the Project's ability to produce a 67.5% Fe direct reduction (DR) grade concentrate at a rate of 5.5 Mtpa. The revised flowsheet and mine plan resulted in a post-tax NPV (10%) of US$1.97 billion over a 15-year mine life, with pre-production capital investment of US$377 million. Installation licence applications have been submitted, and once granted, will allow, subject to financing, the recommissioning of the Project.

 

For further information, contact:

 

Cadence Minerals plc

+44 (0) 20 3582 6636

Andrew Suckling

Kiran Morzaria

Zeus (NOMAD & Broker)

+44 (0) 20 3829 5000

James Joyce

Darshan Patel

Gabriella Zwarts

 

Fortified Securities - Joint Broker

+44 (0) 20 3411 7773

Guy Wheatley

Brand Communications

+44 (0) 7976 431608

Public & Investor Relations

Alan Green

 

Qualified Person

Kiran Morzaria B.Eng. (ACSM), MBA, has reviewed and approved the information contained in this announcement. Kiran holds a Bachelor of Engineering (Industrial Geology) from the Camborne School of Mines and an MBA (Finance) from CASS Business School.

 

Cautionary and Forward-Looking Statements

Certain statements in this announcement are or may be considered forward-looking. Forward-looking statements are identified by their use of terms and phrases such as "believe", "could", "should", "envisage", "estimate", "intend", "may", "plan", "will", or the negative of those variations or comparable expressions, including references to assumptions. These forward-looking statements are not based on historical facts but rather on the Directors' current expectations and assumptions regarding the company's future growth, results of operations, performance, future capital, and other expenditures (including the amount, nature, and sources of funding thereof), competitive advantages, business prospects and opportunities. Such forward-looking statements reflect the Directors' current beliefs and assumptions and are based on information currently available to the Directors. Many factors could cause actual results to differ materially from the results discussed in the forward-looking statements, including risks associated with vulnerability to general economic and business conditions, competition, environmental and other regulatory changes actions by governmental authorities, the availability of capital markets reliance on crucial personnel uninsured and underinsured losses and other factors many of which are beyond the control of the company. Although any forward-looking statements contained in this announcement are based upon what the Directors believe to be reasonable assumptions. The company cannot assure investors that results will be consistent with such forward-looking statements.

 


[1] Rio Tinto - 2024 unit cash costs (Pilbara, FOB, US$/wmt): https://docs.publicnow.com/viewDoc.aspx?filename=38005%5CEXT%5C7D1C3296E9201932463FECF59F2BB06A0A31A898_10EC183AC157CD9D0ADE0635BEA9959D58927997.PDF

[2] Capesize freight, Port Hedland → Qingdao, examples ~US$10-12/t (June 2024), PDF: https://www.hellenicshippingnews.com/wp-content/uploads/2024/06/Bancosta-Weekly-2024-22.pdf

[3]  BHP - WAIO C1 unit costs (FY24/FY25e), PDF: https://www.bhp.com/-/media/documents/media/reports-and-presentations/2024/240827_bhpresultsfortheyearended30june2024.pdf

[4]  Vale - 2024 C1 cash cost guidance (US$/t dmt), PDF: https://www.latibex.com/docs/Documentos/esp/hechosrelev/2024/Vale%27s%20Performance%20in%203Q24.pdf

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
MSCPRMLTMTTBBLA
Date   Source Headline
17th Jun 20267:00 amRNSAzteca Execution Update
28th May 202611:15 amRNSAzteca Restart Update
19th May 20268:44 amRNSHolding(s) in Company
7th May 202610:36 amRNS-RCEO Interview on grant of Installation License
6th May 20265:32 pmRNSIssue of Options
5th May 20267:00 amRNSAmapá – Installation Licence Granted
2nd Apr 20268:00 amRNS-RInvestor Presentation via Investor Meet Company
2nd Apr 20267:05 amRNSIssue of shares to EBT and Total Voting Rights
2nd Apr 20267:00 amRNSAmapá Project Update - Licensing and Azteca
25th Mar 20267:00 amRNSSonora Lithium Project Arbitration Funding
13th Mar 20267:06 amRNSAmapá Project Update
13th Mar 20267:06 amRNSAmapá Project Update
9th Jan 202610:35 amRNS-RInvestor Presentation via Investor Meet Company
7th Jan 202610:32 amRNS-RCEO Interview on Amapá & Azteca Plant
6th Jan 20267:00 amRNSGrant of Preliminary Environmental Licence - Amapá
15th Dec 20257:00 amRNSAmapá Project Update
12th Dec 20257:00 amRNSAmapá Project Update
1st Dec 20257:00 amRNSExecution of Binding Prepayment Offtake Agreement
17th Nov 202511:09 amRNSUpdate on Offtake Financing for the Azteca Plant
6th Oct 20257:00 amRNSResult of Oversubscribed WRAP Retail Offer
3rd Oct 20251:41 pmRNSEarly Close of WRAP Retail Offer
2nd Oct 20257:00 amRNSWRAP Retail Offer for up to £200,000
30th Sep 20257:00 amRNSFunding Secured for Azteca Offtake Agreement
29th Sep 202511:38 amRNSInterim Results for six months ended 30 June 2025
29th Sep 202510:51 amRNSResult of General Meeting
12th Sep 202511:49 amRNSNotice of GM
10th Sep 20258:08 amRNS-RCEO interview on Funding & Azteca/Amapá Production
9th Sep 20257:00 amRNSCadence Signs Terms to Restart Azteca Plant
18th Aug 20257:00 amRNSSignificant Mining Cost Reduction at Amapá Project
6th Aug 20253:19 pmRNSResult of AGM
10th Jul 20252:42 pmRNSNotice of AGM
9th Jul 20252:45 pmRNSCorp Update - EG1 commences exploration at Leonora
8th Jul 202510:31 amRNSAdmission of Shares
1st Jul 20258:29 amRNS-RCEO Interview Regarding Amapa Developments
27th Jun 20251:36 pmRNSDirector Share Purchases
27th Jun 20257:00 amRNSAmapa Production Plan & Equity Subscription
18th Jun 20253:13 pmRNSAnnual Results for the year ended 31 December 2024
10th Jun 202511:59 amRNSAmapa Iron Ore Project Update
7th May 20254:33 pmRNSCorporate Update–retraction to EG1 acquire Leonora
6th May 20257:00 amRNSCorporate Update - EG1 acquires Leonora Goldfields
17th Jan 20258:47 amRNSIssue of Options
15th Jan 202510:24 amRNSEverGreen: LCT Pegmatite & Gold at Bynoe Project
17th Dec 20247:00 amRNSLOI to acquire Projects, £1m Fundraise & Updates
3rd Dec 20247:00 amRNSUpdated PFS Economic Study Delivers Increased NPV
26th Nov 20247:00 amRNSAmapa Iron Ore Project Update
18th Nov 20247:00 amRNSEverGreen – RC Drilling Commenced at Bynoe Project
29th Oct 20249:07 amRNSEverGreen – Spodumene Discovery at Bynoe Project
18th Oct 20242:55 pmRNSResults of AGM
17th Oct 20248:07 amRNSCorporate Update
27th Sep 20247:00 amRNSInterim Results