Tjate resource statement

4 Jun 2009 10:30

RNS Number : 3559T
Jubilee Platinum PLC
04 June 2009
 



Jubilee Platinum plc ("Jubilee") 

4 June 2009

AIM: JLP

JSE: JBL

Registration number: 4459850

ISIN GB0031852162

Jubilee Announces Completion Of An Independent SAMREC Compliant Mineral Resource Statement On Its Flagship Tjate Project In South Africa.

Jubilee is pleased to announce the results of a recently completed independent SAMREC compliant mineral resource statement by The Mineral Corporation Ltd for the "First mine" area on its 63owned flagship Tjate project in the eastern Bushveld of South Africa. 

Highlights

"First mine" Mineral Resource estimate area shows a combined Indicated and Inferred Mineral Resource of 132.5 million tonnes (after geological losses) of the Merensky and UG2 Reefs at a combined Indicated and Inferred grade of 5.24g/t 3PGE+Au (platinum palladium rhodium and gold) containing 22 million oz 3PGE+Au and at an inferred grade of 5.94 g/t 6PGE*+Au (platinum, palladium, rhodium, iridium, ruthenium, osmium and goldthis area contains 25 million oz 6PGE+Au. This is based on the completion of 42 boreholes containing 154 reef intersections over the "First mine" target area. 

This area contains two coherent widely mineralised Merensky Reef sub-areas that have on average a 3PGE+Au grade of 5.39g/t over an average width of 1.46m. The block widths vary from 1.16 m to 1.71m and have grades in excess of 5.0g/t 3PGE+Au. These widely mineralised Merensky reef areas represent 18% of the Merensky reef tonnage and 21% of the 3PGE+Au.

 

Based on the boreholes drilled and the First mine resource data, the company believes an exploration target of some 368 million tonnes (before geological losses) containing 70 million oz 6PGE+Au is possible for the three farms of the Tjate project.

The company calculates an attributable value at prevailing market prices of US$30 billion to the aforementioned possible metal, for which the viability of its recovery has yet to be established in future studies as the project develops,

The company is progressing the bankable feasibility study of the First mine and the above mentioned resource estimate is a key step in this process.

* All figures that include ruthenium, iridium and osmium (in addition to 3PGE+AU) are in Inferred Mineral Resource category

The Mineral Resource Statement completed by The Mineral Corporation for the Merensky and UG2 Reefs is SAMREC compliant and is provided appended to this announcement.

Colin Bird, CEO of Jubilee and Tjate said: "This is a major advance for the Tjate project and confirms the statements made by management and the board over the last four years that Tjate represents a major PGE resource that as yet has not been developed. These results give Jubilee the confidence to proceed to feasibility study and if appropriate development."

Chris Molefe, Chairman of Tjate said: "I am delighted with the results, which highlight this large eastern Bushveld resource. I compliment the project team on their diligence and focus in bringing this resource together" 

The results of the resource statement indicate that the Merensky reef resource is of a size and grade that could possibly provide a stand alone resource to sustain a projected 20-year life of mine treating 200,000 tonnes per month and producing approximately 320,000 oz 3PGE+Au annually.

 

Geo-Consult International (Pty) Ltd, geological advisers and exploration manager for the Tjate project commented that on the basis of the aforementioned compliant mineral resource statement, estimated over some 40-45% of the project area and their overall understanding of the geology of the Merensky and UG2 Reefs, that it is reasonable to assume that these reefs are possibly developed across the full extent of the project area, albeit with the balance being down-dip of the current resource estimate area.

On this assumption, the company believes that the three farms, which measure some 51 square kilometres, could potentially represent an exploration target of up to 52 million oz 3PGE+Au (59 million oz 6PGE+Au) - after geological losses - (before geological losses approximately 62 Moz 3PGE+Au or 70 Moz 6PGE+Au), for which the viability of recovery the company has yet to establish in future studies as the project develops.

Accordingly, the company believes the total three farms could possibly contain an attributable 44 million oz 6PGE+Au (before geological losses), the gross metal value of which the company calculates at approximately US$30 billion, using current market prices of around US$1,200/oz Pt, US$200/oz Pd, US$1,450/oz Rh, US$400/oz Ir, US$90/oz Ru and US$900/oz Au.

Andrew Sarosi, Technical Director of Jubilee Platinum, who holds a B.Sc Metallurgy and M.Sc Engineering, University of Witwatersrand and is a member of The Institute of Materials, Minerals and Mining, has approved this release.

Notes to editors

The Tjate Project comprises three contiguous farms, totalling 5,143 hectares in the eastern Bushveld: Dsjate, Fernkloof and Quartz Hill. The farms are downdip of Impala Platinum's operating Marula platinum mine and Anglo Platinum's developing Twickenham platinum mine. Jubilee is advancing the Project to feasibility study.

For further information please contact: 

Colin Bird Suzanne Johnson-Walsh

Jubilee Platinum plc Bishopsgate Communications Ltd 

Tel +44 (0) 20 7584 2155 Tel +44 (0) 20 7562 3350 

Andrew Sarosi Brian Chistie/Leonard Eiser

Jubilee Platinum plc  Sasfin Capital

Tel +44 (0) 1752 221937  Tel +27 (0) 11 809 7500

Matthew Robinson/Rose Herbert Dennis Tucker

FinnCap Qinisele Resources

Tel +44 (0) 20 7600 1658 Tel +27 (0) 82 492 4957

  Table  Tjate First mine mineral resource estimate (after 16% and 20%

geological losses for Merensky and UG2 reefs respectively)

Merensky Reef

Inferred Mineral Resources

Total MR

 

Resource Tonnes 

Width (m)

3PGE+Au (g/t)

3PGE+Au (Mozs)

Ni (%)

Cu (%)

6PGE+Au (g/t)

6PGE+Au (Mozs)

 

 

 56,273,224 

1.10

4.66

8.429

0.17

0.10

4.90

8.858

Mineral Resources by Classification

 

 

 

 

Classification

Resource Tonnes

Width (m)

3PGE+Au (g/t)

3PGE+Au (MOzs)

Ni (%)

Cu (%)

6PGE+Au (g/t)

6PGE+Au (Mozs)

Indicated

 6,759,711 

1.01

4.85

1.055

0.18

0.11

5.10

1.108

Inferred

 49,513,514 

1.11

4.63

7.374

0.17

0.10

4.86

7.750

Mineral Resources by Farm and classification

 

 

 

 

Farm

Classification

Resource Tonnes 

Width (m)

3PGE+Au (g/t)

3PGE+Au (MOzs)

Ni (%)

Cu (%)

6PGE+Au (g/t)

6PGE+Au (Mozs)

Dsjate 

Indicated

 6,759,711 

1.01

4.85

1.055

0.18

0.11

5.10

1.108

Dsjate

Inferred

 43,252,250 

1.12

4.66

6.479

0.12

0.10

4.89

6.809

Fernkloof

Inferred

 6,261,264 

1.02

4.45

0.896

0.10

0.10

4.67

0.941

UG2 Reef

Inferred Mineral Resources

Total UG2

 

Resource Tonnes 

Width (m)

3PGE+Au (g/t)

3PGE+Au (MOzs)

Ni (%)

Cu (%)

6PGE+Au (g/t)

6PGE+Au (Mozs)

 

 

 76,207,268 

1.24

5.67

13.900

0.06

0.03

6.69

16.432

Mineral Resources by Classification

 

 

 

 

Classification

Resource Tonnes 

Width (m)

3PGE+Au (g/t)

3PGE+Au (MOzs)

Ni (%)

Cu (%)

6PGE+Au (g/t)

6PGE+Au (Mozs)

Indicated

 4,801,649 

1.10

5.89

0.910

0.06

0.03

6.95

1.075

Inferred

 71,405,620 

1.25

5.66

12.990

0.06

0.03

6.68

15.357

Mineral Resources by Farm and Classification 

 

 

 

 

Farm

Classification

Resource Tonnes 

Width (m)

3PGE+Au (g/t)

3PGE+Au (MOzs)

Ni (%)

Cu (%)

6PGE+Au (g/t)

6PGE+Au (Mozs)

Dsjate

Indicated

 4,801,649 

1.10

5.89

0.910

0.06

0.03

6.95

1.075

Dsjate

Inferred

 63,706,060 

1.24

5.66

11.586

0.06

0.03

6.67

13.696

Fernkloof

Inferred

 7,699,560 

1.32

5.67

1.405

0.06

0.03

6.70

1.661

Total Merensky and UG2

Inferred Mineral Resources

 

 

Resource Tonnes

Width (m)

3PGE+Au (g/t)

3PGE+Au (MOzs)

Ni (%)

Cu (%)

6PGE+Au (g/t)

6PGE+Au (Mozs)

 

 132,480,493 

1.18

5.24

22.329

0.11

0.00

5.93

25.291

Mineral Resources by Classification

 

 

 

 

Classification

Resource Tonnes

Width (m)

3PGE+Au (g/t)

3PGE+Au (MOzs)

Ni (%)

Cu (%)

6PGE+Au (g/t)

6PGE+Au (Mozs)

Indicated

 11,561,359 

1.05

5.28

1.964

0.13

0.08

5.87

2.184

Inferred

 120,919,133 

1.19

5.24

20.365

0.11

0.06

5.93

23.107

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCIIFLARLISIIA
Date   Source Headline
6th Aug 20207:00 amRNSFurther Copper Tailings Resource Secured in Zambia
13th Jul 20207:00 amRNSSix Month Operations Update
18th Jun 20207:00 amRNSLarge Copper Tailings Resources in Zambia Secured
19th May 202011:30 amRNSRelocation of chrome plant to maximise earnings
7th May 20202:00 pmRNSOperations Update in South Africa and Zambia
17th Apr 20209:15 amRNSUpdate: Operations during lockdown in South Africa
26th Mar 202010:10 amRNSUnaudited interim results
24th Mar 202011:33 amRNSSOUTH AFRICAN 21-DAY LOCKDOWN UPDATE
23rd Mar 20204:41 pmRNSSecond Price Monitoring Extn
23rd Mar 20204:37 pmRNSPrice Monitoring Extension
20th Mar 20204:47 pmRNSSecond Price Monitoring Extn
20th Mar 20204:42 pmRNSPrice Monitoring Extension
20th Mar 20202:05 pmRNSSecond Price Monitoring Extn
20th Mar 20202:00 pmRNSPrice Monitoring Extension
16th Mar 20204:42 pmRNSSecond Price Monitoring Extn
16th Mar 20204:37 pmRNSPrice Monitoring Extension
21st Feb 202010:10 amRNSDirector Dealing
28th Jan 20208:15 amRNSSix Monthly Operations Update
6th Dec 201912:45 pmRNSResults of AGM
3rd Dec 20197:00 amRNSDirector Dealing
25th Nov 20192:24 pmRNSTR-1: notification of major holdings
14th Nov 20191:15 pmRNSEquity Placing to Support Targeted Growth
14th Nov 20197:36 amRNSResults for year ended 30 June 2019 & AGM Notice
5th Nov 20198:30 amRNSAcquisition of all chrome rights at Hernic
24th Oct 20193:11 pmRNSAcquisition at Hernic: Transforming Operations
24th Sep 20197:00 amRNSNew Corporate Presentation
17th Sep 20197:00 amRNSKabwe Multi-Metal Processing Project Update
5th Sep 20198:00 amRNSWindsor PGM Project - Full Operational Status
23rd Aug 201910:15 amRNSCompletion of Acquisition in Kabwe & Joint Broker
5th Aug 20199:00 amRNSSix Monthly Operations Update
11th Jul 20197:00 amRNSProjects Update
5th Jun 20191:45 pmRNSProjects Update
9th May 20197:00 amRNSQuarterly Operations Update Q1 2019
3rd May 201912:30 pmRNSTR-1: notification of major holdings
23rd Apr 20197:00 amRNSPrice Monitoring Extension
5th Apr 20192:05 pmRNSSecond Price Monitoring Extn
5th Apr 20192:00 pmRNSPrice Monitoring Extension
4th Apr 20194:41 pmRNSTR-1: notification of major holdings
3rd Apr 20192:26 pmRNSTR-1 NOTIFICATION OF CHANGE IN MAJOR HOLDINGS
2nd Apr 20194:40 pmRNSSecond Price Monitoring Extn
2nd Apr 20194:35 pmRNSPrice Monitoring Extension
29th Mar 20191:35 pmRNSVoting Rights and Capital
29th Mar 201910:38 amRNSTR-1: Form for notification of major holdings
28th Mar 20197:00 amRNSUnaudited interim results
21st Mar 201910:58 amRNSFunding secured for Kabwe Project and Acquisition
20th Mar 20194:18 pmRNSGeneral Operations and Projects Update
17th Jan 20198:30 amRNSQuarterly Operations Update Q4 2018
18th Dec 201812:38 pmRNSTR-1: Notification of major holdings
18th Dec 20188:30 amRNSTR-1: notification of major holdings
17th Dec 20187:00 amRNSCommissioning of fine chrome operation commences

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.