Roan Upgrade Project Commences Operations

8 Aug 2024 07:30

RNS Number : 6345Z
Jubilee Metals Group PLC
08 August 2024
 

Jubilee Metals Group PLC

Registration number (4459850)

AIM share code: JLP

Altx share code: JBL

ISIN: GB0031852162

("Jubilee" or "the Company" or "the Group")

 

 

Dissemination of a Regulatory Announcement that contains inside information according to UK Market Abuse Regulations. Not for release, publication or distribution in whole or in part in, into or from any jurisdiction where to do so would constitute a violation of the relevant laws or regulations of such jurisdiction.

Roan Upgrade Project Commences Operations

Jubilee, a diversified metals producer with operations in South Africa and Zambia, is pleased to announce the commencement of operations at its Roan Upgrade project in Zambia. The commencement of the newly constructed front-end section of the Roan operation adds additional processing capacity and flexibility to the already operating Roan milling and flotation sections. 

Highlights

· Jubilee commences operations at its newly constructed Roan front-end upgrade project.

· Roan's new front-end capacity has been constructed adjacent to the already operating milling and flotation circuits increasing the overall capacity of Roan to a maximum design of 13 000 tonnes of copper per annum (tpa).

· The Roan front-end upgrade forms part of Jubilee's overall operational capacity increase strategy which includes the Sable refinery upgrade project currently underway, targeting to reach a combined processing capacity of 25 000tpa of copper over the coming 12 months.

Leon Coetzer, CEO commented:

"We are proud to announce that the Roan front-end module upgrade project in Zambia has commenced production ramp-up of previously mined material, which has been upgraded at source, prior to producing a saleable copper concentrate at Roan.

It has taken a concerted effort by the team to reach this critical point in the ramp-up of the Roan Upgrade project. I look forward to the team completing an accelerated ramp-up of operations during the coming month.

The upgraded Roan, together with our Sable refinery, offers Jubilee tremendous processing flexibility and affords us the unique opportunity to aggressively pursue copper resources that are unlocked by this capability."

Zambian Copper Strategy

Jubilee's copper strategy is enabled by Jubilee's proven ability to extract value from materials often regarded by the industry as either waste or too complex to extract economically through the traditional methods.

The targeted copper resources are classed into three groups namely:

§ Previously Processed Material (includes tailings, partially processed discarded low-grade materials)

§ Previously Mined Material (includes historically stockpiled low grade mined material, over burden rock, such as the previously announced Waste Rock Project transaction)

§ Open-pit Mining of near surface copper reef (such as the previously announced Munkoyo operation and Project G)

All three categories are held in vast quantities within Zambia, offering Jubilee the opportunity to further upscale its operations through targeted acquisitions of these resources. Jubilee has actively pursued the three material classes to grow its copper resource portfolio as an enabler to drive the expansion of its processing operational footprint in Zambia. The success in securing these targeted resources has afforded Jubilee the opportunity to transition Sable into a dedicated refiner for the processing of Open-pit Mining operations such as the recently announced Munkoyo operation, while the upgraded Roan will process predominantly Previously Mined and Processed Material. 

At completion, an expanded Sable and Roan will operate as independent operations. Once Sable is at full capacity supplied by Open-pit Mining operations, Roan can sell excess concentrate in the open market. The Company is reviewing the option of expanding the Roan operation to incorporate downstream refining of its concentrate depending on capital allocation. The targeted combined processing capacity of approximately 25 000tpa of copper, is achieved by an expanded Sable at 16 000tpa in addition to Roan's expanded capacity.

Roan Upgrade

Following the release on 24 June 2024 announcing civil and mechanical completion on the upgrade and expansion of Roan (Roan Upgrade), the electrical control system (ECS) has now also been successfully installed and commissioned, allowing for the ramp up of production to commence.

The Jubilee team has begun with the feeding of Previously Mined Material into Roan. The material is upgraded at source before being transported to Roan where a saleable copper concentrate is produced. The copper concentrate will initially be refined to copper cathode at Sable until such time that Sable's capacity is fully committed to the Open-pit mined material from Munkoyo and Project G whereafter the Roan concentrate will be traded on the open market.

This Roan Upgrade provides additional processing capacity complementing the existing sulphide copper concentrate capacity at Roan to a combined maximum design capacity of 13 000tpa of copper depending on the copper feed grades.

Website Updates

For more information about the sources of feed processed by Jubilee in Zambia, please refer to the presentation uploaded on our website. Furthermore, a second video of Project Munkoyo has been uploaded on the website showcasing the commencement of mining operations and the establishment of facilities during July 2024.

8 August 2024

**ENDS**

For further information visit www.jubileemetalsgroup.com, follow Jubilee on Twitter (@Jubilee_Metals) or contact:

Jubilee Metals Group PLC 

Leon Coetzer (CEO) / Neal Reynolds (CFO)

Tel: +27 (0) 11 465 1913 

 

Nominated Adviser - SPARK Advisory Partners Limited 

Andrew Emmott/James Keeshan 

Tel: +44 (0) 20 3368 3555 

 

PR & IR Adviser - Tavistock 

Jos Simson/ Gareth Tredway

Tel: +44 (0) 207 920 3150 

 

Joint Broker - RBC Capital Markets

Farid Dadashev/Jamil Miah

Tel +44 (0) 20 7653 4000

 

Joint Broker - Zeus Capital

Harry Ansell/Katy Mitchell  

Tel: +44 (0) 20 7220 1670/+44 (0) 113 394 6618 

 

JSE Sponsor - Questco Corporate Advisory Proprietary Limited 

Alison McLaren

Tel: +27 (0)11 011 9207

 

About Jubilee

Jubilee is a low-cost, diversified producer, specialising in the recovery of metal from previously overlooked resources, such as unprocessed historical waste rock, run-of-mine materials and tailings in South Africa and Zambia. The Company's low-capex, modular processing facilities are deployed close to these various types of material, producing high grade concentrates for sale or further refining to finished metal at the Company's downstream facilities. Production currently consists of copper, chrome and platinum group metals (PGMs). The modular processing facilities offer a platform for growth and the rapid expansion of its operational footprint. Jubilee's success is derived from operational excellence, a highly experienced management team and a pioneering Technical Development Centre.

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
MSCUBRRRSKUWRUR
Date   Source Headline
6th Aug 20207:00 amRNSFurther Copper Tailings Resource Secured in Zambia
13th Jul 20207:00 amRNSSix Month Operations Update
18th Jun 20207:00 amRNSLarge Copper Tailings Resources in Zambia Secured
19th May 202011:30 amRNSRelocation of chrome plant to maximise earnings
7th May 20202:00 pmRNSOperations Update in South Africa and Zambia
17th Apr 20209:15 amRNSUpdate: Operations during lockdown in South Africa
26th Mar 202010:10 amRNSUnaudited interim results
24th Mar 202011:33 amRNSSOUTH AFRICAN 21-DAY LOCKDOWN UPDATE
23rd Mar 20204:41 pmRNSSecond Price Monitoring Extn
23rd Mar 20204:37 pmRNSPrice Monitoring Extension
20th Mar 20204:47 pmRNSSecond Price Monitoring Extn
20th Mar 20204:42 pmRNSPrice Monitoring Extension
20th Mar 20202:05 pmRNSSecond Price Monitoring Extn
20th Mar 20202:00 pmRNSPrice Monitoring Extension
16th Mar 20204:42 pmRNSSecond Price Monitoring Extn
16th Mar 20204:37 pmRNSPrice Monitoring Extension
21st Feb 202010:10 amRNSDirector Dealing
28th Jan 20208:15 amRNSSix Monthly Operations Update
6th Dec 201912:45 pmRNSResults of AGM
3rd Dec 20197:00 amRNSDirector Dealing
25th Nov 20192:24 pmRNSTR-1: notification of major holdings
14th Nov 20191:15 pmRNSEquity Placing to Support Targeted Growth
14th Nov 20197:36 amRNSResults for year ended 30 June 2019 & AGM Notice
5th Nov 20198:30 amRNSAcquisition of all chrome rights at Hernic
24th Oct 20193:11 pmRNSAcquisition at Hernic: Transforming Operations
24th Sep 20197:00 amRNSNew Corporate Presentation
17th Sep 20197:00 amRNSKabwe Multi-Metal Processing Project Update
5th Sep 20198:00 amRNSWindsor PGM Project - Full Operational Status
23rd Aug 201910:15 amRNSCompletion of Acquisition in Kabwe & Joint Broker
5th Aug 20199:00 amRNSSix Monthly Operations Update
11th Jul 20197:00 amRNSProjects Update
5th Jun 20191:45 pmRNSProjects Update
9th May 20197:00 amRNSQuarterly Operations Update Q1 2019
3rd May 201912:30 pmRNSTR-1: notification of major holdings
23rd Apr 20197:00 amRNSPrice Monitoring Extension
5th Apr 20192:05 pmRNSSecond Price Monitoring Extn
5th Apr 20192:00 pmRNSPrice Monitoring Extension
4th Apr 20194:41 pmRNSTR-1: notification of major holdings
3rd Apr 20192:26 pmRNSTR-1 NOTIFICATION OF CHANGE IN MAJOR HOLDINGS
2nd Apr 20194:40 pmRNSSecond Price Monitoring Extn
2nd Apr 20194:35 pmRNSPrice Monitoring Extension
29th Mar 20191:35 pmRNSVoting Rights and Capital
29th Mar 201910:38 amRNSTR-1: Form for notification of major holdings
28th Mar 20197:00 amRNSUnaudited interim results
21st Mar 201910:58 amRNSFunding secured for Kabwe Project and Acquisition
20th Mar 20194:18 pmRNSGeneral Operations and Projects Update
17th Jan 20198:30 amRNSQuarterly Operations Update Q4 2018
18th Dec 201812:38 pmRNSTR-1: Notification of major holdings
18th Dec 20188:30 amRNSTR-1: notification of major holdings
17th Dec 20187:00 amRNSCommissioning of fine chrome operation commences

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.