Projects Status Update

7 Jun 2018 07:00

RNS Number : 5732Q
Jubilee Metals Group PLC
07 June 2018
 

Jubilee Metals Group PLC

Registration number (4459850)

AltX share code: JBL

AIM share code: JLP

ISIN: GB0031852162

("Jubilee" or "the Company")

 

Projects Status Update

 

Projects Highlights

 

· Hernic project achieves record production of 2 101 PGM* ounces for the month of May with Q2 2018 already touching 4 000 PGM ounces in the first two months

· First PGM material from PlatCro targeted for delivery to Northam in June 2018

· Construction of Kabwe project underway with initial focus on the zinc leach circuit

· Implementation of the fine chrome recovery circuit at DCM underway

* 6 Element Platinum Group Metals

 

Leon Coetzer, Chief Executive Officer, says: "

 

I am particularly pleased with the performance of our Hernic operation. The Hernic operation continues to set new benchmarks quarter on quarter with May setting a new record high delivering an impressive 2101 PGM ounces. At the current production rates we are expecting to increase the production of PGM ounces by more than 20% during Q2 2018 compared with Q1 2018.

 

We have awarded the transport contract to commence with the delivery of ourPlatCro PGM material to Northam Platinum for the recovery of the PGM's..

The construction of our Kabwe project is underway following the reinstatement of the mining licence by the Zambian authorities. Our initial focus is on the implementation of the zinc recovery circuit. I will provide further details and clarity on the project following my presentation to the Zambian Mining Department later this month.

 

At DCM we have commenced with the implementation of the hydro-mining circuit to replace the mechanical reclamation of the tailings material. This switch-over forms part of the installation of the integrated fine chrome recovery circuit which is the pre-cursor to the platinum recovery circuit at DCM."

 

 

 

 

Hernic Platinum and Chrome Operation (South Africa)

 

The production rate during the first two months of Q2 2018 continues to show a significant increase in PGM ounces compared with the previous quarter. Production during May 2018 has set a new record high for the operation of 2 101 ounces, an increase of 12% on the previous reported high. The ounces produced to date for Q2 2018 equals 3 972 with a target being set of 6 000 ounces for the full quarter (equates to a targeted growth of 22.5% quarter-on-quarter). The corresponding financial numbers for the quarter-to-date is yet to be finalised.

 

Production performance of the Hernic project for Q1 2018 and Q2 2018 month-to-date as follows:

 

 

Tailings processed Tonnes

PGM Ounces delivered*

 

 

 

Jan-18

26 073

1284

Feb-18

38 052

1755

Mar-18

46 284

1858

Q1 2018

110 409

4897

Apr-18

39 458

1871

May-18

39 734

2101

Jun-18

-

-

 Q2 2018**

79 192

3 972

 

 

 

Project to date

497 745

16305

*Ounces calculated based on assays received to date and subject to final metal accounting.

**Quarter 2 2018 numbers include only the months of April and May 2018.

 

PlatCro Platinum Project (South Africa)

 

Jubilee executed a processing agreement with Northam Platinum's Eland Platinum operation to process the PlatCro PGM material as announced in April 2018. The project targets the processing of 60 000 tonnes of PGM material per month equating to the production of approximately 2 800 PGM ounces per month. Jubilee has awarded the transport contract for the delivery of the PGM material and the first delivery to Northam is expected to commence during June 2018.

 

Kabwe Zinc, Lead and Vanadium Project (Zambia)

 

Our Jubilee and BMR teams are hard at work with the construction of the Kabwe project in Zambia. The initial construction focus is on the zinc primary leach recovery circuit.

 

The lead and vanadium project schedule will be concluded following completion of the circuit optimisation work currently undertaken by Jubilee. The circuit optimisation test work by Jubilee's research and development team includes work to evaluate the optimal product purity specifications. Further detail relating to the project's implementation schedule and design specifications will be provided following the presentation to the Zambian Mining Authorities during June 2018.

 

Clarification note on settlement of historical creditors by BMR Group PLC ("BMR")

 

Jubilee wishes to clarify the conditions under which Jubilee has agreed to allow BMR to allocate a portion of its existing holding of Jubilee shares to settle certain approved BMR creditors.

 

Under the agreement reached with BMR, such number of Jubilee shares as required to settle the approved creditors will be placed into a Jubilee nominated broker account ("transferred shares"). The transferred shares will be now be under Jubilee's control for onward placing to ensure orderly market conditions.

 

 

United Kingdom

7 June 2018

 Contacts

Jubilee Metals Group PLC

Colin Bird/Leon CoetzerTel +44 (0) 20 7584 2155 / Tel +27 (0) 11 465 1913Andrew SarosiTel +44 (0) 1752 221937

Nominated Adviser

SPARK Advisory Partners LimitedMark Brady/Andrew EmmottTel: +44 (0) 203 368 3555

Broker

Shard Capital Partners LLPDamon Heath/Erik WoolgarTel +44 (0) 20 7 186 9900

JSE Sponsor

Sasfin Capital (a member of the Sasfin group)

Sharon OwensTel +27 (0) 11 809 7500

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
DRLFKADKCBKDAAK
Date   Source Headline
21st Nov 20247:00 amRNSTR-1: notification of major holdings
20th Nov 20243:15 pmRNSExercise of Warrants
12th Nov 20242:20 pmRNSResult of AGM
7th Nov 20247:00 amRNSOperational Update Q1 FY2025
6th Nov 20242:30 pmRNSTR-1: Notification of major holdings
5th Nov 20247:00 amRNSAppointment of Remuneration Committee Chairperson
31st Oct 20247:00 amRNSBoard changes
16th Oct 20247:00 amRNSIntegrated Annual Report FY2024 & Notice of AGM
7th Oct 20247:00 amRNSNotice of Full Year Results Investor Presentation
7th Oct 20247:00 amRNSProject G Acquisition and Power Update
3rd Oct 20247:00 amRNSAudited Results for the year ended 30 June 2024
23rd Sep 20247:00 amRNSCopper Projects Update
19th Sep 20247:00 amRNSManagement changes
27th Aug 20247:00 amRNSPrivate Power Purchase Agreement in Zambia
21st Aug 20247:00 amRNSOperational Update Q4 FY2024
13th Aug 20247:00 amRNSRoan Front-End Module’s First Copper Concentrate
8th Aug 20247:30 amRNSRoan Upgrade Project Commences Operations
24th Jul 20241:00 pmRNSDirector/PDMR Shareholding
23rd Jul 20247:00 amRNSDirector/PDMR Shareholding
15th Jul 20247:00 amRNSChange of Broker
24th Jun 20247:00 amRNSRoll-out of Integrated Copper Strategy in Zambia
10th Jun 20242:10 pmRNSTR-1: Notification of major holdings
3rd Jun 20248:00 amRNSExercise of Warrants and Options
23rd Apr 20247:00 amRNSAppointment of Joint Corporate Broker
18th Apr 20247:00 amRNSOperational Update Q3 FY2024
28th Mar 20247:00 amRNSProjects Update
6th Mar 20243:00 pmRNSExercise of Options
6th Mar 20247:00 amRNSChanges to the Board & New Dedicated Exec Boards
29th Feb 20247:00 amRNSInterim Results 2023 Presentation
28th Feb 20249:31 amRNSInterim Results 2023 Presentation Re-scheduled
26th Feb 20247:00 amRNSInterim Financial Report 6 months to December 2023
8th Feb 20247:00 amRNSZambia Copper Expansion Update
23rd Jan 20247:00 amRNSOperational and Projects Update Q2 FY2024
4th Jan 20243:00 pmRNSTR-1: Notification of major holdings
3rd Jan 202412:00 pmRNSResults of General Meeting
15th Dec 20231:53 pmRNSResults of Placing and Notice of General Meeting
15th Dec 20237:00 amRNSProposed Placing
13th Dec 20232:30 pmRNSReply to Shareholder Correspondence Regarding a GM
12th Dec 20237:00 amRNSInvestment in Historical Waste Rock Dump in Zambia
21st Nov 20233:30 pmRNSInvestor Webcast
17th Nov 20237:00 amRNSNew Corporate Presentation
3rd Nov 20231:30 pmRNSResult of AGM
1st Nov 20237:05 amRNSQ1 Operational Report to 30 September 2023
17th Oct 20237:00 amRNSAward of New Slag Project with Mopani Copper Mines
11th Oct 20237:00 amRNSFinal Results and Notice of AGM
5th Oct 20237:00 amRNSNotice of Results
21st Aug 20237:00 amRNSSouth Africa and Zambia Project Expansion Update
14th Aug 20237:00 amRNSAppointment of CFO and Head of Energy Metals
20th Jul 20237:00 amRNSOperational Update for full year to 30 June 2023
6th Jun 20237:00 amRNSEXPANSION OF CHROME AND PGM FOOTPRINT

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.