Operations Update

9 Mar 2011 10:30

RNS Number : 6088C
Jubilee Platinum PLC
09 March 2011
 



 

AIM: JLP

JSE: JBL

Registration number: 4459850

ISIN GB0031852162

Jubilee Platinum PLC

("Jubilee" or the "Company")

Operations Update

 

Jubilee Platinum, the AIM and JSE quoted mine to metal specialist, is pleased to provide the following operations update.

 

HIGHLIGHTS

 

·; First stage infill drilling programme for the Tjate project completed with exceptional results achieved, final modelling of data in progress;

 

·; Drill data confirm continuity of Merensky and UG2 Reefs, with significantly improved grade and thickness for the UG2 reef;

 

·; Application for a Mining Right for Tjate initiated on these encouraging drilling results;

 

·; Delivery times for long-lead items successfully negotiated to ensure new ConRoast 5MW DC Arc furnace remains on track for Q4 2011;

 

·; Numerous small-scale near-term mining opportunities are being presented to Jubilee due to its ConRoast smelting capability to treat chrome bearing platinum concentrates;

 

·; Existing ferroalloys processing infrastructure at Middelburg fully utilised and contributing to short term cash flows;

 

·; New ferroalloy 5MW AC Arc furnace on target for commissioning in Q2 this year and capacity fully contracted; and

 

·; Drilling to commence shortly in Madagascar.

 

 

Leon Coetzer, CEO of Jubilee Platinum commented: "It is important to emphasise that we are developing a company capable of achieving a Mine to Metal business strategy. 

 

"The platinum ConRoast project is on track and will be operational by year end. The Tjate project's exceptional drill results again confirm it as a world-class asset and continue to present an excellent opportunity to develop a world-class platinum mine. I look forward to updating shareholders with regard to the Northam discussions and the Sylvania joint project as and when they conclude. The ferroalloy processing division is operating well and generating short term cash flow for the company. Its contribution to the overall business plan will increase with the commissioning of the first 5MW ferroalloy furnace in May this year.

 

"We continue to assess numerous small-scale near term mining opportunities, which are being presented to the Companydue to our ability to process platinum concentrates containing high chrome values.  These opportunities are in-line with our focus on building our Mine to Metal business strategy." 

 

Corporate developments

 

Discussions to establish a joint venture to evaluate the construction of a new DC Arc furnace facility using ConRoast technology to treat a portion of Northam Platinum's platinum group metal ("PGM") concentrate have advanced under the current Memorandum of Understanding, details of which, when concluded, will be released to the market.

 

The joint project with Sylvania Resources has progressed on schedule with all roasting and smelting trials concluded as specified within the scoping study. The PGM-rich iron alloy from these trials has been couriered to Canada for final CVMR refining trials. The results from these trials will form the basis of the scoping study.

 

Numerous small-scale near term, mining opportunities are being presented to Jubilee due to its ability to process platinum concentrates containing high chrome values. Jubilee is reviewing these opportunities to enable processing of own platinum concentrates through its Middelburg facility. Processing of own platinum concentrates significantly enhances the business model for Jubilee. Further detail on these opportunities will be released to the market on conclusion of the current review.

 

Middelburg Processing Facility

 

Jubilee has made significant progress in the implementation of its mine to metal business strategy. The Company is implementing two distinct business strategies at its Middelburg processing facility:

 

a platinum concentrate processing division operating under Braemore Platinum Smelters (Pty) Ltd, a wholly owned subsidiary of Jubilee; and

 

a ferroalloy processing division, operating under the company RST Metals (Pty) Ltd, a wholly owned subsidiary of Jubilee Smelting and Refining (Pty) Ltd (formerly Thos Begbie Holdings).

 

Platinum Concentrate Processing Division

 

Pyromet Tenova has been formally appointed to support Jubilee with the execution of the 5MW DC Arc Furnace for the ConRoast platinum project. Pyromet Tenova is an internationally recognised company specialising in the execution of pyrometallurgical (smelter) projects. The appointment falls in line with Jubilee's strategy of outsourcing specific technical roles to established industry leaders to enhance the Company's ability to execute the projects to set deliverables.

 

Improved delivery times for key items on the critical path of the ConRoast project have been successfully concluded to ensure the project remains on target and orders will be placed on receipt of written confirmation of these delivery times. Jubilee has concluded the submittal of all relevant environmental applications to ensure the project remains on track.

 

This 5MW ConRoast furnace forms part of the 2nd phase of the Middelburg facility expansion and is scheduled for completion towards the end of 2011. This facility continues to enjoy strong support from the industry.

 

Ferroalloy Processing Division

 

Jubilee has fully contracted the existing smelting capacity at Middelburg utilising the existing processing infrastructure - resulting in increased short-term cash flow. As such it is able to process various ferroalloys including ferronickel and ferrosilicon profitably while continuing with the expansion of the processing facility to include the ConRoast processing plant.

 

The current strong demand for the processing of ferroalloys, in particular ferronickel motivated the decision to construct a new 5MW ferroalloy AC Arc furnace at Middelburg. This builds upon the existing two 2.5MW AC Arc furnaces that are currently operational on site.

 

This 5 MW furnace will form part of the first phase of expansion at the Middelburg ferroalloy smelting facility with commissioning targeted in May 2011. This furnace will be an AC Arc furnace to capitalise on existing electrical infrastructure including available transformers, thereby avoiding the long delivery period associated with a DC Arc transformer.

  

Tjate Project

 

The Tjate project has completed its stage one infill drilling programme with results confirming the previous Merensky reef grades and showing an improvement in 4E (platinum palladium rhodium and gold) grade and reef thickness over that previously obtained for its UG2 reef.

 

During February 2011 the Company completed its first stage 9-borehole infill-drilling programme. The objective of this programme was to confirm the continuity of the Merensky and UG2 reef structures and to establish the drill spacing necessary to complete stage two of the drill programme so as to upgrade the resource estimate category. Five of the boreholes in this programme that were previously drilled to Merensky Reef were extended to UG2.

 

The results of this drilling are shown in the tables below with the weighted average results of previous drilling and all drilling to date.

 

Merensky Reef Infill Drilling Results

Merensky Best Mine Cut Average (80 cm cut-off)

Borehole

Cut Type

Ave 4E g/t

Ave Cu %

Ave Ni %

Ave Width m

DT43

Typical

3.51

0.14

0.24

1.06

DT44

Typical

4.79

0.16

0.27

0.83

DT45

Typical

4.36

0.09

0.15

2.25

DT46

Typical

3.63

0.13

0.21

1.05

DT47

Faulted/Disturbed

3.85

0.004

0.008

1.03

DT48

Typical

4.57

0.21

0.29

0.98

DT49

Typical

4.11

0.15

0.21

1.07

DT50

Typical

5.03

0.15

0.22

1.42

DT51

Typical

3.17

0.11

0.19

1.07

Weighted average Infill drilling

4.23

0.13

0.20

1.20

Previous drilling

4.24

0.11

0.19

1.15

All drilling to date

4.24

0.11

0.19

1.16

 

UG2 Infill Drilling Results

UG2 Cut Averages (Chromitite Only)

Borehole

Reef Type

Ave 4E g/t

Ave Cu %

Ave Ni %

Ave Width m

DT43

Normal

8.40

0.05

0.08

0.89

DT44

Normal

8.01

0.059

0.073

0.69

DT45

Normal

9.30

0.030

0.049

0.67

DT46

Normal

8.28

0.047

0.056

0.73

DT47

Normal

6.72

0.049

0.073

0.47

DT48

Normal

8.92

0.038

0.069

0.63

DT49

Normal

6.94

0.006

0.024

0.80

DT50

Normal

11.26

0.07

0.10

0.97

DT51

Normal

11.93

0.02

0.05

1.25

Weighted average Infill drilling

9.26

0.039

0.064

0.79

Previous drilling

8.35

0.045

0.078

0.60

All drilling to date

8.69

0.043

0.073

0.66

 

The average infill drilling Merensky results confirmed continuity of both the Merensky and the UG2 reefs. The Merensky results match the previous drilling results while the infill UG2 results show both improved average 4E grade (by approximately 0.9g/t 4E) and reef thickness over previous results.

The Company is encouraged by these results to date and has initiated preparation of an application to the Department of Mineral Resources ("DMR") for a Mining Right under the Mineral and Petroleum Resources Development Act 2002 for Tjate.

 

Independent mining industry consultant Snowden is currently modelling the data. These results and their impact on current resource estimate and drill spacing recommendation for stage two are expected to be reported shortly.

 

Phase two of Tjate's three-phase feasibility study is progressing to schedule and completion is targeted for end Q2.

 

Madagascar

 

The Company is shortly to commence exploratory drilling on its Ambodilafa concession located centrally in south-east Madagascar.

 

Andrew Sarosi, Director of Jubilee Platinum, who holds a B.Sc. Metallurgy and M.Sc. Engineering, University of Witwatersrand and is a member of The Institute of Materials, Minerals and Mining, is a 'qualified person' as defined under the AIM Rules for Companies and a competent person under the reporting standards. The technical parts of this announcement have been prepared under Andrew Sarosi's supervision and he has approved the release of this announcement.

 

 

Contacts

 

Colin Bird/Leon Coetzer

Jubilee Platinum plc

Tel +44 (0) 20 7584 2155 / Tel +27 (0)11 465 1913

 

Andrew Sarosi

Jubilee Platinum plc

Tel +44 (0) 1752 221937

Matthew Robinson/Rose Herbert - corporate finance

Joanna Weaving - corporate broking

finnCap Ltd

Tel +44 (0) 20 7600 1658

 

Leonard Eiser /Sharon Owens

Sasfin Capital

Tel +27 (0) 11 809 7500

 

Michael Kinirons/Nick Rome

Bishopsgate Communications Ltd

Tel +44 (0) 20 7562 3350

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCGMGGFGLDGMZM
Date   Source Headline
17th Dec 20187:00 amRNSCommissioning of fine chrome operation commences
10th Dec 20187:15 amRNSJubilee acquires major Chrome Processing Operation
6th Dec 20181:00 pmRNSResults of AGM
4th Dec 20187:02 amRNSSecond Price Monitoring Extn
4th Dec 20187:01 amRNSPrice Monitoring Extension
3rd Dec 20184:40 pmRNSSecond Price Monitoring Extn
3rd Dec 20184:35 pmRNSPrice Monitoring Extension
28th Nov 20181:30 pmRNSJubilee Live Interactive Webcast
14th Nov 20182:40 pmRNSAudited results for the year ended 30 June 2018
5th Nov 20188:00 amRNSMarket Update
17th Oct 20189:30 amRNSQuarterly Operations Update Q3 2018
3rd Aug 20187:00 amRNSClarification on BMR Group PLC & the Kabwe Project
19th Jul 20187:00 amRNSQuarterly Operations Update Q2 2018
2nd Jul 20187:00 amRNSKabwe Project Status Update
21st Jun 20183:00 pmRNSBoard Changes
12th Jun 20182:02 pmRNSTR-1: notification of major holdings
11th Jun 20188:30 amRNSPlacement of BMR Shares fully executed
7th Jun 20187:00 amRNSProjects Status Update
4th Jun 20189:15 amRNSKabwe and BMR Group PLC ("BMR") Update
2nd May 20187:00 amRNSJubilee Executes Kabwe Project Agreements
18th Apr 20187:00 amRNSJubilee Executes Processing Agreement
17th Apr 20187:00 amRNSQuarterly Operations Update & Tjate Share Issue
5th Apr 20187:00 amRNSKabwe Mining Licence Reinstated
29th Mar 201812:00 pmRNSFurther Kabwe Project Update
21st Mar 20187:00 amRNSAppointment of Broker
19th Mar 20181:45 pmRNSJubilee Live Interactive Webcast
7th Mar 20187:00 amRNSUNAUDITED INTERIM RESULTS 31 DECEMBER 2017
2nd Mar 201811:45 amRNSStatement regarding Broker
1st Mar 20187:00 amRNSFurther Kabwe Project Update
23rd Feb 20183:35 pmRNSFurther Kabwe Project Update
7th Feb 20185:00 pmRNSFurther Update re Kabwe project
7th Feb 20183:20 pmRNSUpdate on Kabwe project
6th Feb 20187:00 amRNSJubilee progresses Kabwe Project
5th Feb 20188:56 amRNSTR-1: notification of major holdings
1st Feb 201811:00 amRNSJubilee Live Interactive Webcast
30th Jan 20181:45 pmRNSQuarterly Operations Update
30th Jan 20188:00 amRNSTR-1: notification of major holdings
29th Jan 20184:48 pmRNSHolding(s) in Company
15th Jan 20181:00 pmRNSJubilee Acquires Significant Equity Position - BMR
9th Jan 20188:45 amRNSJubilee Secures Institutional Financing
5th Jan 20182:45 pmRNSJubilee Hernic PGM Project
5th Dec 20172:30 pmRNSChange of name to Jubilee Metals Group PLC
4th Dec 20173:10 pmRNSResults of AGM and Change of Name
20th Nov 20177:00 amRNSHernic Operations Update for October 2017
10th Nov 20177:00 amRNSNotice of AGM & Audited results for the year
26th Oct 20177:00 amRNSQuarterly Operations Update
23rd Oct 20177:00 amRNSJoint venture with BMR Group PLC
28th Sep 20177:00 amRNSHernic Update
7th Sep 20171:01 pmRNSJubilee Live Interactive Webcast - replacement
7th Sep 201710:15 amRNSJubilee Live Interactive Webcast

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.