Independent Oil and Gas plc

 

Operational Update

 

Independent Oil and Gas plc ("IOG" or "the Company"), (AIM: IOG.L), the development and production company focused on becoming a substantial UK gas producer, is pleased to provide an operational update for July 2020.

 

Platforms

· Fabrication of the Phase 1 Southwark and Blythe platforms continues to progress well, with a two-shift system remaining in place to manage Covid-19 restrictions

· Southwark cellar and sub-cellar decks have been fabricated and painted, with deck stacking expected early next week

· Southwark mezzanine and weather decks are on target for timely delivery by the sub-contractor, and jacket fabrication will also commence shortly

· Hydrate inhibitor tanks have been delivered and installation has commenced

· Crane pedestals have been built and delivered, and fabrication of helidecks and suction piles is also progressing well

· Formal platform contract award is expected imminently

 

SURF

· Detailed preparations for installation of Phase 1 pipelines and Elgood umbilical continue with Subsea 7 and supporting contractors

· Welding of 12-inch Blythe and 6-inch Elgood reel lay pipelines is underway at Subsea 7 spool base in Leith ahead of planned installation later this quarter

· Seabed survey for pipeline crossings completed in preparation for pipelay campaign

· 6km 24-inch pipeline extension from the Thames Pipeline to Southwark is expected to be installed in first half of 2021

· All associated regulatory consent processes ongoing, with permits for the 12-inch line being updated to align with latest crossing design and installation techniques

 

Drilling

· Competitive selection process for the jack-up rig for the five-well Phase 1 drilling programme has advanced to final post-tender technical and commercial clarifications, assisted by Petrofac

· Pre-Drill Data Packages for all wells are complete and detailed well design is progressing

· Several awards made and orders placed for critical drilling services and tangibles, and tender processes also underway for numerous others, including cementing, drilling & measurements, conductor/riser analysis, surface wellheads & trees and subsea wellhead tooling

· Pre-drill rig site survey for Elgood subsea well is underway and expected to complete this week

 

Onshore

· Engineering work and procurement is accelerating for the refurbishment of the Thames Reception Facilities ("TRF") at Bacton Gas Terminal ("BGT")

· Clean-out of the existing TRF slugcatchers is complete, with less than expected residues encountered, paving the way for full internal inspection in August

· Preparations are ongoing for tie-in activities during a scheduled BGT shutdown later this year

· Full suite of necessary commercial agreements with BGT operator Perenco UK Limited continues to be progressed

· IOG onshore team continues to optimise and adapt planned activities where necessary to work efficiently around the current Covid-19 restrictions at Bacton

 

Subsurface & Licences

· Seismic reprocessing to further improve subsurface imaging of the Vulcan Satellites area (Southwark, Nailsworth and Elland fields) is on track for completion by Q4 2020, in order to optimise field developments and well designs

· Harvey and Redwell seismic reprocessing is expected to provide updated volumetric estimates by Q4 2020, to support plans for high-return potential incremental developments

· Equivalent work on Goddard and Abbeydale assets also projected to complete in 1H 2021

· Final determination of Southwark, Blythe and Elgood fields confirmed by OGA

· Results of targeted applications for nearby blocks submitted in the 32nd UK Offshore Licence Round awaited from the Oil & Gas Authority (OGA) in due course

 

Andrew Hockey, CEO of IOG, commented: 

 

"I am pleased to provide this operational update to keep our investors informed on Phase 1 progress and wider business development. Amid the challenges of Covid-19 and the wider macroeconomic environment, the IOG team and our contractors and suppliers continue to work hard across the board to safely and efficiently execute the four key project elements - Platforms, SURF, Drilling and Onshore - and bring Phase 1 into production in Q3 2021. This in turn will catalyse our further value creation strategy, adding on higher-return incremental investments to our established infrastructure and using cost efficiencies to strengthen cash flows.

 

To that end, we are also making good progress with the seismic reprocessing work to advance our subsurface interpretations of all pre-development assets in the IOG portfolio, including Harvey, Redwell, Nailsworth, Elland, Goddard and Abbeydale. If successful, the additional nearby discovered resources that we have specifically targeted in our 32nd Round applications could also create further portfolio upside."

 

Certain information communicated in this announcement was, prior to its publication, inside information for the purposes of Article 7 of Regulation 596/2014.

Enquiries:

 

Independent Oil and Gas plc

Andrew Hockey (CEO)

Rupert Newall (CFO)

James Chance (Head of Corporate Finance & IR)

 

+44 (0) 20 7036 1400

finnCap Ltd

Christopher Raggett

Simon Hicks

 

+44 (0) 20 7220 0500

Peel Hunt LLP

Richard Crichton

David McKeown

 

+44 (0) 20 7418 8900

Vigo Communications

Patrick d'Ancona

Chris McMahon

Simon Woods

 

+44 (0) 20 7390 0230

About IOG:

 

IOG owns and operates a 50% stake in substantial low risk, high value gas reserves in the UK Southern North Sea. The Company's Core Project targets a gross 2P peak production rate of 140 MMcfe/d (c. 24,000 Boe/d) from gross 2P gas Reserves of 302 Bcfe¹ + 2C gas Contingent Resources of 108 Bcfe², via an efficient hub strategy. In addition to the independently verified 2P reserves at Blythe, Elgood, Southwark, Nailsworth and Elland and 2C Contingent Resources at Goddard, IOG also has independently verified best estimate gross unrisked prospective gas resources of 73 Bcfe² at Goddard. Alongside this IOG has management estimated mid-case recoverable gas volumes of 40 Bcfe and 100 Bcfe at the Harvey and Redwell licences and continues to pursue value accretive acquisitions to generate significant shareholder returns.

 

1ERC Equipoise Competent Persons Report: October 2017, adjusted by Management to account for updated project timing and compression

2ERC Equipoise Competent Persons Report: October 2018

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDWPUWAMUPUGBU
Date   Source Headline
27th Jun 20177:00 amRNSOGA SNS Tight Gas Strategy and New Presentation
8th Jun 20177:00 amRNSNotice of AGM and Issue of New Shares
31st May 20177:00 amRNSIssue of New Shares
26th May 20177:00 amRNSFinal Results for the Year Ended 31 December 2016
11th Apr 20177:00 amRNSAcquisition of SNS Pipeline
31st Mar 20177:00 amRNSExtension of pipeline MOU
27th Mar 20177:00 amRNSHarvey and Elgood licence Updates
21st Mar 20179:00 amRNSConversion of Salaries & Fees into Share Options
21st Mar 20177:00 amRNSDirectorate Change
1st Mar 201710:55 amRNSAcquisition of SNS Pipeline Update
1st Mar 20178:59 amRNSDirectorate Change
23rd Jan 201712:31 pmRNSConversion of Salaries and Fees into Share Options
16th Jan 20177:00 amRNSAcquisition of SNS Pipeline and Skipper Update
20th Dec 20167:00 amRNSIssue of New Shares
16th Dec 20167:00 amRNSSouthern North Sea Resources Increase
8th Dec 20167:00 amRNSExtension of the Blythe Licence
3rd Nov 20167:00 amRNSIssue of New Shares
1st Nov 20167:00 amRNSInitial Results of Seismic and Update on Cronx
28th Oct 20167:00 amRNSCompletion of Vulcan Satellites Acquisition
3rd Oct 20162:05 pmRNSSecond Price Monitoring Extn
3rd Oct 20162:00 pmRNSPrice Monitoring Extension
30th Sep 20167:00 amRNSInterim Results 2016
30th Sep 20167:00 amRNSInitial Skipper Appraisal Well Results
31st Aug 20167:00 amRNSResignation of Director
19th Aug 20167:00 amRNSCompletion of the Skipper Appraisal Well
17th Aug 20167:00 amRNSSkipper Well Update
29th Jul 20167:00 amRNSDirectorate Change
20th Jul 20162:00 pmRNSSkipper Update
14th Jul 20167:00 amRNSSkipper Update and Issue of New Shares
30th Jun 20167:00 amRNSResult of AGM and Skipper Appraisal Well Update
21st Jun 20167:00 amRNSCompletion of Blythe Acquisition
14th Jun 201610:44 amRNSIssue of New Shares
13th Jun 20167:00 amRNSAcquisition of Vulcan Satellites fields
7th Jun 20167:00 amRNSSkipper Appraisal Well rescheduled for July 2016
27th May 20167:00 amRNSAudited Results for the Year Ended 31 December 15
22nd Apr 20167:00 amRNSHolding(s) in Company
19th Apr 20168:00 amRNSConversion of Salaries and Fees into Share Options
19th Apr 20167:00 amRNSAcquisition of Blythe Discovery
30th Mar 20161:15 pmRNSPotential Acquisition Update
30th Mar 20167:00 amRNSFunding and Strategic Update
7th Mar 20169:23 amRNSIssue of New Shares
22nd Feb 201610:44 amRNSResult of General Meeting
5th Feb 201611:16 amRNSLoan Facility, Corporate Update and Board Changes
28th Jan 20167:00 amRNSExtension of Skipper Licence
18th Jan 20164:35 pmRNSPrice Monitoring Extension
13th Jan 20164:40 pmRNSSecond Price Monitoring Extn
13th Jan 20164:35 pmRNSPrice Monitoring Extension
13th Jan 20167:00 amRNSRescheduling of Skipper Well & Additional Funding
31st Dec 20157:00 amRNSCronx Licence Extension
29th Dec 20156:00 pmRNSResult of GM and Skipper Licence Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.